| Literature DB >> 35529306 |
Prakash S1, Angel Rajan Singh1, Sidhartha Satpathy1, Jean Patrice Khoshbin2.
Abstract
Aim Healthcare infrastructure projects are a requirement for the progress of the country. The aim of this study was to identify major completed healthcare infrastructure projects in a tertiary teaching hospital in Northern India and to find out the various factors that influenced the success or failures and the cost and time overrun during the project implementation. Materials and methods Periodical review meetings were conducted, right from the planning to the execution and commissioning of these projects. All these had been documented as minutes of the meetings, and the records of the same had been maintained. The study comprised of studying all these documents in detail and finding an answer to the research questions. Results Four major completed projects of a tertiary medical institute of India, All India Institute of Medical Sciences (AIIMS), New Delhi, India, were studied. These were the new Outpatient Department (OPD) Block, Burns and Plastic Surgery Block (BPS), Maternal and Child Health Block (MCH), and National Cancer Institute (NCI). Our study revealed that there was no dearth of funds, and hence, there was no cost overrun in any of the projects. Whenever the funds had to be reworked, the funds that were asked for were released. However, there was a considerable time overrun in all the projects ranging from about one to four years. The various reasons that could be attributed to this are the delay in obtaining statutory clearances, political interference, communication hurdles, improper planning, introducing a project officer late into the project, safety concerns, and the COVID-19 pandemic. Conclusions This study focuses mainly on the very important hurdles that were faced during the implementation of the projects and tries to suggest an average time frame for various activities for project implementation in a healthcare project in the Indian scenario. This can be taken as blueprints while planning newer healthcare projects of this magnitude.Entities:
Keywords: healthcare project management; infrastructure; planning; statutory requirements for hospital constructions; time overrun
Year: 2022 PMID: 35529306 PMCID: PMC9072285 DOI: 10.7759/cureus.24684
Source DB: PubMed Journal: Cureus ISSN: 2168-8184
Costs incurred on the projects
| Projects | Cost (in million INR) |
| Burns and Plastic Surgery Block (BPS) | 2478.5 |
| Maternal and Child Health Block (MCH) | 7258.4 |
| New Rajkumari Amrit Kaur OPD (New RAK) | 5729.9 |
| National Cancer Institute (NCI) | 20,350 |
Summary of various hurdles faced during the implementation of the projects
| Phase | Project stage | Hurdles |
| Prerequisites | Finances | Finances were never a hurdle for the projects. In fact, good meticulous planning had been done for the planning of all the projects, and there was never any delay in the release of funds. The only issues that have been highlighted were that in some cases, the consultant party had delayed the handing over of money to the contractors, which had to be tackled. |
| Site selection | This was a major hurdle in two of the projects, i.e., the National Cancer Institute (NCI) and the Burns and Plastic Surgery Block. Also, political interference played an important role in the execution of manpower of the projects. | |
| Statutory requirements | Most of the delays anticipated were because of the delay in obtaining many of the statutory clearances from various bodies, such as the Archaeological Survey of India (ASI), Environmental Impact Assessment (EIA) clearance, Director General Civil Aviation (DGCA) clearance, and water and electricity clearances. | |
| Planning | Planning | When we go through the observations, it is noticed that almost all the hurdles faced during the construction phase were because most of the planning was poorly done, without taking all the stakeholders into confidence. This led to most of the changes in plans, and hence, there were fines that were levied. |
| Human resources | Human resources were not planned properly as at times there were no proper recruitment rules framed, or they were framed arbitrarily without taking into consideration the number of staff for similar posts in various other hospitals or without a proper framework or norms. | |
