| Literature DB >> 31750402 |
Saru Bhartia1, Pradaya Wahi1, Rinu Goyal2.
Abstract
In early 2013, several outpatients at Sitaram Bhartia Institute of Science and Research in New Delhi, India complained that their laboratory results were not ready at the promised time. We reviewed the data for 3 months and learnt that 16% of outpatient results were not ready when patients returned to receive them. We formed a multidisciplinary team to fix the problem. After conducting a time-and-motion study, process mapping and discussions the team identified two key problems: (1) the laboratory consultant did not have a set time to validate the results and (2) the reasons of delay in laboratory reports were not documented; this made it hard to identify and solve specific reasons. The team decided to set a fixed time for the consultant to verify results and to document reasons for delay in each case. The team used Plan-Do-Study-Act (PDSA) cycles to finalise the verification system and to set up the documentation system. Documentation led to the identification of new problems which were also solved using PDSA cycles. Delay in reports reduced significantly from 16% in March 2013 to less than 3% in a period of 4 months. We have sustained these gains for the past 5 years. © Author(s) (or their employer(s)) 2019. Re-use permitted under CC BY-NC. No commercial re-use. See rights and permissions. Published by BMJ.Entities:
Keywords: healthcare quality improvement; laboratory medicine; quality improvement
Year: 2019 PMID: 31750402 PMCID: PMC6830465 DOI: 10.1136/bmjoq-2018-000547
Source DB: PubMed Journal: BMJ Open Qual ISSN: 2399-6641
Plan-Do-Study-Act (PDSA) cycles to test change ideas for reducing delays in laboratory reports
| Plan | Do | Study | Act | |
| Change 1: setting a time to verify laboratory results | ||||
| PDSA 1a | Test whether the laboratory consultant would be able to do a final verification of reports within the scheduled time frame. We tested this from 11 June to 20 June 2013 for biochemistry and immunoassay tests | As planned | The laboratory consultant was able to do a final verification for 90% of the biochemistry and immunoassay tests within the scheduled time frame. As a result of this change, only 5.5% biochemistry and immunoassay reports were delayed | Expand this system to all tests |
| PDSA 1b | Use the system from PDSA 1a for all laboratory tests | As planned | Worked well. 5% delayed since then | Continue this approach |
| Change 2: documenting reasons for delays | ||||
| PDSA 2a | The test was run from 25 June to 29 June 2013 to test if it would be practical for the laboratory consultant to fill the reasons of delay in LIS daily | As planned | During these 5 days, the compliance to filling reasons for delay was 17% only | The consultant learnt that his current approach was not working. He planned some changes to his routine and tested them in PDSA 2b |
| PDSA 2b | This PDSA was run for July 2013 to test if the changes in laboratory consultant’s routine would help in filling reasons for delay in the LIS | As planned | With the changes in schedule, the laboratory consultant was able to fill reasons for 63% of the delayed reports | The laboratory consultant started filling the reasons for all delays |
| Change 3: booking samples in LIS only after they were received | ||||
| PDSA 3 | As a result of PDSA 2b, we learnt that some results were included even when samples were not taken. To test if the protocol to not book samples until they were received was feasible and effective, we ran a new PDSA from 12 August to 31 August 2013 | As planned | The protocol helped in not booking 110 samples that were not received | The protocol was implemented |
| Change 4: inform patients about delay in reports | ||||
| PDSA 4 | This PDSA was run to test if it was feasible for the front desk to inform patients in advance of any delay in reports. It was run from 1 October to 12 October 2013 | As planned | 28 reports were delayed during this time and all patients were informed of the delay before they came to the hospital | The front desk made calling the patients in case of delay a standard task from then |
LIS, laboratory information system.