| Literature DB >> 35368528 |
Shitaw Tafesse1, Yidnekachew Esayas Girma1, Eliyas Dessalegn1.
Abstract
This study aims to analyze the significant socioeconomic and environmental impacts of construction waste and to indicate management strategies. An extensive review of the literature and interviews with construction experts were used to identify waste impact factors. Then a questionnaire survey was conducted based on a five-point Likert scale and the data were analyzed by descriptive statistics. The result showed that construction waste becomes a challenge for almost 95.71% of ongoing construction projects. However, only 57.14% of the construction companies have recorded and measured the volume of material waste. From purchased materials, 6-10% is recorded as waste that lead to project cost overrun. In addition, there is no professional assigned to handle waste issues in 75.71% of construction companies. The study also indicates that project cost overrun, pollution of the environment, reduction in profit and failure of construction firms, excessive consumption of raw materials, and public health and safety risks are ranked as the five major impacts of construction waste, respectively. Employing a waste management officer, using prefabricated or off-site components, implementing strong onsite management practices, reusing and recycling materials leftover on the sites, and practicing green building codes and specifications are measures devised to mitigate construction waste and its impacts.Entities:
Keywords: Construction waste; Environment; Impact of waste; Sustainability; Waste management
Year: 2022 PMID: 35368528 PMCID: PMC8971575 DOI: 10.1016/j.heliyon.2022.e09169
Source DB: PubMed Journal: Heliyon ISSN: 2405-8440
Figure 1Waste of construction materials (authors field observation).
Impact factors of construction waste.
| No. | Impacts of construction wastes | Reference/Source |
|---|---|---|
| 1 | Project cost overrun | |
| 2 | Disease-associated with high levels of air pollutants | |
| 3 | Pollution of the environment by discharging chemicals and other materials | |
| 4 | Reduction in profit and failure of construction firms | |
| 5 | Lower the GDP contribution of construction firms | |
| 6 | Excessive consumption of raw material and resources depletion | |
| 7 | Public health and safety risks | |
| 8 | Pollution of soil by chemicals and other materials | |
| 9 | Delay of project time or time overrun | |
| 10 | Sustainability reduction of construction sectors | |
| 11 | Land occupancy or land consumption for dumping wastes | |
| 12 | Traffic congestion | |
| 13 | Generate waste that causes water pollution | |
| 14 | Effect on biodiversity and destruction of the living environment | |
| 15 | Severe effects on the welfare of the waste disposed of communities | |
| 16 | Emission of greenhouse gases into the atmosphere causes climate change | |
| 17 | Dust generation to the surrounding | |
| 18 | Flooding due to blockages by waste debris | |
| 19 | Increase in illegal dumping | |
| 20 | Reduce agricultural productivity | |
| 21 | Spending costs to landfill fee for disposing of wastes | Interview/pilot survey |
| 22 | Transportation charges to transport wastes | Interview/pilot survey |
| 23 | Increase price of raw materials | Interview/pilot survey |
| 24 | Disagreement between construction stakeholders | Interview/pilot survey |
| 25 | Losing reputability and caused conflicts with the community | Interview/pilot survey |
Figure 2Flow chart of the research.
Descriptive statistics and normality test of the collected data.
| S.No. | Impacts of construction waste | Mean | Std. Deviation | Rank | Cronbach's alpha if item deleted a∗∗ | Kolmogorov-Smirnov test | ||
|---|---|---|---|---|---|---|---|---|
| Statistic | df | Sig. | ||||||
| EC1 | Project cost overrun | 4.21 | .931 | 1 | .953 | .272 | 70 | .000 |
| EN1 | Pollution of the environment by discharging chemicals and other materials | 4.14 | .967 | 2 | .953 | .284 | 70 | .000 |
| EC2 | Reduction in Profit and failure of construction firms | 4.00 | 1.090 | 3 | .956 | .271 | 70 | .000 |
| EN2 | Excessive consumption of raw material and resources depletion | 3.99 | 1.210 | 4 | .955 | .256 | 70 | .000 |
| SE1 | Public health and safety risks | 3.97 | 1.179 | 5 | .952 | .238 | 70 | .000 |
| EN3 | Pollution of soil by chemicals and other materials | 3.93 | 1.121 | 6 | .952 | .240 | 70 | .000 |
| EC3 | Delay of project time or time overrun | 3.91 | 1.100 | 7 | .952 | .274 | 70 | .000 |
| EC4 | Spending costs to landfill fee for disposing of waste | 3.90 | 1.079 | 8 | .952 | .223 | 70 | .000 |
| EN4 | Sustainability reduction of construction sectors | 3.87 | 1.006 | 9 | .956 | .237 | 70 | .000 |
| EN5 | Generate waste that causes water pollution | 3.83 | 1.239 | 10 | .952 | .269 | 70 | .000 |
| EN6 | Land occupancy or land consumption for dumping waste | 3.81 | .997 | 11 | .956 | .188 | 70 | .000 |
| SE2 | Traffic congestion | 3.79 | 1.034 | 12 | .953 | .194 | 70 | .000 |
| EC5 | Transportation charges to transport waste | 3.77 | 1.253 | 13 | .953 | .208 | 70 | .000 |
| EN7 | Effect on biodiversity and destruction of the living environment | 3.76 | 1.233 | 14 | .952 | .207 | 70 | .000 |
| EC6 | Lower the GDP contribution of construction firms | 3.74 | 1.359 | 15 | .953 | .275 | 70 | .000 |
| SE3 | Disease-associated with high levels of air pollutants | 3.73 | 1.350 | 16 | .956 | .251 | 70 | .000 |
| EN8 | Severe effects on the welfare of the waste disposed communities | 3.67 | 1.176 | 17 | .954 | .210 | 70 | .000 |
| EC7 | Increase price of raw materials | 3.66 | 1.361 | 18 | .952 | .257 | 70 | .000 |
| EN9 | Emission of greenhouse gases into the atmosphere causes climate change | 3.61 | 1.487 | 19 | .954 | .288 | 70 | .000 |
| .958 | .231 | 70 | .000 | |||||
| EN11 | Dust generation to the surrounding | 3.47 | 1.411 | 20 | .954 | .217 | 70 | .000 |
| SE4 | Flooding due to blockages by waste debris | 3.43 | 1.420 | 21 | .953 | .256 | 70 | .000 |
| SE5 | Disagreement between construction parties | 3.40 | 1.232 | 22 | .953 | .158 | 70 | .000 |
| SE6 | Losing reputability and caused conflicts with the community | 3.37 | 1.374 | 23 | 0.56 | .176 | 70 | .000 |
| EC8 | Reduce the crop productivity | 3.21 | 1.371 | 24 | .954 | .181 | 70 | .000 |
a∗∗; Overall Cronbach's alpha coefficient is 0.956.
