| Literature DB >> 35323798 |
Daniel Janowitz1, Sophie Groche1,2, Süleyman Yüce1,3, Thomas Melin3, Thomas Wintgens2.
Abstract
The Middle East will face tremendous water scarcity by 2050, which can only be mitigated by large-scale reverse osmosis seawater desalination. However, the coastal land in the region is rare and costly, so outsourcing the desalination facility to artificial islands could become a realistic scenario. This study investigated the ecological and economic challenges and possible advantages of that water supply option by analysing conceptual alternatives for offshore membrane-based desalination plants of up to 600 MCM/y capacity. Key environmental impacts and mitigation strategies were identified, and a detailed economic analysis was conducted to compare the new approach to state-of-the-art. The economic analysis included calculating the cost of water production (WPC) and discussing the differences between offshore alternatives and a conventional onshore desalination plant. In addition, the study investigated the impact of a changing energy mix and potential carbon tax levels on the WPC until 2050. The results indicate that offshore desalination plants have ecological advantages compared to onshore desalination plants. Furthermore, the construction cost for the artificial islands has a much lower effect on the WPC than energy cost. In contrast, the impact of potential carbon tax levels on the WPC is significant. The specific construction cost ranges between 287 $/m2 and 1507 $/m2 depending on the artificial island type and distance to the shoreline, resulting in a WPC between 0.51 $/m3 and 0.59 $/m3. This work is the first to discuss the environmental and economic effects of locating large-scale seawater desalination plants on artificial islands.Entities:
Keywords: arid regions; artificial islands; carbon tax level; cost-efficiency; environmental impact; large-scale desalination; offshore desalination; renewable energy; seawater reverse osmosis membranes; water scarcity
Year: 2022 PMID: 35323798 PMCID: PMC8953854 DOI: 10.3390/membranes12030323
Source DB: PubMed Journal: Membranes (Basel) ISSN: 2077-0375
Figure 1Map of the region including the considered areas for new desalination plants investigated in the SALAM initiative and a zoom-in on the study relevant alternatives No. 2 and No. 3 next to Shavei Zion.
Alternatives for marine structures for large-scale desalination plants next to Shavei Zion.
| Alternatives | Water Depth | Crest Height of the Structure |
|---|---|---|
| No. 1—Artificial Island | −5 m | +8 m |
| No. 2—Artificial Island | −12 m | +14 m |
| No. 3—Artificial Island | −30 m | +14.4 m |
Figure 2Conceptual cross-section design of alternative No. 3—5 km offshore −30 m water depth [33].
Figure 3Desalination project context on the artificial islands.
Figure 4Simplified flow chart of two-pass reverse osmosis desalination with energy recovery.
Technical parameters for the reverse osmosis desalination plant.
| Parameter | Value | Unit |
|---|---|---|
| Type | BOT project | |
| Capacity | 600 | MCM/y |
| Availability | >95 | % |
| Feed TDS | 40,500 | ppm [ |
| Permeate TDS | 300 | ppm [ |
| Recovery rate | ~45 | % [ |
| Energy demand | 3 | kWh/m3 [ |
Figure 5The main influences on the water production cost.
Essential parameters for the economic assessment.
| Parameter | Value | Unit |
|---|---|---|
|
| ||
| Share of sponsoring/equity from total capital costs | 10 | % |
| BOT contract/funding period | 25 | years [ |
| Sum interest rate and repayment rate | 5 | % |
|
| ||
| Maintenance and repair desalination plant | 3 | % |
| Maintenance and repair infrastructure (onshore) | 1 | % |
| Maintenance and repair infrastructure (offshore) | 2 | % |
|
| ||
| Chemicals | 0.03 | $/m3 [ |
| Replacement of membranes and cartridge filters | 0.04 | $/m3 [ |
| Waste disposal | 0.017 | $/m3 [ |
Figure A1Detailed cost table for the economic analysis—onshore desalination.
Figure A2Detailed cost table for the economic analysis—Alternative No. 1.
Figure A3Detailed cost table for the economic analysis—Alternative No. 2.
Figure A4Detailed cost table for the economic analysis—Alternative No. 3.
Variation in the energy mix and assumed Levelized Cost of Energy (LCOE).
| Parameter | Value | Value | Value | Unit |
|---|---|---|---|---|
| Share of | 30 | 65 | 100 | % |
| LCOE PV | 0.03 [ | 0.015 [ | 0.01 [ | $/kWh |
| LCOE PV + | 0.12 [ | 0.11 | 0.10 | $/kWh |
| Total LCOE | 0.03 | 0.066 | 0.073 | $/kWh |
| LCOE CCPP | 0.06 | 0.06 | 0.06 | $/kWh |
Cost estimate for the artificial island—Alternative No. 3.
