| Literature DB >> 35927557 |
Harpreet Sharma1, Akmaral Imanbayeva2.
Abstract
One of the major driving factors in the shifting of the present grid paradigm to an active grid network is the reliability and resiliency of the utility network. With hefty investment in the distribution network protection and maintenance, the reliability of the feeders is considerably enhanced; however, large numbers of outages are still occurring every year which caused major production loss to the manufacturing sector. In this paper, the role of the solar grid-based Virtual Power Plant (VPP) is evaluated in the state power utility for the reliability enhancement and cost minimization using a multi-objective model based on MILP optimization. A 90 bus industrial feeder having automatic reclosers, DER, and DSM is selected on which the MCS method is utilized for computing reliability indices using the utility reliability parameters. The value of reliability indices such as EENS is declined by 68% by utilizing the VPP scenario. These values of this reliability index are fed into the multi-objective model for cost minimization. After running the optimization, the results reveal that the operational and the annual energy cost are reduced by 61% and 55% respectively which advocates the VPP implementation in the utility network. Both modes of the Virtual Power Plant such as grid-connected and autonomous mode have been discussed in detail. Lastly, the results of the developed model with MILP are compared with the proprietary derivative algorithm, and it is found that the proposed MILP is more cost-effective. The overall results advocate the VPP implementation in the utility grid as the economical advantage is provided to both utility and the consumers in terms of reduction in EENS and energy charges respectively.Entities:
Mesh:
Year: 2022 PMID: 35927557 PMCID: PMC9352725 DOI: 10.1038/s41598-022-16389-8
Source DB: PubMed Journal: Sci Rep ISSN: 2045-2322 Impact factor: 4.996
Schedulable load data.
| Feeder | Controllable load (percentage of aggregated load) during Peak day | Controllable load (percentage of aggregated load) during Weekday | Controllable load (percentage of aggregated load) during Weekend | Maximum load curtailment during peak hours | Maximum period |
|---|---|---|---|---|---|
| Industrial | 18% | 18% | 32% | 800 kW | 12 h |
Figure 1Workflow of MILP optimization.
Figure 2Annual average solar radiation and clearness index data.
Figure 311 kV Industrial feeder 90 bus system.
Figure 4Load profile of industrial feeder.
Industrial feeder technical parameters.
| Feeder loading parameters | Feeder reliability parameters | ||
|---|---|---|---|
| Annual average demand | 1033 kW | 47 | |
| Annual Peak demand | 4288 kW | 0.15 | |
| Total annual energy consumption | 97,18,850 kWh | 0.5 h | |
| Peak Month | November | 41 | |
| Total consumers on feeder | 257 | 0.5 | |
| Total length of feeder | 2.174 KM | 1.5 h | |
| Current capacity of feeder conductor | 254 Amp | 1 | |
| Connected Load of feeder | 9228 kVA | 0.6 | |
| Maximum demand | 290 Amp/5518 kVA | 4 h | |
Specification of VPP components.
| Solar panel price ($/kW) | $ 1150 |
|---|---|
| Solar panel lifetime | 20 Years |
| Inverter price (100 kW) | $500 |
| Solar panel peak eff | 14.9% |
ToD tariff.
| Date | Duration | Price/kWh |
|---|---|---|
| 1–4–18 to 31–5–18 | 06:00 AM to 06:00 PM | $0.0907 |
| 06:00PM to 10:00 PM | $0.0907 | |
| 10:00 PM to 06:00 AM | $0.0713 | |
| 1–6–18 To 30–9–18 | 06:00 AM to 06:00 PM | $0.0907 |
| 06:00PM to 10:00 PM | $0.1220 | |
| 10:00 PM to 06:00 AM | $0.0907 | |
| 1–10–18 To 31–3–19 | 06:00 AM to 06:00 PM | $0.0907 |
| 06:00PM To 10:00 PM | $0.0907 | |
| 10:00 PM To 06:00 AM | $0.0713 |
Reliability results of Industrial feeder.
| Case | SAIFI | SAIDI | CAIDI | ASAI | EENS |
|---|---|---|---|---|---|
| Case1:base case with initial values | 27.686 | 34.2946 | 1.2387 | 0.99609 | 37,045 kWh |
| Case2:with automatic reclosers | 23.6684 | 31.3868 | 1.3261 | 0.99642 | 33,869 kWh |
| Case3:with automatic reclosers and VPP | 9.5266 | 10.153 | 1.0657 | 0.99884 | 11,689 kWh |
Proposed MILP optimization results.
