| Literature DB >> 35863774 |
Michael Pridgeon1, Nathan Proudlove2.
Abstract
At the Walton Centre we conduct a relatively large number of complex and lengthy elective (booked) spinal operations. Recently, we have had a particular problem with half or more of these sessions finishing late, resulting in staff discontent and greater use of on-call staff.These operations require patient monitoring by neurophysiology clinical scientists. Before the surgeon can start the operation, in-theatre neurophysiological measurements are required to establish a baseline. We reasoned that reducing this set-up time would reduce the risk of surgery starting late, and so the whole session finishing later than expected.In this project we redesigned the neurophysiology parts of in-theatre patient preparation. We conducted five Plan-Do-Study-Act cycles over 3 months, reducing the duration of pre-surgery preparation from a mean of 70 min to around 50 min. We saw improvements in surgical start times and session finish times (both earlier by roughly comparable amounts). The ultimately impact is that we saw on-time session finishes improve from around 50% to 100%. Following this project, we have managed to sustain the changes and the improved performance.The most impactful change was to conduct in-theatre neurophysiology patient preparation simultaneously with anaesthesia, rather than waiting for this to finish; when we performed this with a pair of clinical scientists, we were able to complete neurophysiology patient preparation by the time the anaesthetist was finished, therefore not introducing delays to the start of surgery. A final change was to remove a superfluous preparatory patient-baseline measurement.This is a very challenging and complex environment, with powerful stakeholders and many factors and unpredictable events affecting sessions. Nevertheless, we have shown that we can make improvements within our span of influence that improve the wider process. While using pairs of staff requires greater resource, we found the benefit to be worthwhile. © Author(s) (or their employer(s)) 2022. Re-use permitted under CC BY-NC. No commercial re-use. See rights and permissions. Published by BMJ.Entities:
Keywords: Control charts/Run charts; PDSA; Preoperative Care; Surgery
Mesh:
Year: 2022 PMID: 35863774 PMCID: PMC9310250 DOI: 10.1136/bmjoq-2021-001808
Source DB: PubMed Journal: BMJ Open Qual ISSN: 2399-6641
Figure 1‘As-is’ process map, focusing on the neurophysiology input to the process. It shows value (green) and waste (red) steps, problems identified and metrics used in this project. BM, balancing metric; MEP, motor evoked potential; OM, outcome metric; PDSA, Plan-Do-Study-Act; PM, process metric; SSEP, somatosensory evoked potential.
Figure 2Main performance metrics over baseline and five cycles of Plan-Do-Study-Act (A1 to C). OM, outcome metric; PM, process metric.
Improvement cycles
| PDSA cycle | Plan/prediction | Do | Study | Act |
|
| If cases planned and leave dept at 8:30 (instead of waiting to be contacted) then | 10 May 2021. | OM1: ☒ 30% of cases finished on time (worse!). | OM1: ‘Long’ case consistently finish after their planned finish time. |
|
| If have done head measurement on the ward and leave earlier (08:15) then | 1 June 2021. | OM1: ☒ 70% finished on time. | Conclude: attendance |
|
| If simultaneous NP set-up with anaesthesia, then reduce pre-surgery delays, so PM2, PM3 and OMs. | 24 June 2021. | OM1: ☒ 60% finished on time. | Long cases still problematic. |
|
| If NP set-up in pairs then NP duration ≤anaesthesia duration: PM2 reduced, so PM3 and OM1 reduced. | 20 July 2021. | OM1: ☑ 100%. All cases finished within planned finish time. | Setting up in pairs has a significant impact on PM2: 40% cases within target, but still >target (45 min). |
|
| If we only perform prone intraoperative baselines, we can remove duplication from the system. | 11August 2021. | OM1: ☑ 100%. All cases finished on time again. | Removing baseline duplication within the system significantly improved PM2 and PM3 (now capable of meeting target). |
☑: Target met; ☒: Target not met.
BM, balancing metric; CC, common cause (ie, random) variation; L, long; M, medium-length; NP, neurophysiology; OM, outcome metric; PM, process metric; S, planned (relatively) short duration operations; SC, special cause variation; UPL, upper process limit (also known as upper control limit); WA, theatre waiting area.