| Literature DB >> 35594291 |
Fengfeng Zhu1, Hao Hu1, Feng Xu1.
Abstract
Given the complexity of international construction projects (ICP), risk management difficulties commonly cause cost overruns. This paper analyzes the problems of risk interdependence and subjective ratings in the application of the traditional risk assessment model in ICP. To solve the above problems, this paper proposes a risk assessment model for ICP that considers risk interdependence and obtains references from similar projects. The model applies the Decision-Making Trial and Evaluation Laboratory (DEMATEL) to determine the risk interdependence and its contribution to the overall project risk. Moreover, this model recalls the risks, probabilities, impacts, and risk events records of similar historical projects as the necessary inputs, thereby addressing the issue of subjectivity. An integrated framework is provided to identify, analyze, and prioritize ICP risks to incorporate risk interdependence into the risk management process. Finally, this paper demonstrates and validates the proposed model through a real project. The proposed model is useful for international construction companies to support project selection and bidding decisions in the early stage of ICP.Entities:
Mesh:
Year: 2022 PMID: 35594291 PMCID: PMC9122217 DOI: 10.1371/journal.pone.0265972
Source DB: PubMed Journal: PLoS One ISSN: 1932-6203 Impact factor: 3.240
Application of MCDM methods for risk assessment in construction projects.
| MCDM methods | Brief introduction | References | Interdependence between criteria |
|---|---|---|---|
| Analytic Hierarchical Process (AHP) | AHP constructs a hierarchy and determines the weights of criteria by pairwise comparison separately. | Mustafa et al. [ |
|
| Analytic Network Process (ANP) | ANP is a generalization of AHP involving the interdependence among criteria. | Bu-Qammaz et al. [ |
|
| Best-Worst Method (BWM) [ | BWM utilizes two sets of pairwise comparisons (the best criteria with the others and the worst criteria with the others) to find the optimum proportion of weights and consistency | Luo et al. [ |
|
| Weighted Aggregated Sum Product Assessment (WASPAS) [ | WASPAS applies a joint criterion for determining the total importance of alternatives, giving weighted contribution of Weighted Sum Method (WSM) and Weighted Product Method (WPM) for a total evaluation | Dejus and Antucheviciene [ |
|
| COmplex PRoportional Assessment (COPRAS) | COPRAS ranks alternatives via obtaining their significance and utility degree. | Zavadskas et al. [ |
|
| Technique for Order Performance by Similarity to Ideal Solution (TOPSIS) | TOPSIS finds the optimal alternative with the shortest distance from the positive ideal solution and the farthest distance from the negative ideal solution simultaneously. | KarimiAzari et al. [ |
|
| Vise Kriterijumska Optimizacija I Kompromisno Resenje (VIKOR) | VIKOR chooses the compromise solution from rank lists of distance to the ideal solution. | Zolfaghari and Mousavi [ |
|
| Evaluation based on Distance from Average Solution EDAS [ | EDAS uses positive and negative distances from the average solution for appraising alternatives. | Yazdani et al. [ |
|
Fig 1Risk assessment model for international construction projects that considers risk interdependence.
Risk checklist for international construction projects.
