Abstract

BACKGROUND: An improvement team from the Complex Care Center at our large pediatric medical center participated in a 60-day initiative to use Lean methodologies to standardize their processes, eliminate waste and improve the timely and reliable provision of durable medical equipment and supplies.
METHODS: The team used value stream mapping to identify processes needing improvement. Improvement activities addressed the initial processing of a request, provider signature on the form, returning the form to the sender, and uploading the completed documents to the electronic medical record. Data on lead time (time between receiving a request and sending the completed request to the Health Information Management department) and process time (amount of time the staff worked on the request) were collected via manual pre- and post-time studies.
RESULTS: Following implementation of interventions, the median lead time for processing durable medical equipment and supply requests decreased from 50 days to 3 days (p < 0.0001). Median processing time decreased from 14min to 9min (p < 0.0001). The decrease in processing time realized annual cost savings of approximately $11,000.
CONCLUSIONS: Collaborative leadership and multidisciplinary training in Lean methods allowed the CCC staff to incorporate common sense, standardize practices, and adapt their work environment to improve the timely and reliable provision of equipment and supplies that are essential for their patients. IMPLICATIONS: The application of Lean methodologies to processing requests for DME and supplies could also result in a natural spread to other paperwork and requests, thus avoiding delays and potential risk for clinical instability or deterioration.
Copyright © 2017 Elsevier Inc. All rights reserved.

Entities:  

Keywords:  Durable medical equipment; Improvement; Lead time; Lean methodologies; Process time

Mesh:

Year:  2017        PMID: 29246539     DOI: 10.1016/j.hjdsi.2017.11.003

Source DB:  PubMed          Journal:  Healthc (Amst)        ISSN: 2213-0764


  2 in total

Review 1.  The Role of Value Stream Mapping in Healthcare Services: A Scoping Review.

Authors:  Juan A Marin-Garcia; Pilar I Vidal-Carreras; Julio J Garcia-Sabater
Journal:  Int J Environ Res Public Health       Date:  2021-01-22       Impact factor: 3.390

2.  Sustained Reduction in Intravenous Pump Turnaround Time Using Lean Methodology.

Authors:  Smriti Neogi; Glenn Schneider; Joshua K Schaffzin
Journal:  Pediatr Qual Saf       Date:  2022-08-01
  2 in total

北京卡尤迪生物科技股份有限公司 © 2022-2023.