| Literature DB >> 35249628 |
Selman Aslan1, Osman Hürol Türkakın2.
Abstract
INTRODUCTION: At the beginning of the COVID-19 pandemic, various social measures were taken and various sectors were affected with strict precautions and safety measurements. The construction industry, where numerous employees work together, was affected by these COVID restrictions. The pandemic period typically further delayed the construction contracts.Entities:
Keywords: AHP; COVID-19; Multi-objective optimization; OHS; Pandemic
Mesh:
Year: 2021 PMID: 35249628 PMCID: PMC8648395 DOI: 10.1016/j.jsr.2021.11.007
Source DB: PubMed Journal: J Safety Res ISSN: 0022-4375
Activities and their essential values.
| ID | Names | Predecessor | Quantity | Manhour | Worker Hour Cost (TL) | Material Unit Cost (TL) | Min. Worker | Max. Worker |
|---|---|---|---|---|---|---|---|---|
| 1 | Excavation | – | 45.00 | 0.30 | 227.00 | 0.00 | 1 | 1 |
| 2 | Concrete Forming | 1 | 10.00 | 3.50 | 18.45 | 8.72 | 3 | 5 |
| 3 | Reinforcement Bars | 2 | 2.68 | 115.00 | 18.45 | 2827.12 | 4 | 15 |
| 4 | Concrete Finishing | 3 | 30.00 | 9.37 | 18.45 | 181.52 | 2 | 15 |
| 5 | Brick Masonry | 4 | 200.00 | 2.01 | 18.45 | 25.26 | 2 | 7 |
| 6 | Roof Framing | 5 | 10.00 | 40.00 | 18.45 | 1519.61 | 2 | 25 |
| 7 | Clay Roof Tiles | 6 | 101.98 | 0.60 | 18.45 | 75.20 | 2 | 10 |
| 8 | Select Finishes | – | 40.00 | 1.00 | 18.45 | 0.00 | 1 | 1 |
| 9 | Interior Plaster | 15 | 360.00 | 2.07 | 18.45 | 3.37 | 3 | 10 |
| 10 | Exterior Plaster | 15 | 195.00 | 2.07 | 18.45 | 3.37 | 3 | 10 |
| 11 | Wood Windows | 9,10 | 264.00 | 0.40 | 18.45 | 3.55 | 2 | 5 |
| 12 | Wall Tiling | 14 | 45.00 | 3.49 | 18.45 | 83.85 | 2 | 20 |
| 13 | Floor Tiling | 14 | 135.00 | 4.70 | 18.45 | 25.38 | 2 | 20 |
| 14 | Interior Painting | 11 | 450.00 | 1.00 | 18.45 | 4.32 | 2 | 20 |
| 15 | Temporary Scaffolding | 7,8 | 214.50 | 0.56 | 18.45 | 4.68 | 2 | 10 |
| 16 | Clean-Up | 12,13,21 | 150.00 | 1.00 | 18.45 | 1.00 | 1 | 6 |
| 17 | Delivery Garage Doors | – | 1.00 | 1.00 | 18.45 | 5000.00 | 1 | 1 |
| 18 | Brick Masonry-Garage | 4 | 100.00 | 2.01 | 18.45 | 25.26 | 2 | 10 |
| 19 | Roof Framing-Garage | 18 | 5.00 | 40.00 | 18.45 | 1519.61 | 2 | 10 |
| 20 | Clay Roof Tiles-Garage | 19 | 50.99 | 0.60 | 18.45 | 75.20 | 2 | 10 |
| 21 | Garage Doors | 17,20 | 1.00 | 30.00 | 30.00 | 0.00 | 5 | 5 |
Fig. 1Random worker locations with different social distances.
Fig. 2The upper limit of worker numbers with changing of social distances.
Fig. 3Average social distance values depending on the worker number.
Fig. 4The first parallel scheduling steps for a sample network (Source:Klein, 1999).
Fig. 5A sample Pareto Front for Two Objectives.
Fig. 6Flowchart of a Generic Multi-Objective GA.
The scale of Relative Importance (Saaty & Kearns, 1985).
| Important value | Definition | Explanation |
|---|---|---|
| 1 | Equally preferred | Two activities contribute equally to the objective. |
| 3 | Moderately preferred | Experience and judgment slightly favor one activity over another. |
| 5 | Strongly preferred | Experience and judgment strongly favor one activity over another. |
| 7 | Very strongly preferred | Activity is strongly favored and its dominance is demonstrated in practice. |
| 9 | Extremely preferred | The evidence favoring one activity over another is of the highest possible order of affirmation. |
| 2, 4, 6, 8, | Intermediate values between the two adjacent judgments | When compromise is needed. |
Random consistency (RI) (Saaty & Kearns, 1985).