| Risk level | Risk name | Risk events |
|---|---|---|
| Nation/Region level | Political risk | War and conflict; Regime change; Bureaucracy; Revocation of license; Nationalization and expropriation |
| Economic risk | Economic restructuring; Inflation; Interest rate change; Tax rate change | |
| Legal risk | Immature local laws; Complex procedures of planning approval | |
| Labor risk | Strong labor union; Lack of labor; Strike | |
| Market risk | Lack of materials; Lack of equipment; Lack of production factors; Poor logistics infrastructure | |
| Social risk | Bribery and corruption; Poor public security; Negative media reports | |
| Public health risk | Epidemic diseases; Lack of clean water; Poor environment; Poor medical infrastructure | |
| Trans-nation level | Multilateral policy risk | Deterioration of diplomatic relations; Trade protectionism; Lack of support for foreign investment; Lack of trade agreements; Sovereign debt restructuring |
| Capital liquidity risk | Exchange rate change; Restricted exchange; Mandatory agency; Mandatory contributions; Double taxation | |
| Material transportation risk | Import and export restrictions; Rising cost of cross-border transportation; delay in cross-border transportation; Cumbersome customs clearance procedures; Rising tariff | |
| Expatriate risk | Bilateral policy on expatriate; Local labor quotas; Work visa | |
| Standard difference risk | Different legal systems; Transnational claims and litigation; Different environmental impact assessment (EIA) requirements; Different design standards; Different construction standards; Other local special standards | |
| Cultural difference risk | Xenophobia; Religious differences; Language barrier; Cultural incompatibility | |
| Organization level | Owner risk | Strong owners; Delay in payment; Delay in site delivery; Nominated subcontractors; Engineering changes; Unilateral breach of contract; Bankruptcy |
| Partner risk | Poor performance; Poor communication; Unilateral breach of contract | |
| Contract risk | Nonstandard contract; Different language versions; Vagueness of contract condition | |
| Internal risk | Lack of key technologies; Lack of technical personnel; Lack of experience; Poor management ability; Multi-project; Poor cost estimation; High financing cost; Cash flow fracture | |
| Construction level | Health, safety, and environment (HSE) risk | Safety accident; Health damage; Environmental pollution; Security incidents like kidnapping, hijacking, etc. |
| Natural risk | Unforeseen geological conditions; Unforeseen climatic conditions | |
| Design risk | Design defects; Poor constructability; Delay in design | |
| Technical risk | Unfamiliar technologies; Poor construction organization design; Poor construction quality | |
| Human risk | Incompetence; Human error; Low efficiency; Discontent within the staff | |
| Material risk | Unfamiliar materials or equipment; Delay in materials or equipment; Poor quality of materials or equipment |
Five-point logarithmic value and range.
| Linguistic variables | Qualitative scales | Quantitative probability | Lower bound | Higher bound | Quantitative impact | Lower bound | Higher bound |
|---|---|---|---|---|---|---|---|
| Very low | 1 | 0.2% | 0 | 2% | 0.0001% | 0 | 0.01% |
| Low | 2 | 6.32% | 2% | 12% | 0.1% | 0.01% | 0.4% |
| Medium | 3 | 20% | 12% | 28% | 1% | 0.4% | 1.9% |
| High | 4 | 35.57% | 28% | 43% | 3.16% | 1.9% | 4.6% |
| Very high | 5 | 50.24% | 43% | 100% | 6.3% | 4.6% | - |
Probability and impact of the risks that occurred in similar projects.
| Risk Name | Project 1 | Project 2 | Project 3 | Project 4 | ||||
|---|---|---|---|---|---|---|---|---|
| (Under Construction) | (Completion) | (Under Construction) | (Under Construction) | |||||
| P | I | P | I | P | I | P | I | |
| Political risk | 5 | 4 | 0 | 0 | 3 | 5 | 3 | 3 |
| Economic risk | 5 | 4 | 0 | 0 | 0 | 0 | 0 | 0 |
| Legal risk | 4 | 2 | 0 | 0 | 0 | 0 | 3 | 4 |
| Labor risk | 3 | 1 | 3 | 1 | 0 | 0 | 0 | 0 |
| Market risk | 0 | 0 | 0 | 0 | 0 | 0 | 3 | 2 |
| Social risk | 5 | 1 | 0 | 0 | 5 | 2 | 5 | 1 |
| Public health risk | 2 | 5 | 0 | 0 | 2 | 3 | 3 | 3 |
| Multilateral policy risk | 0 | 0 | 0 | 0 | 2 | 5 | 0 | 0 |
| Capital liquidity risk | 5 | 4 | 5 | 4 | 0 | 0 | 5 | 3 |
| Material transportation risk | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Expatriate risk | 4 | 2 | 0 | 0 | 0 | 0 | 0 | 0 |
| Standard difference risk | 0 | 0 | 4 | 2 | 0 | 0 | 0 | 0 |
| Cultural difference risk | 0 | 0 | 4 | 3 | 4 | 1 | 0 | 0 |
| Owner risk | 4 | 3 | 5 | 5 | 4 | 2 | 0 | 0 |
| Partner risk | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Contract risk | 0 | 0 | 5 | 3 | 0 | 0 | 0 | 0 |
| Internal risk | 3 | 4 | 5 | 5 | 3 | 2 | 0 | 0 |
| HSE risk | 3 | 1 | 3 | 1 | 0 | 0 | 5 | 2 |
| Natural risk | 5 | 2 | 4 | 2 | 5 | 3 | 0 | 0 |
| Design risk | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Technical risk | 0 | 0 | 5 | 5 | 3 | 1 | 0 | 0 |
| Human risk | 5 | 1 | 3 | 2 | 0 | 0 | 0 | 0 |
| Material risk | 5 | 1 | 0 | 0 | 0 | 0 | 0 | 0 |
Analysis results of individual project risks for the target project.
