| Literature DB >> 33114063 |
Abstract
Offshore waste disposal facilities are unique marine infrastructures that exist only in a few countries. Although the existing facilities in Japan and Singapore have been successfully operated in general, there have been no investigations on the probable hazards they pose on the environment. Considering this, conceivable hazards were identified for an offshore waste disposal facility that has recently been proposed in Korea. The causes and consequences of each of the identified hazards were analyzed to seek countermeasures for reducing the environmental impact in advance. Hazards of waste disposal facilities can be classified according to their design, construction, maintenance, operation, and site utilization. For these areas, except for site utilization, subsystem hazard analysis was performed. In the initial assessment, seven elements were found to be in the extreme risk zone, 30 were in the high-risk zone, and six were in the moderate-risk zone. After applying the alternative mitigation methods, the final risk assessment resulted in 27 moderate-risk and 16 low-risk elements. Therefore, it was confirmed that the potential risks of the proposed offshore waste disposal facility were within acceptable ranges.Entities:
Keywords: environmental impact; hazard analysis; offshore waste disposal facility; risk matrix; subsystem
Mesh:
Year: 2020 PMID: 33114063 PMCID: PMC7660325 DOI: 10.3390/ijerph17217755
Source DB: PubMed Journal: Int J Environ Res Public Health ISSN: 1660-4601 Impact factor: 3.390
Figure 1Overview of the subsystem hazard analysis (adapted and redrawn from [27]).
Figure 2Conceptual diagram of the subsystem hazard analysis for the offshore waste disposal facility. PHA denotes preliminary hazard analysis, SSHA—subsystem hazard analysis, TLM—top-level mishaps, and SCFs—safety critical functions, respectively.
Figure 3Location of the proposed offshore waste disposal facility.
Figure 4Details of the revetments constituting the proposed offshore waste disposal facility.
Figure 5Cross-sections of the revetments constituting the offshore waste disposal facility: (a) the barrier revetment corresponding to Sections A–E; (b) the separating revetment corresponding to Section I; and (c) the connection revetment corresponding to Section L.
Monitoring items and remarks for landfill management.
| Monitoring Items | Remarks |
|---|---|
| Changes in water level inside and outside the offshore disposal facility | Performance of the cut-off barrier can be checked by monitoring changes in water level inside and outside the facility. It is necessary to confirm that the water level inside the facility is not influenced by the adjacent tide level. |
| Revetment deformation due to ground settlement | It is necessary to measure the displacement of revetment on the ground as well as underwater. Monitoring ground settlement is also required by installing inclinometers and settlement gauges. |
| Landfill height change | Landfill height should be distributed as evenly as possible within the disposal facility for stable landfill management. |
| Water quality inside and outside the facility | Measurement of dissolved oxygen (DO), pH, and other water quality indices is requested at least once every 6 months over at least two locations. |
Worksheet used for the subsystem hazard analysis. IMRI—initial mishap risk index, FMRI—final mishap risk index.
| No. | Hazard | Causes | Consequences | IMRI | Mitigation | FMRI |
|---|---|---|---|---|---|---|
| ① | ② | ③ | ④ | ⑤ | ⑥ | ⑦ |
Mishap risk indices according to MIL-STD-882D [27].
| Severity | Probability |
|---|---|
| (1) Catastrophic | (A) Frequent |
| (2) Critical | (B) Probable |
| (3) Marginal | (C) Occasional |
| (4) Negligible | (D) Remote |
| (E) Improbable |
The list of severities and probabilities of all 43 identified hazards.
