| Literature DB >> 33981889 |
Adebayo Adeboye Fashina1, Mustafe Abdillahi Omar2, Ahmed Abdullahi Sheikh3, Funke Folasade Fakunle4.
Abstract
Over the past decades, construction delays have been perceived as a global challenge that hinders the time delivery, budget, and quality of construction projects. It is the most common, expensive, and risky problem associated with both private and public construction projects. Within this context, the aim of this study is to investigate the significant factors that influence delays in construction projects in Hargeisa, using the road and building projects as a baseline. Through a questionnaire survey with 51 critical delay factors that are categorized into seven major groups, data were collected from 51 construction stakeholders selected based on simple random sampling from the different construction companies. Feedback from the respondents was analyzed using Relative Importance Index (RII) for ranking purposes. Results showed that delay in honoring payment progressively, underestimation or overestimation of the project cost, and delay in the approval of major changes in the work scope were ranked as the three major causes of delays in construction projects in Hargeisa. The implications of these results are vital to future projects as they clearly demonstrate how less attention is given to the application of project management tools such as robust cost, scope and risk management in construction projects. As such, construction stakeholders are recommended to make efforts to use the appropriate project management practices needed to manage the 16 identified critical delay factors, when executing future construction projects. Although, the current study focused on Somaliland construction projects, it expands and improves the understanding of delay factors in the global context, and as such can be applied to other countries and future studies.Entities:
Keywords: Construction delays; Construction projects; Hargeisa; Project management; Road and building projects
Year: 2021 PMID: 33981889 PMCID: PMC8085700 DOI: 10.1016/j.heliyon.2021.e06826
Source DB: PubMed Journal: Heliyon ISSN: 2405-8440
Internal consistency of Cronbach's Alpha (Gliem and Gliem, 2003).
| S/N | Cronbach's alpha, α | Internal consistency |
|---|---|---|
| 1 | α ≥ 0.8 | Excellent |
| 2 | 0.8 > α ≥ 0.7 | Good |
| 3 | 0.7 > α ≥ 0.5 | Satisfactory |
| 4 | α < 0.5 | Poor |
The results of the Cronbach's Alpha reliability test for the seven categories of the causes of delay.
| Factors | Numbers of questions | Cronbach's alpha | Internal consistency |
|---|---|---|---|
| Owner | 12 | 0.827 | Excellent |
| Contractor | 11 | 0.813 | Excellent |
| Consultant | 8 | 0.720 | Good |
| Labor | 4 | 0.550 | Satisfactory |
| Material | 6 | 0.694 | Satisfactory |
| Equipment | 4 | 0.737 | Good |
| External Factors | 6 | 0.730 | Good |
Classification of RII.
| Scale | Level of contribution | RII |
|---|---|---|
| 1 | Very low | 0.0 ≤ RII ≤ 0.2 |
| 2 | Low | 0.2 < RII ≤ 0.4 |
| 3 | Average | 0.4 < RII ≤ 0.6 |
| 4 | High | 0.6 < RII ≤ 0.8 |
| 5 | Very high | 0.8 < RII ≤ 1.0 |
RII ranking for Clients/Owners-related delay factors.
| S/N | Owner-related causes of delay | RII | RII ranking | Level of contribution |
|---|---|---|---|---|
| 1 | Delay in honoring payment progressively | 0.846 | 1 | Very high |
| 2 | Delay in the provision or delivery of project site | 0.742 | 4 | High |
| 3 | Slow decision-making process | 0.658 | 9 | High |
| 4 | Errors in design and specifications | 0.696 | 7 | High |
| 5 | Lateness in the revision and approval of design documents | 0.729 | 5 | High |
| 6 | Poor communication and coordination with contracting parties | 0.767 | 3 | High |
| 7 | Difficulties in accessing credit facilities (E.g. Loan) | 0.683 | 8 | High |
| 8 | Change orders during construction by owner | 0.792 | 2 | High |
| 9 | Conflicts between project joint-owners | 0.708 | 6 | High |
| 10 | Indefinite suspension of work by owner | 0.696 | 7 | High |
| 11 | Lack of complete documentation before commencement of project | 0.642 | 10 | High |
| 12 | Delay in the approval of sample materials | 0.625 | 11 | High |
RII ranking for Contractors-related delay factors.
| S/N | Contractor-related causes of delay | RII | RII ranking | Level of contribution |
|---|---|---|---|---|
| 1 | Difficulties in project financing | 0.783 | 2 | High |
| 2 | Errors during construction | 0.696 | 8 | High |
| 3 | Improper planning and preparation during construction project | 0.721 | 6 | High |
| 4 | Poor site management and coordination | 0.700 | 7 | High |
| 5 | Delays in sub-contractor's work | 0.779 | 3 | High |
| 6 | Underestimation or overestimation of the project cost | 0.808 | 1 | Very High |
| 7 | Conflicts between contractor and other parties | 0.746 | 5 | High |
| 8 | Delays in the mobilization of workers | 0.650 | 10 | High |
| 9 | Regular change of sub-contractor's technical staff | 0.746 | 5 | High |
| 10 | Conflicts in sub-contractor's schedule in execution of project | 0.692 | 9 | High |
| 11 | Underestimation of the project durations | 0.763 | 4 | High |
RII ranking for Consultants-related delay factors.
