Riccardo Crescenzi1, Mara Giua2, Giulia Valeria Sonzogno3.
Abstract
This paper develops an evidence-based approach to the selection and prioritisation of Next Generation EU (NGEU) projects for timely implementation and impact of the Recovery Plan for Europe. The analysis of a large sample of projects, currently funded by the European Union (EU) with the same priorities and objectives of NGEU, suggests that a timely implementation should be driven - within the EU Commission coordination framework - by national governments liaising directly with their citizens through participatory procedures, involving relevant stakeholders. Simplified implementation procedures with clear spatial targeting and limited involvement of regional authorities are necessary conditions for the avoidance of implementation delays.Entities:
Keywords: Cohesion Policy; Covid-19; European Union; Next generation EU; Recovery Fund
Year: 2021 PMID: 35702572 PMCID: PMC9186471 DOI: 10.1016/j.jpolmod.2021.03.002
Source DB: PubMed Journal: J Policy Model ISSN: 0161-8938
Identification of NGEU-like projects.
| Intervention fields | N. Projects | |
|---|---|---|
| 004 | Productive investment linked to the cooperation between large enterprises and SMEs for developing information and communication technology (ICT) products and services, e-commerce and enhancing demand for ICT | 1 |
| 010 | Renewable energy: solar | 20 |
| 012 | Other renewable energy (including hydroelectric, geothermal and marine energy) and renewable energy integration (including storage, power to gas and renewable hydrogen infrastructure) | 2 |
| 013 | Energy efficiency renovation of public infrastructure, demonstration projects and supporting measures | 271 |
| 015 | Intelligent Energy Distribution Systems at medium and low voltage levels (including smart grids and ICT systems) | 49 |
| 017 | Household waste management (including minimisation, sorting, recycling measures) | 4 |
| 021 | Water management and drinking water conservation (including river basin management, water supply, specific climate change adaptation measures, district and consumer metering, charging systems and leak reduction) | 1 |
| 022 | Waste water treatment | 6 |
| 023 | Environmental measures aimed at reducing and / or avoiding greenhouse gas emissions (including treatment and storage of methane gas and composting) | 66 |
| 043 | Clean urban transport infrastructure and promotion (including equipment and rolling stock) | 15 |
| 044 | Intelligent transport systems (including the introduction of demand management, tolling systems, IT monitoring, control and information systems) | 7 |
| 046 | ICT: High-speed broadband network (access/local loop; >/=30 Mbps) | 2 |
| 068 | Energy efficiency and demonstration projects in SMEs and supporting measures | 275 |
| 069 | Support to environmentally-friendly production processes and resource efficiency in SMEs | 10 |
| 070 | Promotion of energy efficiency in large enterprises | 14 |
| 078 | e-Government services and applications (including e-Procurement, ICT measures supporting the reform of public administration, cyber-security, trust and privacy measures, e-Justice and e-Democracy) | 74 |
| 080 | e-Inclusion, e-Accessibility, e-Learning and e-Education services and applications, digital literacy | 7,369 |
| 082 | ICT Services and applications for SMEs (including e-Commerce, e-Business and networked business processes), living labs, web entrepreneurs and ICT start-ups) | 164 |
| 085 | Protection and enhancement of biodiversity, nature protection and green infrastructure | 13 |
| 086 | Protection, restoration and sustainable use of Natura 2000 sites | 2 |
| 087 | Adaptation to climate change measures and prevention and management of climate related risks e.g. erosion, fires, flooding, storms and drought, including awareness raising, civil protection and disaster management systems and infrastructures | 21 |
| 089 | Rehabilitation of industrial sites and contaminated land | 13 |
| 090 | Cycle tracks and footpaths | 6 |
Notes: Keyword search for NGEU-like Projects is based on the following selected keywords: artificial intelligence, big data, bike path/cycle, bio, blue-economy, circular economy, cleanup, climat*, cloud, cyber, depurate*, digit, ecology*, ecosist*, elettron*, emission, energy efficiency, environm*, green, habitat, health, hub, hydro/water, ICT, innov*, lab, natur*, photovoltaic, restoration, sustainab*, tecnol*, telematic, verd*, waste management.