| No | Risk Name | Probability | Probability Scale | Impact | Impact Scale | Expected Loss |
|---|---|---|---|---|---|---|
| 1 | Political risk | 41.99% | 4 | 3.54% | 4 | 1.48551% |
| 2 | Economic risk | 50.24% | 5 | 3.16% | 4 | 1.58866% |
| 3 | Legal risk | 33.84% | 4 | 0.44% | 3 | 0.14902% |
| 4 | Labor risk | 20.00% | 3 | 0.00% | 1 | 0.00002% |
| 5 | Market risk | 20.00% | 3 | 0.10% | 2 | 0.02000% |
| 6 | Social risk | 50.24% | 5 | 0.02% | 2 | 0.00917% |
| 7 | Public health risk | 7.57% | 2 | 4.86% | 5 | 0.36794% |
| 8 | Multilateral policy risk | 6.32% | 2 | 6.31% | 5 | 0.39905% |
| 9 | Capital liquidity risk | 50.24% | 5 | 3.00% | 4 | 1.50506% |
| 10 | Expatriate risk | 35.57% | 4 | 0.10% | 2 | 0.03557% |
| 11 | Standard difference risk | 35.57% | 4 | 0.10% | 2 | 0.03557% |
| 12 | Cultural difference risk | 35.57% | 4 | 0.67% | 3 | 0.23715% |
| 13 | Owner risk | 39.76% | 4 | 2.39% | 4 | 0.94971% |
| 14 | Contract risk | 50.24% | 5 | 3.16% | 4 | 1.58866% |
| 15 | Internal risk | 28.64% | 4 | 3.62% | 4 | 1.03802% |
| 16 | HSE risk | 26.05% | 3 | 0.02% | 2 | 0.00523% |
| 17 | Natural risk | 46.05% | 5 | 0.23% | 2 | 0.10523% |
| 18 | Technical risk | 40.16% | 4 | 4.21% | 4 | 1.68955% |
| 19 | Human risk | 40.16% | 4 | 0.03% | 2 | 0.01341% |
| 20 | Material risk | 50.24% | 5 | 0.00% | 1 | 0.00005% |
Fig 2Diagram of the initial risk network for the target case.
Result of the risk interdependence analysis.
| Risk | Interdependence Contribution | Depending Degree | Depended Degree | Centrality Degree | Cause Degree |
|---|---|---|---|---|---|
| ( | ( | ( | ( | ( | |
| Political risk | 0.490 | 1.348 | 0 | 1.348 | 1.348 |
| Economic risk | 0.211 | 0.433 | 0 | 0.433 | 0.433 |
| Legal risk | 0.203 | 0.410 | 0 | 0.410 | 0.410 |
| Labor risk | 0.111 | 0.333 | 0 | 0.333 | 0.333 |
| Market risk | 0.102 | 0.205 | 0 | 0.205 | 0.205 |
| Social risk | 0.241 | 0.889 | 0.333 | 1.222 | 0.556 |
| Public health risk | 0.157 | 0.556 | 0 | 0.556 | 0.556 |
| Multilateral policy risk | 0.167 | 0 | 0.556 | 0.556 | -0.556 |
| Capital liquidity risk | 0.610 | 0.229 | 1.314 | 1.543 | -1.086 |
| Expatriate risk | 0.056 | 0.167 | 0 | 0.167 | 0.167 |
| Standard difference risk | 0.065 | 0.194 | 0 | 0.194 | 0.194 |
| Cultural difference risk | 0.096 | 0.481 | 0 | 0.481 | 0.481 |
| Owner risk | 0.657 | 0.371 | 0.886 | 1.257 | -0.514 |
| Contract risk | 0.056 | 0.167 | 0 | 0.167 | 0.167 |
| Internal risk | 0.389 | 0.167 | 0.167 | 0.333 | 0 |
| HSE risk | 0.389 | 0.167 | 1.111 | 1.278 | -0.944 |
| Natural risk | 0.519 | 0.556 | 0 | 0.556 | 0.556 |
| Technical risk | 0.333 | 0 | 0.898 | 0.898 | -0.898 |
| Human risk | 0.333 | 0 | 1.185 | 1.185 | -1.185 |
| Material risk | 0.167 | 0 | 0.222 | 0.222 | -0.222 |
Results for the expected loss, significance index, and corresponding ranks.
