Yutong Xue1, Pengcheng Xiang1,2,3, Fuyuan Jia1, Zhaowen Liu4.
Abstract
Due to their characteristics and multiple objectives, high-speed rail (HSR) projects carry more complex risks than conventional projects and high correlation and conductivity are among the associated risk factors. Previous risk assessment frameworks for rail infrastructure have ignored the effects of risk interactions that inflate risk levels, namely, risk coupling effects. Based on a system dynamics method, this paper develops a risk coupling model for HSR project risk assessments. A risk factor list is established from a literature review, and relationships analysed using a case study and expert interviews. System dynamics equations are constructed and their parameters obtained by expert evaluations of risk factors. The proposed model is applied to a real-world HSR project to demonstrate it in detail. The model can evaluate the risk levels of HSR projects during a simulation period. In particular, it can identify the key coupling effects that are the main increased risk. It provides a significant resource, using which HSR project managers can identify and mitigate risks.Entities:
Keywords: dynamic risk; high-speed rail; risk assessment; risk coupling; risk interaction; system dynamics
Mesh:
Year: 2020 PMID: 32717994 PMCID: PMC7432577 DOI: 10.3390/ijerph17155307
Source DB: PubMed Journal: Int J Environ Res Public Health ISSN: 1660-4601 Impact factor: 3.390
High-speed rail (HSR) project risk subsystems, categories and factors, with the coding system used in subsequent analysis.
| Risk Subsystems | Risk Categories | Risk Factors |
|---|---|---|
| Vulnerability | Capital risk | Financing difficulty |
| Technical risk | Survey and design defects | |
| Management risk | Decision defect | |
| Threatening | Ecological risk | Regional ecosystem vulnerability |
| Economic risk | Unfavorable economic situation | |
| Social risk | War and riot | |
| Strong public interest appeals |
General risk assessment methods in construction projects.
| Reference | Method | Features and Advantages | Limitations |
|---|---|---|---|
| [ | Analytic hierarchy process | The comprehensive importance of each level factor can be obtained, making it suitable for decision-making in complex systems with multiple objectives, levels and factors. | The data is subjective and not always convincing enough, and new decision-making options are not available. |
| [ | Fuzzy comprehensive evaluation | Based on the theory of fuzzy mathematics, multi-layer operations are run to determine the risk level of the project. It is suitable for the evaluation of fuzzy or qualitative risks. | The determination of factor weights is subjective and not convincing enough. |
| [ | Delphi | Semi-structured questionnaires on risk are sent to a group of experts for multiple rounds until a reliable consensus is reached. Used for problems that are difficult to handle by other methods. | The results depend largely on the experts’ qualifications and number. |
| [ | Monte Carlo simulation | A risk structure is established and the mathematical relationships between risk variables are expressed by a Bayesian formula. Applicable to problems with obvious causality between risks. | Large amounts of high-quality data are required to obtain a convincing risk structure and conditional risk probability distributions. |
| [ | Bayesian network | The risk structure is established and the mathematical relationship between risk variables is expressed by Bayesian formula. It is applicable to the problems with obvious causality between risks. | Large amounts and high-quality data are required to obtain a convincing risk structure and conditional probability distributions of risks. |
| [ | Interpretative structural modeling | An adjacency matrix is used to study the interactions between risks and establish a risk structure. Risks can be divided into several categories according to the type and intensity of their interactions. | Only suitable for qualitative risk analysis. Quantitative evaluations cannot be obtained. |
| [ | System dynamics | A complex system with multiple variables and nonlinear characteristics can be constructed and predicted dynamically, and the interactions of the system’s components can be represented quantitatively. | It is difficult to construct a suitable dynamic model of a complex system. |
| [ | N-K model | The current status of a complex system and the effects of the interactions between different components can be analyzed quantitatively. | A large amount of complete historical data is required, and the future situation cannot be predicted. |
Figure 1Research framework.
Figure 2Schematic diagram of coupled risk relationships in high-speed rail (HSR) projects.
Figure 3Risk coupling in the vulnerability risk subsystem.