b∗∗∗; Item was removed because it does not contribute to the overall reliability.
EC; economic impacts, SE; social impacts, and EN are environmental impacts of construction waste.
Characteristics of the study respondents.
| Characteristics of respondents | Frequency | Percentage (%) | Characteristics of respondents | Frequency | Percentage (%) |
|---|---|---|---|---|---|
| Contractor | 34 | 49 | Site engineer | 20 | 28.57 |
| Consultant | 24 | 34 | Office engineer | 16 | 22.86 |
| Client | 12 | 17 | Project manager | 7 | 10 |
| Quantity surveyor | 7 | 10 | |||
| 1–5 year | 19 | 27.14 | Resident engineer | 4 | 5.78 |
| 6–10 year | 22 | 31.42 | Site supervisor | 4 | 5.78 |
| 11–15 year | 18 | 25.72 | General formal | 3 | 4.29 |
| ≥16 year | 11 | 15.72 | Counterpart engineer | 2 | 2.86 |
| Designer | 2 | 2.86 | |||
| 1–5 year | 31 | 44.29 | Architect | 2 | 2.86 |
| 6–10 year | 30 | 42.86 | Contract administer | 2 | 2.86 |
| 11–15 year | 5 | 7.14 | Design and supervision department manager | 1 | 1.43 |
| ≥16 year | 4 | 5.71 | |||
Level of the agreement of respondents on the existence of material waste.
| Level of respondent responses | Contractors | Consultants | Clients | Overall | ||||
|---|---|---|---|---|---|---|---|---|
| Frequency | Percent | Frequency | Percent | Frequency | Percent | Frequency | Percent | |
| Strongly agree | 13 | 38.2 | 12 | 50 | 7 | 58.33 | 32 | 45.71 |
| Agree | 15 | 44.1 | 9 | 37.5 | 4 | 33.33 | 28 | 40 |
| Moderately agree | 4 | 11.8 | 2 | 8.33 | 1 | 8.33 | 7 | 10 |
| Disagree | 0 | 0 | 1 | 4.17 | 0 | 0 | 1 | 1.43 |
| Strongly disagree | 2 | 5.9 | 0 | 0 | 0 | 0 | 2 | 2.86 |
| Total | 34 | 100.0 | 24 | 100 | 12 | 100 | 70 | 100 |
Figure 3The record of waste, its cost overrun, and waste management professionals.
Figure 4Cost overrun due to construction material waste.
Implementation of waste management strategies.
| Response | Frequency | Percentage (%) |
|---|---|---|
| Yes | 32 | 45.71 |
| No | 38 | 54.29 |
| Total | 70 | 100 |
Construction waste management practices.
| No. Waste management practices |
|---|
| 1. Employing a specific professionals to inspect and handle construction waste related issues |
| 2. Adoption of prefabricated or off-site production of components and recent technology products which enable to reduce construction waste |
| 3. Strong coordination between consultant, client, contractors, and other stakeholders during the planning, design, and construction stages of projects. |
| 4. Implement strong onsite management practice and create awareness among the construction work members |
| 5. Reusing and recycling the material leftover on sites |
| 6. Offer incentives and tender premiums related to waste management |
| 7. Increased implementation of green building codes and specifications |
| 8. Introduction of penalties for construction firms with poor waste management practices |
| 9. Increased landfill charges |
| 10. Incorporation of a material waste minimization plan policy in construction contracts |
| 11. Measuring the size of the work and using the proper amount of material on site help to reduce the work item needed to rework, repair and replace. |
| 12. Enhancing proper material storage, effective and frequent site supervision |
| 13. Taking into account the environment during designing and aiming to achieve resource optimization |
| 14. Providing scheduled training on material waste minimization strategies for construction workers |
| 15. Keep in mind the economic, social, and environmental effects of waste at all stages of the project |