| Risk name | Expected Loss | Significance Index | EL Ranking | SI Ranking | Risk events in similar projects |
|---|---|---|---|---|---|
| (×10−7) | (×10−7) | ||||
| Political risk | 148551.27 | 72808.46 | 5 | 2 | Bureaucracy |
| Economic risk | 158865.65 | 33538.3 | 2 | 6 | Inflation |
| Legal risk | 14901.81 | 3027.67 | 11 | 11 | Complex procedures of planning approval |
| Labor risk | 2 | 0.22 | 20 | 20 | Many different local labor unions |
| Market risk | 2000 | 203.17 | 15 | 17 | Lack of materials (e.g., steel) |
| Social risk | 917.34 | 220.84 | 17 | 15 | Poor public security; Negative media reports |
| Public health risk | 36793.61 | 5791.59 | 9 | 9 | Delay due to COVID-19 |
| Multilateral policy risk | 39905.25 | 6650.87 | 8 | 8 | Trade protectionism; Lack of support for foreign investment |
| Capital liquidity risk | 150505.8 | 91736.87 | 4 | 1 | Adverse change in the exchange rate |
| Expatriate risk | 3556.56 | 197.59 | 13 | 18 | Difficulty in applying for the work visa; Lower foreign labor quotas |
| Standard difference risk | 3556.56 | 230.52 | 13 | 14 | Different construction standards |
| Cultural difference risk | 23714.54 | 2268.98 | 10 | 12 | Religious differences (local workers do not participate in the construction during Hajj and Ramadan) |
| Owner risk | 94971.49 | 62409.83 | 7 | 3 | Delay in site delivery; Nominated subcontractors; Engineering changes; Delay in payment |
| Contract risk | 158865.65 | 8825.87 | 2 | 7 | Nonstandard contract; Different language versions |
| Internal risk | 103801.92 | 40367.41 | 6 | 5 | Poor cost estimation |
| HSE risk | 523.23 | 203.48 | 18 | 16 | Environmental pollution (e.g. wildlife habitat involved) |
| Natural risk | 10523.31 | 5456.53 | 12 | 10 | Extreme high temperature; Sand storm |
| Technical risk | 168955 | 56318.33 | 1 | 4 | Poor construction organization design; |
| Human risk | 1341.42 | 447.14 | 16 | 13 | Low efficiency |
| Material risk | 5.02 | 0.84 | 19 | 19 | Delay in materials and equipment |
List of response measures for the target project.
| No | Measure Description | Classification |
|---|---|---|
| 1 | Check the terms one by one in FIDIC format to avoid ambiguity in different languages; Clarify contractor’s rights in the EPC contract. | Transfer |
| 2 | Purchase Chinese Export Credit Insurance to transfer the risk of owner bankruptcy, government prohibition or restriction of exchange, deferred payment order, war, revolution, and riot; Purchase other insurance specified in the contract. | Transfer |
| 3 | Remain strictly politically neutral in local government and parliament; Remain strictly politically neutral in different parties; Maintain communications with local chiefs. | Mitigation |
| 4 | Determine the payment option in advance; Open an offshore account in advance; Check the bilateral investment protection agreement between China and Ghana in advance. | Mitigation |
| 5 | Hire more local workers; Allocate schedule reserves to account for possible religious holidays of local workers. | Mitigation |
| 6 | Maintain communications with local labor unions; Sign a package contract to specify the minimum wage, salary increase range, etc.; Hire a local person to deal with labor disputes | Mitigation |
| 7 | Select efficient subcontractors | Mitigation |
| 8 | Maintain communications with residents; take actions to improve the community environment to avoid residents’ protests against the construction. | Mitigation |
| 9 | Pay attention to environmental protection and wildlife protection within the scope of the construction site. | Mitigation |
| 10 | Maintain communications with local media; Set up a website for information disclosure to avoid misunderstanding | Mitigation |
| 11 | Clarify the price and availability of local materials and equipment; Consider the time and cost of international transportation in the contract. | Mitigation |
| 12 | Retain the change orders from the owner in case of claims; Select an appropriate place of arbitration | Mitigation |
| 13 | Maintain communications with the Chinese medical team stationed in Ghana; Bring the necessary medications; Vaccinate Chinese employees before going abroad | Mitigation |