Figure 4Risk coupling in the threatening risk subsystem.
Risk coupling between the vulnerability and threatening risk subsystems.
| Case Description | Causal Relationship of Risk Factors | Direction of Risk Coupling |
|---|---|---|
| Beijing-Shanghai high-speed rail (HSR) passes through the Ming Mausoleum (a key national heritage conservation unit) and crosses Yangcheng Lake Ecological Area (an ecological protection zone). In order to defend the integrity of the sites and reduce water pollution, the original design and construction scheme of the project has been modified. The new scheme increased the length of the bridge by 5931 m and the main engineering cost increased by 29.02 million yuan. The major changes to the project have caused great financial stress for its investors. | Nature reserves and historic reservation | Ecological risk |
| During the construction of the Beijing-Shanghai HSR, costs increased significantly due to high inflation. Owing to the large amount of project loans, long construction period and rising interest rate, the debt burdens of the Ministry of Railways and of local governments increased. For example, 80.8% of the lines have used viaduct technology, for which the cost per km is 20–30 million yuan higher than that of ordinary subgrade. Half of this investment is financed by bank loans. Even if the minimum interest rate of syndicated loans at that time was 5.5%, the annual interest expense would be 6.05 billion yuan. | Unfavorable economic situation | Economic risk |
| Poor geological engineering conditions along the Beijing-Shanghai HSR, mainly manifested as soft soil, make its construction difficult. | Complex hydrological, geological, and meteorological conditions | Ecological risk |
| During the construction of the Beijing-Shanghai HSR, the design institutes did not complete the design work in time according to the environmental impact assessment (EIA) document, which affected the implementation of the environmental protection measures. Additionally, the construction enterprises did not carry out unified treatment of waste soil according to their contracts, instead using it to fill ponds and mountain gullies, thus causing air and water pollution, which is harmful to the local water and soil environments. | Corporate defaults | Management risk |
| Due to a lack of public participation in the HSR planning system during the planning of the Shanghai-Wuhan-Chengdu HSR and Shanghai-Kunming HSR, members of the public spontaneously gathered for demonstrations and caused mass incidents to express their strong appeal for the implementation of HSR transit in their areas. | Decision defect | Management risk |
| During the planning of the Dazhou-Chongqing HSR, there was a dispute between the East Line and West Line, which caused local governments to compete for the project. Among them, the governments of Dazhou and Guang’an made different statements regarding the line chosen for HSR on their information websites, which aroused dissatisfaction and strong appeals from the public. | Conflicts of interest | Management risk |
| Due to the continental plate on which Indonesia is located, earthquakes and volcanic eruptions are frequent. Indonesia’s Ministry of Transport have stressed twice that, if earthquake resistance requirements cannot be met, construction of the Jakarta-Bandung HSR project will not be permitted. Such natural disasters pose challenges to existing design and construction technology. | Natural disasters | Ecological risk |
| Compensation for land acquired for the Zhengzhou-Xuzhou HSR was embezzled by local officials. Because the compensation did not meet state standards, this hurt the interests of the people and resulted in petitions. | Corruption and bribery | Capital risk |
| As local people may lack the capacity and willingness to pay for tickets, only about 30 pairs of HSR Electric Multiple Units (EMUs) of Zhengzhou-Xi’an HSR operates every day, with an attendance rate of less than 50%. After two years’ operation, in 2016, this HSR line lost 1.4 billion yuan, leaving the Zhengzhou Railway Bureau at a loss of 1 billion yuan. | Lower-level regional economy development | Economic risk |
| A serious epidemic influenced the macro-economies of various countries. Basic economic activity nearly collapsed and market demand for HSR was almost non-existent. The volume of passenger traffic in the Beijing-Shenyang HSR was less than 10%, and ticket revenue could not support the high operating cost. | Unfavorable economic situation | Economic risk |
| The Fujian section of the Ganzhou-Longyan HSR is located in the mountains of Northwest Fujian. Carbonate rock and karst are widely distributed, and the erosional surface is dissected deeply by valleys. It is difficult to carry out accurate surveys, resulting in the hidden danger of engineering design defects. | Complex hydrological, geological, and meteorological conditions | Ecological risk |
| China Railway Corporation’s financial report shows that, up to September 2018, the company’s debt was 5.28 trillion yuan, which is mainly borne by the Railway Bureau and local governments. Experts have stated that once the debt risk is out of control, it may cause systemic financial risk. | Government debt | Capital risk |
| The California HSR project is located on the Pacific Plate, which has high seismic activity. Generally speaking, HSR needs rigid structures to meet strict limits of deflection and vibration control. However, in earthquake areas, flexible and ductile structures are more earthquake-proof, which brings additional challenges to the designers and constructors of this project. | Natural disasters | Ecological risk |
Figure 5Causality diagram of risk couplings in the high-speed rail (HSR) project. Black lines represent couplings in the vulnerability risk subsystem, blue lines represent them in the threatening risk subsystem, and red lines represent the couplings between risk subsystems. The gray variables are used as the shadow variables of their corresponding black variables to keep the structure concise. They have the same function as their corresponding black variables.