| Code | Hazard | Severity | Probability |
|---|---|---|---|
| S1-A | Cracking and collapse of the separate revetment | 3 | D |
| S1-B | Circular slip failure of the revetment | 2 | B |
| S1-C | Displacement of the revetment due to waste disposal | 3 | C |
| S2-A | Corrosion of barriers made of steel | 2 | B |
| S2-B | Deformation and damage of joints caused by an earthquake | 2 | D |
| S2-C | Deformation and damage of joints during landfill | 2 | D |
| S2-D | Deformation and damage of joints due to landfill pressure | 2 | B |
| S2-E | Insufficient stability of mortar at joints caused by poor filling | 3 | B |
| S2-F | Degradation of stability of mortar at joints caused by aging | 3 | B |
| S2-G | Poor construction of joints | 3 | C |
| S2-H | Insufficient depth of barriers due to poor construction | 2 | A |
| S2-I | Insufficient depth of barriers due to heterogeneity of ground | 2 | A |
| S2-J | Degradation of cut-off performance at joints | 2 | C |
| S3-A | Locally permeable ground | 3 | D |
| S3-B | Damage of waterproof sheets due to the poor fusion of adhesive parts | 3 | C |
| S3-C | Damage of waterproof sheets due to landfill weight | 3 | C |
| S3-D | Damage of waterproof sheets due to slip on the slope | 3 | C |
| S3-E | Degradation of cut-off performance of the separate revetment | 3 | C |
| S3-F | Degradation of cut-off performance of the connection revetment | 3 | C |
| S3-G | Floating of waterproof sheets due to lack of sufficient weight | 3 | C |
| S3-H | Degradation of cut-off performance of the barrier revetment | 3 | C |
| S4-A | Failure of detecting leakages of leachate | 3 | C |
| S4-B | Failure of confirming the location where leakages occur | 3 | C |
| S5-A | Failure of treating retained water | 2 | C |
| S5-B | Degradation of the capability of retained water treatment | 3 | D |
| S5-C | The outflow of retained water to the sea | 2 | C |
| S5-D | Exceedance of retained water greater than treatment capacity | 2 | C |
| S5-E | Fire | 2 | C |
| S5-F | Flooding | 2 | C |
| S5-G | Electric shock from high voltage | 2 | D |
| S5-H | Wave overtopping | 2 | C |
| S5-I | Deterioration of employee’s health | 2 | C |
| S6-A | Malfunction of the sensors measuring water level | 3 | B |
| S6-B | Malfunction of the sensors measuring water quality | 3 | B |
| S6-C | Exceedance of measurement range of the sensors | 3 | B |
| S6-D | Power supply interruption to the sensors | 3 | B |
| S6-E | Malfunction of the movable sensing device | 3 | D |
| S6-F | Errors in the communication signal | 3 | C |
| S6-G | Inability of collecting sensing data | 3 | D |
| S6-H | Failure of operation and management system | 3 | D |
| S7-A | Collison of a ship to the revetment | 2 | D |
| S7-B | Suspended particles in the air | 2 | A |
| S7-C | Traffic congestion | 2 | A |
Figure 6Risk assessment matrix of initial subsystem hazard analysis (SSHA) of the offshore waste disposal facility.
Measures required for reducing or controlling the hazards according to the associated risk level [29].
| Risk Level | Measure |
|---|---|
| Extreme | Shall be eliminated |
| High | Shall only be accepted when risk reduction is impracticable and with the agreement of the authority |
| Moderate | Acceptable with adequate control and the agreement of the authority |
| Low | Acceptable with/without the agreement of the authority |
Extremely hazardous elements identified by subsystem hazard analysis (SSHA) and measures to mitigate them. IMRI—initial mishap risk index, FMRI—final mishap risk index.
| No. | Hazard | Cause | Consequence | IMRI | Mitigation | FMRI |
|---|---|---|---|---|---|---|
| S1-B | Circular slip failure of the revetment | Excessive surface load on the separating revetment | Collapse of the revetment | 2B | Modify the design of the separating revetment to satisfy the safety standards by reinforcing the fore slope of the revetment | 2E |
| S2-A | Corrosion of barriers made of steel | Exposure to seawater | Cracks in the barrier and deterioration of cut-off performance | 2B | Apply cathodic protection method or use special steels for anti-corrosion | 2E |
| S2-D | Deformation and damage of joints due to landfill pressure | Pressures from the landfilled waste | Cracks in the barrier and deterioration of cut-off performance | 2B | Apply a double layer waterproof sheets on the joints or use sheet piles implementing fail-safe technology | 2E |
| S2-H | Insufficient depth of barriers due to poor construction | Uncertainty associated with the construction of vertical barriers | Failure of barriers or deterioration of cut-off performance | 2A | Monitor the driving depth of vertical barriers and check verticality during construction | 2E |
| S2-I | Insufficient depth of barriers due to heterogeneity of ground | Poor construction of vertical barriers influenced by the heterogeneity of ground | Failure of barriers or deterioration of cut-off performance | 2A | Apply longer barriers than required to have extra driving depth considering the associated uncertainty | 2E |
| S7-B | Suspended particles in the air | Waste transportation and unloading to the disposal facility | Problems with the health and well-being of local residents | 2A | Apply a shield to the transportation vehicles and build a special device to minimize particle suspension during transportation and unloading | 2E |
| S7-C | Traffic congestion | Waste transportation on land | Inconvenience and uneasiness to local residents | 2A | Make a detour away from the residential area and transport waste avoiding crowded hours | 2E |
Figure 7Risk assessment matrix of the final subsystem hazard analysis (SSHA) of the offshore waste disposal facility. Blurred background colors indicate the results of the initial SSHA.
Figure 8Cross-sections of the revetments constituting the offshore waste disposal facility that have been modified based on the subsystem hazard analysis. (a) The barrier revetment corresponding to Sections A–E; (b) the separating revetment corresponding to Section I; and (c) the connection revetment corresponding to Section L.