| Size of matrix | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
|---|---|---|---|---|---|---|---|---|---|---|
| Random consistency | 0 | 0 | 0.58 | 0.9 | 1.12 | 1.24 | 1.32 | 1.41 | 1.45 | 1.49 |
Baseline schedule without pandemic effects.
| Activity name | Duration | Early start | Early finish | Duration in pandemic | Start day in Pandemic | Finish day in pandemic |
|---|---|---|---|---|---|---|
| Excavation | 2 | 0 | 2 | 2 | 0 | 2 |
| Concrete Forming | 1 | 2 | 3 | 2 | 2 | 4 |
| Reinforcement Bars | 3 | 3 | 6 | 10 | 4 | 14 |
| Concrete Finishing | 3 | 6 | 9 | 9 | 14 | 23 |
| Brick Masonry | 8 | 9 | 17 | 26 | 23 | 49 |
| Roof Framing | 2 | 17 | 19 | 25 | 49 | 74 |
| Clay Roof Tiles | 1 | 19 | 20 | 2 | 74 | 76 |
| Select Finishes | 5 | 0 | 5 | 5 | 0 | 5 |
| Interior Plaster | 10 | 22 | 32 | 32 | 89 | 121 |
| Exterior Plaster | 6 | 22 | 28 | 7 | 121 | 128 |
| Wood Windows | 3 | 32 | 35 | 5 | 128 | 133 |
| Wall Tiling | 1 | 38 | 39 | 5 | 152 | 157 |
| Floor Tiling | 4 | 38 | 42 | 40 | 152 | 192 |
| Interior Painting | 3 | 35 | 38 | 19 | 133 | 152 |
| Temporary Scaffolding | 2 | 20 | 22 | 3 | 86 | 89 |
| Clean-Up | 4 | 42 | 46 | 7 | 192 | 199 |
| Delivery Garage Doors | 1 | 0 | 1 | 1 | 0 | 1 |
| Brick Masonry-Garage | 3 | 9 | 12 | 3 | 76 | 79 |
| Roof Framing-Garage | 3 | 12 | 15 | 5 | 79 | 84 |
| Clay Roof Tiles-Garage | 1 | 15 | 16 | 1 | 84 | 85 |
| Garage Doors | 1 | 16 | 17 | 1 | 85 | 86 |
Fig. 7Pareto results of different labor limits.
Fig. 8Comparison of four worker condition’s Pareto Front projections.
Alternatives for AHP Classification.
| Alternatives | Risk (%) | Duration (Day) | Cost (Turkish Lira) | Cost Difference |
|---|---|---|---|---|
| Alternative 1 | 0.86 | 70 (25 worker) | 175,562.4 | +0 TL |
| Alternative 2 | 0.76 | 98 (20 worker) | 176,272.2 | +709.72 TL |
| Alternative 3 | 0.66 | 125 (15 worker) | 178,522.2 | +2,959.715 |
| Alternative 4 | 0.56 | 156 (10 worker) | 181,991.1 | +6,428.63 TL |
| Alternative 5 | 0.46 | 199 (10 worker) | 185,722 | +10,159.56 TL |
AHP Results.
| Criteria | Level of importance | Ranking |
|---|---|---|
| Risk | 0.648 | 1 |
| Duration | 0.122 | 3 |
| Cost | 0.230 | 2 |
| Consistency ratio: 0.006 (CR < 0,1) | ||
| Risk Criterion | Level of importance | Ranking |
| Alternative 1 | 0.062 | 5 |
| Alternative 2 | 0.099 | 4 |
| Alternative 3 | 0.161 | 3 |
| Alternative 4 | 0.262 | 2 |
| Alternative 5 | 0.416 | 1 |
| Consistency ratio: 0,026 (CR < 0,1) | ||
| Duration Criterion | Level of importance | Ranking |
| Alternative 1 | 0.412 | 1 |
| Alternative 2 | 0.258 | 2 |
| Alternative 3 | 0.159 | 3 |
| Alternative 4 | 0.109 | 4 |
| Alternative 5 | 0.062 | 5 |
| Consistency ratio: 0,056 (CR < 0,1) | ||
| Cost Criterion | Level of importance | Ranking |
| Alternative 1 | 0.337 | 1 |
| Alternative 2 | 0.258 | 2 |
| Alternative 3 | 0.182 | 3 |
| Alternative 4 | 0.127 | 4 |
| Alternative 5 | 0.095 | 5 |
| Consistency ratio: 0,024 (CR < 0,1) | ||
| Decision | Level of importance | Ranking |
| Alternative 1 | 0.168 | 3 |
| Alternative 2 | 0.155 | 5 |
| Alternative 3 | 0.166 | 4 |
| Alternative 4 | 0.212 | 2 |
| Alternative 5 | 0.299 | 1 |