Figure 6Flow-stock diagram of risk coupling in high-speed rail (HSR) projects. The gray variables are used as the shadow variables of their corresponding black variables to keep the structure concise. They have the same function as their corresponding black variables.
Weights of risk indicators.
| Target Layer Indicator | Standard Layer | Field Layer Indicators | Index Layer | Mean Value |
Absolute Weights of
| Relative Weights of |
|---|---|---|---|---|---|---|
| Risk of HSR project | Vulnerability risk | Capitalrisk | Financing difficulty | 4.125 | 0.055 | 0.266 |
| Poor profitability | 3.267 | 0.044 | 0.212 | |||
| Government debt | 3.625 | 0.049 | 0.237 | |||
| Corruption and bribery | 4.400 | 0.059 | 0.285 | |||
| Technical risk | Survey and design defects | 4.400 | 0.059 | 0.328 | ||
| Technical complexity | 3.500 | 0.047 | 0.261 | |||
| Different technical standard | 3.267 | 0.044 | 0.244 | |||
| Inadequate safety protection | 2.215 | 0.030 | 0.167 | |||
| Management risk | Decision defect | 3.625 | 0.049 | 0.295 | ||
| Conflicts of interest | 3.375 | 0.045 | 0.271 | |||
| Insufficient member ability | 2.250 | 0.030 | 0.181 | |||
| Corporate defaults | 3.125 | 0.042 | 0.253 | |||
| Threatening risk | Ecological risk | Regional ecosystem vulnerability | 3.533 | 0.047 | 0.324 | |
| Complex hydrological, geological, and meteorological conditions | 3.067 | 0.041 | 0.283 | |||
| Natural disasters | 2.375 | 0.032 | 0.221 | |||
| Nature reserves and historic reservations | 1.875 | 0.025 | 0.172 | |||
| Economic risk | Unfavorable economic situation | 3.667 | 0.049 | 0.32 | ||
| Unbalanced development of regional economy | 2.375 | 0.032 | 0.209 | |||
| Alternative transportation facilities | 2.215 | 0.030 | 0.196 | |||
| Lower-level regional economy development | 3.133 | 0.042 | 0.275 | |||
| Social risk | War and riot | 2.533 | 0.034 | 0.228 | ||
| Difficulties in land acquisition, demolition and resettlement | 4.000 | 0.054 | 0.362 | |||
| Strong public interest appeals | 1.750 | 0.024 | 0.161 | |||
| Public sensitivity to pollution | 2.750 | 0.037 | 0.249 |
Risk value classification.
| Risk Value | 0.1 | 0.3 | 0.5 | 0.7 | 0.9 |
|---|---|---|---|---|---|
| Degree of impact | Negligible | Low | Medium | Serious | Very serious |
Values of risk factors in the Zhengzhou-Wanzhou (ZW) high-speed rail (HSR) project.