| Cost Item | Volume (m3) | Unit Price ($/m3) | Total Cost ($) |
|---|---|---|---|
| Reclamation fill | 9,800,230 | 15 | 147,003,450 |
| Core fill | 7,652,648 | 15 | 114,789,720 |
| Filter layer (0.4–2 ton) | 953,964 | 35 | 33,388,740 |
| Filter layer (4–6 ton) | 796,019 | 35 | 27,860,665 |
| Armour (24 m2 Accropode) | 303,998 | 120 | 36,479,760 |
| Toe structure (10–12 ton) | 297,116 | 50 | 14,855,800 |
| Back Armour (10–12 ton) | 202,760 | 50 | 10,138,000 |
| Direct investment cost | - | - | 384,516,135 |
| Indirect investment cost | 35 | % | 134,580,647 |
|
|
|
Cost estimate for land reclamation: Alternative No. 1.
| Cost Component | Volume (m3) | Unit Price ($/m3) | Total Cost ($) |
|---|---|---|---|
| Reclamation fill | 3,393,600 | 10 | 33,930,600 |
| Core fill | 1,074,222 | 10 | 10,742,220 |
| Filter layer (0.4–2 ton) | 263,391 | 20 | 5,267,820 |
| Filter layer (4–6 ton) | 202,652 | 20 | 4,053,040 |
| Armour (18 m3 Accropode) | 120,087 | 120 | 14,410,440 |
| Toe (4–6 ton) | 50,479 | 35 | 1,766,765 |
| Back Armour (10–12 ton) | 74,094 | 40 | 2,963,760 |
| Direct investment cost | - | - |
|
| Indirect investment cost | 35 | % |
|
|
|
|
Cost estimate for the artificial island: Alternative No. 2.
| Cost Item | Volume (m3) | Unit Price ($/m3) | Total Cost ($) |
|---|---|---|---|
| Reclamation fill | 5,421,158 | 15 | 81,317,370 |
| Core fill | 2,705,163 | 15 | 40,577,445 |
| Filter layer (0.4–2 ton) | 536,505 | 35s | 18,777,675 |
| Filter layer (4–6 ton) | 382,045 | 35 | 13,371,575 |
| Armour (18 m3 Accropode) | 229,489 | 120 | 27,538,680 |
| Toe (4–6 ton) | 65,696 | 35 | 2,299,360 |
| Back Armour (10–12 ton) | 202,760 | 50 | 10,138,000 |
| Direct investment cost | - | - | 194,020,105 |
| Indirect investment cost | 35 | % | 67,907,037 |
|
|
|
Data of comparable artificial islands projects based on rubble mound breakwaters.
| Artificial Island | Construction Cost per Square Meter (2022) | Water Depth | Project | Location |
|---|---|---|---|---|
| Alternative No. 1 | ~287 $/m2 | −10 m | Rectangular Shape | North Haifa, Israel |
| Alternative No. 2 | ~760 $/m2 | −12 m | Rectangular Shape | North Haifa, Israel |
| Alternative No. 3 | ~1507 $/m2 | −30 m | Rectangular Shape | North Haifa, Israel |
| Upper Zakum Field | ~469 $/m2 *2 | −6 m to −13 m | Falcon-shaped, 2011–2014 | Abu Dhabi, UAE |
| Sateh Al Razboot oilfield (constructed) [ | - | −13 m to −15 m | Falcon-shaped, 2011–2013 | Abu Dhabi, UAE |
| Artificial Island North Sea Wind Power Hub (planned) [ | ~333 $/m2 | −18 m | Expected Realisation | Middle of North Sea between Europe and the United Kingdom |
| Artificial Island for an airport offshore Tel Aviv | ~1395 $/m2 *1 | ~−19.5 m | Rectangular Shape | Tel Aviv, Israel |
*1 adjusted value using 55% inflation rate from 2002 to 2022. *2 adjusted value using 25% inflation rate from 2011 to 2022.
Direct investment costs for all offshore alternatives including piping and the marine structures.
| Alternative | Intake Piping *1 | Outfall Piping *1 | Product Piping *1 | Piping ($) + Structure ($) = Total Cost ($) |
|---|---|---|---|---|
| No. 1—Artificial Island | 1 km | 2 km | Discharge already | ~53 Mio. $ + ~73 Mio. $ = 126 Mio. $ |
| No. 2—Artificial Island | Intake | 1 km | 1 km | ~34 Mio. $ + ~194 Mio. $ = 228 Mio. $ |
| No. 3—Artificial Island | Intake | Outfall | 5 km | ~83 Mio. $ + ~385 Mio. $ = 468 Mio. $ |
*1 The cost for the HDPE pipes was estimated concerning plant modules with a capacity of 200 MCM/y. For 400 MCM/y intake ~ 3 × 1800 mm OD pipes, for 200 MCM/y brine outfall ~ 2 × 1400 mm OD pipes, for 200 MCM/y product water transport ~ 2 × 1400 mm OD pipes.
Figure 6Comparison of the specific water production cost for all alternatives.
Figure 7Comparison of water production cost varying the carbon tax level for Alternative No. 3.
Figure 8Comparison of the specific water production cost varying the share of renewable energy for alternative No. 3.
Figure 9Expected beach profile of an offshore structure close to the coastline (extreme scenario) [33].
Figure 10Fish return system adapted from [76].
Figure 11Heatmap for the environmental assessment of the alternatives.