| S/N | Consultant-related causes of delay | RII | RII ranking | Level of contribution |
|---|---|---|---|---|
| 1 | Delay in the approval of major changes in the work scope | 0.800 | 1 | Very high |
| 2 | Poor communication and coordination | 0.767 | 2 | High |
| 3 | Lack of significant experience of consultant | 0.750 | 3 | High |
| 4 | Mistakes and discrepancies in contract documents | 0.700 | 6 | High |
| 5 | Delays in creating design documents | 0.733 | 4 | High |
| 6 | Inadequate site survey and data collection before design | 0.713 | 5 | High |
| 7 | Delay in instructions from consultants | 0.671 | 8 | High |
| 8 | Back report of the consultant | 0.692 | 7 | High |
RII ranking for Labor-related delay factors.
| S/N | Labor-related causes of delay | RII | RII ranking | Level of contribution |
|---|---|---|---|---|
| 1 | Lack/shortage of labors | 0.763 | 1 | High |
| 2 | Labor strike | 0.688 | 3 | High |
| 3 | Personal conflicts between labors | 0.679 | 4 | High |
| 4 | Lack of sufficient skilled labors | 0.742 | 2 | High |
RII ranking for Materials-related delay factors.
| S/N | Materials-related causes of delay | RII | RII ranking | Level of contribution |
|---|---|---|---|---|
| 1 | Materials procurement difficulties (Lateness) | 0.763 | 2 | High |
| 2 | Shortage/lack of materials in the market place | 0.758 | 3 | High |
| 3 | Increase/Fluctuation in the prices of materials | 0.792 | 1 | High |
| 4 | Delay in the delivery of materials | 0.738 | 4 | High |
| 5 | Changes in material types during construction | 0.708 | 5 | High |
| 6 | Damage of sorted materials that are needed urgently | 0.650 | 6 | High |
RII ranking for Equipment-related delay factors.
| S/N | Equipment-related causes of delay | RII | RII ranking | Level of contribution |
|---|---|---|---|---|
| 1 | Shortage/lack of equipment | 0.767 | 1 | High |
| 2 | Breakdown/Failure of equipment | 0.721 | 2 | High |
| 3 | Low level of equipment-operator's skills | 0.696 | 4 | High |
| 4 | Challenges with the efficiency and effectiveness of equipment | 0.704 | 3 | High |
RII ranking for external factors-related delay factors.
| S/N | External factors-related causes of delay | RII | RII ranking | Level of contribution |
|---|---|---|---|---|
| 1 | Unfavorable site conditions | 0.763 | 1 | High |
| 2 | Change in weather condition | 0.733 | 2 | High |
| 3 | Delay in securing permits | 0.675 | 6 | High |
| 4 | Occurrence of accident during construction | 0.725 | 3 | High |
| 5 | Introduction of new government policies, regulations, and laws | 0.708 | 4 | High |
| 6 | Delay in services provided by utility service providers | 0.696 | 5 | High |
RII ranking for the ten most significant factors that causes construction delays in Hargeisa.
| RII ranking | Top ten significant factors | RII | Number of factors | Category |
|---|---|---|---|---|
| 1 | Delay in honoring payment progressively | 0.846 | 1 | Owner-related |
| 2 | Underestimation or overestimation of the project cost | 0.808 | 1 | Contractor-related |
| 3 | Delay in the approval of major changes in the work scope | 0.800 | 1 | Consultant-related |
| 4 | Change orders during construction by owner Increase/Fluctuation in the prices of materials | 0.792 | 2 | Owner-related Materials-related |
| 5 | Difficulties in project financing | 0.783 | 1 | Contractor-related |
| 6 | Delays in sub-contractor's work | 0.779 | 1 | Contractor-related |
| 7 | Poor communication and coordination with contracting parties | 0.767 | 3 | Owner-related |
| Poor communication and coordination | Consultant-related | |||
| Shortage/lack of equipment | Equipment-related | |||
| 8 | Underestimation of the project durations | 0.763 | 4 | Contractor-related |
| Lack/shortage of Labors | Labor-related | |||
| Materials procurement difficulties (Lateness) | Materials-related | |||
| Unfavorable site conditions | External Factors | |||
| 9 | Shortage/lack of materials in the market place | 0.758 | 1 | Materials-related |
| 10 | Lack of significant experience of consultant | 0.750 | 1 | Consultant-related |