| Risk Factor | Risk Value | Risk Factor | Risk Value |
|---|---|---|---|
| Financing difficulty | 0.77 | Regional ecosystem vulnerability | 0.64 |
| Poor profitability | 0.75 | Complex hydrological, geological, and meteorological conditions | 0.76 |
| Government debt | 0.67 | Natural disasters | 0.54 |
| Corruption and bribery | 0.67 | Nature reserves and historic reservations | 0.23 |
| Survey and design defects | 0.60 | Unfavorable economic situation | 0.45 |
| Technical complexity | 0.90 | Unbalanced development of regional economy | 0.31 |
| Different technical standard | 0.19 | Alternative transportation facilities | 0.29 |
| Inadequate safety protection | 0.42 | Lower-level regional economy development | 0.41 |
| Decision defect | 0.79 | War and riot | 0.26 |
| Conflicts of interest | 0.84 | Difficulties in land acquisition, demolition and resettlement | 0.51 |
| Insufficient member ability | 0.60 | Strong public interest appeals | 0.48 |
| Corporate defaults | 0.85 | Public sensitivity to pollution | 0.35 |
Coupling coefficients of Zhengzhou-Wanzhou (ZW) high-speed rail (HSR) project risk factors.
| Coupled Risk Factors | Coupling Coefficient | Coupled Risk Factors | Coupling Coefficient |
|---|---|---|---|
| CV11-V14 | 0.976 | CV31-V33 | 0.910 |
| CV11-T14 | 0.178 | CV31-V14 | 0.166 |
| CV11-V22 | 0.966 | CV32-V31 | 0.995 |
| CV11-V12 | 0.999 | CV33-V11 | 0.925 |
| CV12-T24 | 0.428 | CV33-V22 | 0.806 |
| CV12-T21 | 0.940 | CV33-T13 | 0.986 |
| CV13-V12 | 0.984 | CV34-V32 | 0.839 |
| CV13-T21 | 0.821 | CT11-V33 | 0.794 |
| CV14-V34 | 0.932 | CT11-T13 | 0.965 |
| CV21-T12 | 0.933 | CT13-T12 | 0.865 |
| CV22-V23 | 0.061 | CT21-V13 | 0.821 |
| CV22-V21 | 0.806 | CT21-T13 | 0.959 |
| CV22-T12 | 0.960 | CT23-T24 | 0.861 |
| CV22-T13 | 0.714 | CT32-T31 | 0.573 |
| CV24-V21 | 0.854 | CT32-V14 | 0.911 |
| CV24-V22 | 0.482 | CT33-V31 | 0.736 |
| CV24-V31 | 0.612 | CT34-T11 | 0.639 |
| CV24-V33 | 0.854 | CT21-T31 | 0.690 |
| CT33-V32 | 0.679 | - | - |
The risk standard of Zhengzhou-Wanzhou (ZW) high-speed rail (HSR) project.
| Risk Rating | Interval of Risk Level | Specified Interval Value of Risk Level | Risk Management Principle |
|---|---|---|---|
| V | (0, 20%) | (3.75, 9.55) | There are acceptable minor risks and the project can be carried out normally |
| IV | (20%, 40%) | (9.55, 15.36) | There are general risks that should be attended to |
| III | (40%, 60%) | (15.36, 21.16) | There are obvious risks and mitigation measures should be taken |
| II | (60%, 80%) | (21.16, 26.96) | The project is highly risky and needs to be modified immediately |
| I | (80%, 100%) | (26.96, 32.7) | The project is extremely risky and needs to be suspended, with risk control measures implemented immediately |
Figure 7The total risk level of the Zhengzhou-Wanzhou (ZW) high-speed rail (HSR) project.
Figure 8Field risk levels of the Zhengzhou-Wanzhou (ZW) high-speed rail (HSR) project.
Figure 9Risk levels of management and capital risk factors.
Figure 10Models of homogeneous risk coupling effects.
Figure 11Coupling effects of homogeneous vulnerability risk pairs.
Figure 12Models of heterogeneous risk coupling effects.
Figure 13Coupling effects of heterogeneous vulnerability risk pairs.
Figure 14Coupling effects of heterogeneous vulnerability-threatening risk pairs.