| Literature DB >> 35991975 |
Quintin Mokoena1, Ilesanmi Daniyan1, Khumbulani Mpofu1, Oluwayemisi Abisuga1.
Abstract
Drones are considered to become more significant as technology develops and be used in creative ways. The aim of this paper is to develop a framework to improve the turnaround time (TAT) of the drone application process at South African Civil Aviation Authority (SACAA). According to some of the drone companies, application process of drone approval takes time to complete. These delays impact negatively to drone companies in South Africa. Drone operators were interviewed, and the current status of the application process was captured. Thirteen drone operators were interviewed using a structured set of questionnaires. Results show that application process is not well implemented and that the structure does not create a positive outcome to the South African drone industry. Findings indicate that the average turnaround time to complete the approval process is long, and it is time consuming. The framework to improve the current turnaround time of the application process was developed. The proposed framework consists of three techniques (process activities improvement, capacity enhancement and process redesign). The proposed framework can be used as a guide to improve the situation at SACAA. .Entities:
Keywords: Drones; Framework; Process improvement; Turnaround time
Year: 2022 PMID: 35991975 PMCID: PMC9382269 DOI: 10.1016/j.heliyon.2022.e10075
Source DB: PubMed Journal: Heliyon ISSN: 2405-8440
Type of operations and required approval.
| Required approval | Type of operations | |||
|---|---|---|---|---|
| Commercial | Corporate | Non-profit | Private | |
| ASL | ✓ | N/A | N/A | N/A |
| ROC | ✓ | ✓ | ✓ | N/A |
| RLA | ✓ | ✓ | ✓ | N/A |
| RPL | ✓ | ✓ | ✓ | N/A |
| CofR | ✓ | ✓ | ✓ | N/A |
ASL– Air Service License.
ROC – RPAS Operator Certificate.
RLA – RPAS Letter of Approval.
RPL – Remote Pilot’s License.
CofR – Certificate of Registration.
Participants' working environment.
| Participant | Commercially RPAS operation |
|---|---|
| P1 | Services to the agriculture, construction, mining infrastructure and spectrums, Survey, film space |
| P2 | Construction, tracking and land surveying purposes |
| P3 | Agriculture and data collection |
| P4 | Commercial filmmaking |
| P6 | Survey, mining and inspections |
| P7 | Filming, building inspections, and concrete analysis. |
| P8 | Aerial surveys, for the surveying of mine and open pit mines |
| P9 | Promotional videos, music videos and mapping jobs. |
| P10 | Filming |
| P11 | Survey |
| P12 | Quantity survey, mapping of areas and infrastructure and videography. |
| P13 | Photography and media |
Figure 1Application process's perception.
Figure 2Longest application phase.
Figure 3Shortest application phase.
Figure 4Value-adding steps.
Figure 5Non-adding value steps.
Figure 6Negative impact due to turnaround time.
Time taken to complete all required SACAA approvals.
| Participant | ASL (Month) | ROC (Month) | RLA (Month) | RPL (Month) | CofR (Month) |
|---|---|---|---|---|---|
| P1 | 8 | 7 | 3 | P | 1 |
| P2 | 9 | 18 | P | 1 | 1 |
| P4 | 4 | 18 | 6 | 2 | 1 |
| P6 | 8 | 18 | 4 | 1 | 1 |
| P7 | 8 | 6 | 6 | 1 | 1 |
| P8 | 6 | 8 | P | 2 | P |
| P9 | 12 | 24 | 3 | 1 | 1 |
| P10 | P | 24 | 18 | 2 | 1 |
| P11 | 6 | 12 | 6 | 1 | 1 |
| P12 | 16 | 34 | 24 | 18 | 1 |
| P13 | 3 | 48 | 2 | P | 2 |
Figure 7Capacity to handle application process.
Figure 8Effective turnaround time strategies.
Figure 9Proposed framework for turnaround time improvement.