Classifying implementation for traditional and NGEU-like Projects.
| ‘Traditional’ Projects | NGEU-like Projects | Total | ||
|---|---|---|---|---|
| On time | # | 249,736 | 9,945 | 259,681 |
| % | 88.24 | 69.83 | 87.36 | |
| Light delay | # | 15,780 | 1,253 | 17,033 |
| % | 5.58 | 8.80 | 5.73 | |
| Severe delay | # | 17,494 | 3,044 | 20,538 |
| % | 6.18 | 21.37 | 6.91 | |
| Total | # | 283,010 | 14,242 | 297,252 |
| % | 100.00 | 100.00 | 100.00 |
Description of projects’ observable variables.
| Variable name | Variable description | # Projects |
|---|---|---|
| EU | =1 if the project belongs to an ESIF (European Structural and Investment Funds) Program | 13,155 |
| =0 if the project belongs to a Nationally funded Program (‘Fondo Sviluppo e Coesione’ / ‘Piano di Azione e Coesione’ and others) | 1,087 | |
| Regions | =1 if the project belongs to a Regional Operative Program | 5,394 |
| =0 if the project belongs to a National Operative Program | 8,848 | |
| Centralized design | =1 if the project is designed by a central authority (Ministries Departments or Presidency of Ministries) | 7,570 |
| =0 if the project is designed by a regional or subregional authority (e.g. Provinces, Municipalities, Functional Bodies) | 6,672 | |
| People-led | =1 if the implementation of the project is led by persons | 140 |
| =0 if the implementation of the project is led by public authorities/bodies or by companies | 14,102 | |
| Multiple beneficiaries | =1 if the project has multiple beneficiaries | 95 |
| =0 if the project has a single beneficiary | 14,147 | |
| Multiple territories | =1 if the project location involves more than one Local Labour System | 535 |
| =0 if the project location involves a unique Local Labour System | 13,707 | |
| Negotiated Tenders | =1 if the project has been activated through a negotiated procedure | 509 |
| =0 if the project has been activated through standard procedures (direct assignments/open calls) | 13,733 | |
| Public Administration | =1 if the project contributes to the Public Administration sector according to the CUP (Codice Unico Progetto) classification | 489 |
| =0 if the project does not contribute to the Public Administration sector according to the CUP (Codice Unico Progetto) classification | 13,753 | |
| ICT | =1 if the project contributes to the ICT sector according to the CUP (Codice Unico Progetto) classification | 455 |
| =0 if the project does not contribute to the ICT sector according to the CUP (Codice Unico Progetto) classification | 13,787 | |
| Social Inclusion | =1 if the project contributes to the Social Inclusion sector according to the CUP (Codice Unico Progetto) classification | 7,877 |
| =0 if the project does not contribute to the Social Inclusion sector according to the CUP (Codice Unico Progetto) classification | 6,365 | |
| Procurement/Grant/Capital | =1 if the project is a procurement operation, an individual grant assignment or a capital contribution according to the CUP (Codice Unico Progetto) classification | 9,674 |
| =0 if the project is an infrastructural intervention or a company incentive according to the CUP (Codice Unico Progetto) classification | 4,568 | |
| Less Developed Regions | =1 if the project is located in a Less Developed Region as classified by the 2014−2020 EU Cohesion policy (Basilicata, Calabria, Campania, Puglia, Sicilia) | 5,457 |
| =0 if the project is not located in a Less Developed Region as classified by the 2014−2020 EU Cohesion policy (Basilicata, Calabria, Campania, Puglia, Sicilia) | 8,737 | |
| Funding amount | Log of the total cost of the project | 10.410 |
Notes: for the Funding amount variable we reported the value of the mean of the Logaritmic transformation.
NGEU-like projects: bottlenecks to a timely implementation.
| Dependent variable: Delay | |||||
|---|---|---|---|---|---|
| (1) | (2) | (3) | (4) | (5) | |
| EU | −0.249*** | −0.0487 | |||
| (0.0190) | (0.0360) | ||||
| Regions | 0.382*** | 0.123*** | |||
| (0.0134) | (0.0333) | ||||
| Centralized design | −0.412*** | −0.303*** | |||
| (0.0135) | (0.0344) | ||||
| People-led | −0.374*** | −0.310*** | |||
| (0.0398) | (0.0380) | ||||
| Multiple territories | 0.133*** | 0.106*** | |||
| (0.0233) | (0.0221) | ||||
| Multiple beneficiaries | 0.207*** | 0.157*** | |||
| (0.0477) | (0.0492) | ||||
| Negotiated Tenders | −0.228*** | −0.204*** | |||
| (0.0237) | (0.0251) | ||||
| Public Administration/ICT/Social Inclusion | ✓ | ✓ | ✓ | ✓ | ✓ |
| Procurement/Grant/Capital | ✓ | ✓ | ✓ | ✓ | ✓ |
| Less Developed Regions | ✓ | ✓ | ✓ | ✓ | ✓ |
| Funding amount | ✓ | ✓ | ✓ | ✓ | ✓ |
| Constant | 0.680*** | 0.943*** | 0.875*** | 0.784*** | 0.824*** |
| (0.0439) | (0.0377) | (0.0397) | (0.0391) | (0.0429) | |
| Observations | 14,193 | 14,194 | 14,194 | 14,194 | 14,193 |
| R-squared | 0.454 | 0.462 | 0.410 | 0.413 | 0.473 |
Notes: 48 Projects (out of 14,242) are excluded from the analysis since they cannot be associated to a certain location (i.e. projects that are implemented at the national level or involving all regions of the country, or a subsample of regions that include both Less Developed Region and More Developed Region).