| Model solution status | 8 integer solution |
|---|---|
| Solver termination condition | 1 normal completion |
| Number of iterations | 1936 |
| Number of variables | 726,673 |
| Number of discrete Variables | 50,526 |
| Relative solver precision | 0.02 |
| Objval ub | 0.097 best found |
| Objval lb | 0.096 |
| Equations | 535,547 |
| non zeros | 1,458,906 |
Techno-economic analysis.
| Base case | With Reclosers | With Reclosers and VPP | |
|---|---|---|---|
| PV capacity | – | – | 1916 kW |
| Total annual energy costs | $18,91,000 | $18,46,614 | $8,46,016 |
| Annual savings | 0 | $44,386 | $10,44,984 |
| Optimized operational cost | $18,91,000 | $18,46,614 | $7,37,578 |
| Total electric costs | $18,90,513 | $18,46,051 | $7,25,280 |
| Total annual electricity purchase | 97,18,850 kWh | 97,18,850 kWh | 65,11,797 kWh |
| Total annual on-site generation | – | – | 36,02,959 kWh |
| Load curtailment cost | $5,08,998 | $46,53,60 | $1,60,606 |
Figure 5Electrical dispatch with VPP.
Figure 6Electrical dispatch with VPP during an outage (Islanding mode).
VPP section-wise autonomous response.
| Load section | Connected load (kW) | Running load (kW) | PV (kW) | Flexible load (kW) | Load shed (kW) |
|---|---|---|---|---|---|
| 0–A | 9228 | 4401 | 884 | 660 | 2857 |
| A–B | 9128 | 4354 | 874 | 653 | 2827 |
| C–D | 8928 | 4258 | 854 | 1339 | 2065 |
| D–E | 8528 | 4067 | 833 | 1279 | 1955 |
| E–F | 8328 | 3972 | 813 | 1249 | 1910 |
| F–G | 8128 | 3877 | 793 | 1219 | 1865 |
| G–H | 7898 | 3767 | 770 | 1184 | 1813 |
| H–I | 6878 | 3280 | 670 | 1031 | 1579 |
| I–J | 6678 | 3285 | 650 | 1001 | 1634 |
| J–K | 6578 | 3137 | 640 | 986 | 1511 |
| K–L | 6378 | 3042 | 620 | 956 | 1466 |
| L–M | 5378 | 2565 | 522 | 806 | 1237 |
| M–N | 5178 | 2469 | 502 | 776 | 1191 |
| N–O | 4678 | 2231 | 483 | 701 | 1047 |
| O–P | 4478 | 2136 | 462 | 671 | 1003 |
| P–Q | 4278 | 2040 | 441 | 641 | 958 |
| Q–R | 4178 | 1992 | 430 | 626 | 936 |
| R–S | 3778 | 1802 | 388 | 566 | 848 |
| S–T | 3678 | 1754 | 377 | 551 | 826 |
| T–U | 3478 | 1659 | 356 | 521 | 782 |
| U–V | 2978 | 1420 | 304 | 446 | 670 |
| V–W | 2778 | 1325 | 283 | 416 | 626 |
| W–X | 2578 | 1229 | 262 | 386 | 581 |
| X–Y | 2115 | 1008 | 214 | 317 | 477 |
| Y–Z | 1615 | 770 | 163 | 242 | 365 |
| Z–A1 | 1552 | 749 | 156 | 232 | 361 |
| A1–A2 | 1489 | 710 | 149 | 223 | 338 |
| A2–A3 | 889 | 424 | 88 | 133 | 203 |
| A3–A4 | 263 | 125 | 66 | 39 | 20 |
| A4–A5 | 200 | 94 | 50 | 30 | 14 |
| A5–A6 | 100 | 47 | 23 | 15 | 9 |
Comparison of Different Optimization Techniques.
| Optimization algorithm | Optimal operational cost | Execution time |
|---|---|---|
| Only grid | $18,91,000 | 00 S |
| HOMER Pro | $8,88,571 | 03.6 S |
| Proposed MILP | $7,37,578 | 15.1 S |