| Project officer | Qualified project officers were brought in the middle of the projects. The study of these projects has thrown light on the importance of such a person to steer the projects in the right direction. Without one such person unifying the command, coordinating it, and providing direction, projects were going haywire under multiple leadership. | |
| Execution | Safety measures | Incidents of accidents that led to litigations and compensations were noted, which also led to time lost in inquiries. |
| Regular supervision and communication with the stakeholders | Weekly follow-up, monthly meetings with the stakeholders, quarterly meetings at the institute levels, and yearly supervision by the government were some of the good salient features of the project execution. | |
| COVID-19 pandemic | The COVID-19 pandemic played a dual role in the project implementation. Although at one stage it did halt the progress of the projects because of the nonavailability of manpower and materials, at the same time, there was immense pressure from the government to complete and start these hospitals on a war footing as these would add further beds to the country during the pandemic. The bureaucracy did help by giving concessions in the lockdown for faster execution of the projects. |
Area and number of floors vis-à-vis the time taken for construction
G: ground floor, B: basement, BPS: Burns and Plastic Surgery Block, MCH: Maternal and Child Health Block, New RAK OPD: New Rajkumari Amrit Kaur Outpatient Department (Dr. Rajkumari Amrit Kaur was the first Health Minister of India), NCI: National Cancer Institute
| Block/center | Floors | Area | Total period of construction (proposed) | Actual period of construction |
| BPS | G+3B+8 | 24,027 m2 | 24 months | 36 months |
| MCH | G+3B+8 | 45,352 m2 | 24 months | 73 months |
| New RAK OPD | G+3B+8 | 93,352 m2 | 40 months | 56 months |
| NCI | Most of the buildings have G+2B+5 floors | 252,000 m2 (which includes 100,207 m2 of residential dwellings) | 45 months | 60 months |
Figure 1Comparison between the expected and the actual period of the projects (in months)
BPS: Burns and Plastic Surgery Block, MCH: Maternal and Child Health Block, New RAK OPD: New Rajkumari Amrit Kaur Outpatient Department (Dr. Rajkumari Amrit Kaur was the first Health Minister of India), NCI: National Cancer Institute
Figure 2Timeline chart showing the progress of the pace of work (work completed in percentage at the end of the year) for the basic infrastructure (data collected from the yearly progress meeting presented to the Prime Minister’s Office)
BPS: Burns and Plastic Surgery Block, MCH: Maternal and Child Health Block, RAK: New Rajkumari Amrit Kaur Outpatient Department, NCI: National Cancer Institute
Average period of milestones for different activities (expected vis-à-vis actual) and the delay
| Milestone | Duration of activity (planned (average)) | Average time (actual) | Average delay |
| Concept design and development | 1 month | 3 months | 2 months |
| Approval of concept | 1 month | 1 month | Nil |
| Submission for Environment Impact Assessment (EIA) clearances | 1 month | 2 months | 1 month |
| Detailed preparation of drawings – architectural, structural, electrical, plumbing, services, landscaping, and elevators | 3 months | 3 months | Nil |
| EIA clearances | 3 months | 20 months | 17 months |
| Height clearance | 1 month | 3 months | 2 months |
| Pollution control board clearance | 1 month | 2 months | 1 month |
| Clearance from Green Tribunal | 1 month | 1 month | Nil |
| Water requirement | 1 month | 6 months | 5 months |
| Electricity requirement | 1 month | 8 months and permanent meter obtained after handing over | 7 months |
| Archaeological Survey of India clearance | 15 days | 2 months | 45 days |
| Submission and drawing of approval from local bodies and the Atomic Energy Regulatory Body (AERB) and Geotechnical Survey (soil testing) | 2 months | 12 months | 10 months |
| Preparation of tender documents | 2 months | 6 months | 4 months |
| Tendering and award of work | 3 months | 8 months | 5 months |
| Actual construction | 3200 m2/month | 1800 m2/month | |
| Equipment | During the process of construction | During the process of construction | |
| Furniture | 6 months | 12 months | 6 months |
| Manpower | 12 months | 36 months | 24 months |
| IT work | 6 months | 12 months | 6 months |
| Handing over | 1 month | 1 month | Nil |
| Fire clearance | At the start, in between, and in the end | Approximately takes 15 days if no omissions are found |