Robust Standard errors in parentheses *** p < 0.01, ** p < 0.05, * p < 0.1.
NGEU-like projects: bottlenecks to a timely implementation (light delays).
| Dependent variable: Light Delay | |||||
|---|---|---|---|---|---|
| (1) | (2) | (3) | (4) | (5) | |
| EU | −0.187*** | −0.0274 | |||
| (0.0196) | (0.0372) | ||||
| Regions | 0.327*** | 0.119*** | |||
| (0.0135) | (0.0351) | ||||
| Centralized design | −0.343*** | −0.243*** | |||
| (0.0138) | (0.0362) | ||||
| People-led | −0.347*** | −0.296*** | |||
| (0.0396) | (0.0382) | ||||
| Multiple territories | 0.105*** | 0.0870*** | |||
| (0.0279) | (0.0267) | ||||
| Multiple beneficiaries | 0.134** | 0.0771 | |||
| (0.0657) | (0.0672) | ||||
| Negotiated Tenders | −0.203*** | −0.168*** | |||
| (0.0234) | (0.0250) | ||||
| Public Administration/ICT/Social Inclusion | ✓ | ✓ | ✓ | ✓ | ✓ |
| Procurement/Grant/Capital | ✓ | ✓ | ✓ | ✓ | ✓ |
| Less Developed Regions | ✓ | ✓ | ✓ | ✓ | ✓ |
| Funding amount | ✓ | ✓ | ✓ | ✓ | ✓ |
| Constant | 0.782*** | 1.034*** | 0.999*** | 0.932*** | 0.892*** |
| (0.0459) | (0.0399) | (0.0417) | (0.0412) | (0.0453) | |
| Observations | 12,940 | 12,941 | 12,941 | 12,941 | 12,940 |
| R-squared | 0.410 | 0.415 | 0.371 | 0.376 | 0.425 |
Notes: 48 Projects (out of 14,242) are excluded from the analysis since they cannot be associated to a certain location (i.e. projects that are implemented at the national level or involving all regions of the country, or a subsample of regions that include both Less Developed Region and More Developed Region). Projects experiencing severe delays are excluded from the analysis.
Robust Standard errors in parentheses *** p < 0.01, ** p < 0.05, * p < 0.1.
NGEU-like projects: bottlenecks to a timely implementation (severe delays).
| Dependent variable: Severe Delay | |||||
|---|---|---|---|---|---|
| (1) | (2) | (3) | (4) | (5) | |
| EU | −0.0639*** | −0.0370 | |||
| (0.0188) | (0.0362) | ||||
| Regions | 0.206*** | 0.133*** | |||
| (0.0125) | (0.0348) | ||||
| Centralized design | −0.203*** | −0.0817** | |||
| (0.0127) | (0.0360) | ||||
| People-led | −0.295*** | −0.222*** | |||
| (0.0272) | (0.0286) | ||||
| Multiple territories | 0.129*** | 0.152*** | |||
| (0.0303) | (0.0295) | ||||
| Multiple beneficiaries | 0.276*** | 0.240*** | |||
| (0.0620) | (0.0646) | ||||
| Negotiated Tenders | −0.208*** | −0.181*** | |||
| (0.0182) | (0.0201) | ||||
| Public Administration/ICT/Social Inclusion | ✓ | ✓ | ✓ | ✓ | ✓ |
| Procurement/Grant/Capital | ✓ | ✓ | ✓ | ✓ | ✓ |
| Less Developed Regions | ✓ | ✓ | ✓ | ✓ | ✓ |
| Funding amount | ✓ | ✓ | ✓ | ✓ | ✓ |
| Constant | 0.125*** | 0.346*** | 0.309*** | 0.249*** | 0.223*** |
| (0.0444) | (0.0406) | (0.0404) | (0.0400) | (0.0437) | |
| Observations | 11,159 | 11,160 | 11,160 | 11,160 | 11,159 |
| R-squared | 0.269 | 0.268 | 0.245 | 0.250 | 0.292 |
Notes: 48 Projects (out of 14,242) are excluded from the analysis since they cannot be associated to a certain location (i.e. projects that are implemented at the national level or involving all regions of the country, or a subsample of regions that include both Less Developed Region and More Developed Region). Projects experiencing light delays are excluded from the analysis.
Robust Standard errors in parentheses *** p < 0.01, ** p < 0.05, * p < 0.1.