Sintayehu D Kebede1, Zhang Tiewei1.
Abstract
Time, money, and quality are the three basic criteria for measuring construction project efficiency. The Ethiopian construction sector in general and public work projects, in particular, are believed to suffer from inefficiencies despite their quantitative growth in recent years. Previous researches have made attempts to explore factors determining the efficiency of the sector such as the low capacity of contractors (both financial and equipment, shortage of skilled human resource on technical, managerial, and entrepreneurial skills, etc…), the poor performances of the supply chain, inflation in the economy and so on. However, process and system-based challenges of the sector resulting from the existing legal frameworks governing the sector such as the modes of delivery of projects (modes of contracting) have not been a subject of extensive study. In this study, doctrinal and non-doctrinal legal research methods are employed to explore project delivery system(s) recognized in Ethiopia's public work contract laws and appraise their efficiency in terms of ensuring prompt completion of public construction projects. The doctrinal aspect of the research exposed that, despite an implied recognition of Design-Build (DB) and its variant forms of project delivery system, the country's public work contract laws set up Design-Bid-Build (DBB) as a default mode of contracting. Besides, the result from a survey questionnaire of 158 respondents which was computed by using Research Package for Social Sciences (SPSS) to generate the Relative Importance Index (RII) of each mode of contracting corroborated by primary data derived from the completion and status report of 40 road and 9 building projects, shows that even though construction project time overrun (delay) often happens in both routes of contracting, the magnitude of such inefficiency is greater in public projects of DBB than DB delivery mode.Entities:
Keywords: Construction project time overrun; Design-bid-build; Design-build; Project delivery system; Public work contracts
Year: 2021 PMID: 33763614 PMCID: PMC7973297 DOI: 10.1016/j.heliyon.2021.e06462
Source DB: PubMed Journal: Heliyon ISSN: 2405-8440
Population characteristics.
| SN | Respondent's Demography | Qualifications | # of Respondents | Percentage |
|---|---|---|---|---|
| 1 | Based on an academic level | Diploma | 3 | 1.8% |
| First degree (BSc) | 100 | 63.4% | ||
| Second Degree (MSc) | 55 | 34.6% | ||
| Third Degree (Ph.D.) | None | None | ||
| 2 | Based on years of work experience | 0–5 years | 22 | 13.79 |
| 5–10 years | 54 | 34.18% | ||
| 10–15 years | 39 | 24.45% | ||
| Over 15 years | 43 | 27.58% | ||
| 3 | Based on professional qualification | Office Engineers | 33 | 20.8% |
| Site Engineers | 19 | 11.6% | ||
| Project Managers | 34 | 21.3% | ||
| Designers and consultants | 69 | 43.7% | ||
| Client project Engineers and others | 6 | 3.5% |
RII computed based on the response of participant's with different years of work experience.
| Experience | PDS | Number of Response | #of Respondents | RII | Rank | ||||
|---|---|---|---|---|---|---|---|---|---|
| Very low | Low | Medium | High | Very high | |||||
| Below 5 years | DBB | 4 | 5 | 8 | 5 | 0 | 22 | 0.445455 | 2 |
| DB | 0 | 5 | 11 | 6 | 0 | 22 | 0.472727 | 1 | |
| 5–10 years | DBB | 0 | 0 | 11 | 25 | 18 | 54 | 0.981481 | 1 |
| DB | 10 | 36 | 5 | 0 | 3 | 54 | 0.359259 | 2 | |
| 10–15 years | DBB | 0 | 0 | 9 | 20 | 9 | 38 | 0.973684 | 1 |
| DB | 3 | 23 | 6 | 6 | 0 | 38 | 0.478947 | 2 | |
| More than 15 years | DBB | 3 | 3 | 8 | 22 | 8 | 44 | 0.922727 | 1 |
| DB | 6 | 14 | 5 | 14 | 5 | 44 | 0.713636 | 2 | |
The aggregate RII.
| PDS | Number of Response | #of Respondents | RII | Rank | ||||
|---|---|---|---|---|---|---|---|---|
| Very low | Low | Medium | High | Very high | ||||
| DBB | 7 | 8 | 36 | 72 | 35 | 158 | 0.888608 | 1 |
| DB | 19 | 78 | 27 | 26 | 8 | 158 | 0.502532 | 2 |
DBB road projects contract duration and project status in percentage.
| No | Project Name | Initial Contract period | Completion (Yes/No) | Revised contract Period | EOT in % |
|---|---|---|---|---|---|
| 1 | Ageremariam – Yabelo | May 2011 to 10 May 2014 | No | May 2011 to Nov. 2015 | 52.05% |
| 2 | Aposto-Wondo-Negele | Apr. 2009 to Apr.2012 | No | Apr.2009 to Jun. 2014 | 85.84% |
| 3 | Arbaminch-Kemba-Sawla contract I | April. 2010 to Apr.2013 | No | April. 2010 to Aug. 2016 | 110.95% |
| 4 | Arbaminch-Kemba-Sawla Lot II | Sep. 2011 to sep.2014 | No | Sep. 2011 to July, 2017 | 94.52% |
| 5 | Arbereketi-Gelemso | May 2015 to May 2018 | No | May 2015 to May 2019 | 33.33% |
| 6 | Ayra - Chanka | Jul. 2011 to Apr. 2014 | No | Oct. 2011 to Dec. 2015 | 68.24% |
| 7 | Chanka- Dembidolo | Jul. 2011 to Apr. 2014 | No | Oct. 2011 to Feb.2016 | 72.52% |
| 8 | Dansha-Abderafi- Maikadra | Dec. 2013 - Dec 2016 | Yes | No changes | ---- |
| 9 | GedoBako-Nekemte | Jan. 2010 to Jan. 2014 | No | Jan. 2010 to Jun. 2014 | 35.7% |
| 10 | Gelemso-Mechara-Micheta | Nov. 2015 to Nov. 2018 | No | Nov. 2015 to Feb. 2019 | 8.21% |
| 11 | Kong – Begondi – Wombera | Jan. 2013 to Jan. 2016 | No | Jan. 2013 to May 2019 | 110.95% |
| 12 | Mekenajo-Ayra | Jul. 2011 to Apr. 2014 | No | Oct. 2011 to Jun. 2015 | 46.15% |
| 13 | Otolo-Sawla lot III | Sep. 2011 to Sep. 2014 | No | Sep. 2011 to Nov.2016 | 72.14% |
| 14 | Sawla-Kako | Sep. 2011 to Mar. 2014 | No | Sep.2011 to Sep.2014 | 19.78% |
| 15 | Sembo – Sholagebeya – | Jan. 2010 to May 2013 | No | Jan. 2010 to May 2016 | 100% |
| 16 | ShambuBako | Jul. 2016 to Jul. 2019 | No | No changes | --- |
Status of DBB road projects with original contract period extending to 2020.
| N | Project Name | Original Completion Date | Project Status till the end of Jul. 2019 | Lapsed contract period | Slippage of work |
|---|---|---|---|---|---|
| 1 | Afdera-Irebti Junction-Ertale Junction-Ahmed Ela | May 2017 to May 2020 | 29.15% | 72.15% | 43% |
| 2 | Babile - Fik Lot I | May 2017 to May 2020 | 43.68% | 74.34% | 31% |
| 3 | Babile - Fik: Lot III | May 2017 to May 2020 | 52.78 % | 72.4% | 20% |
| 4 | Babile - Fik: Lot IV | May 30, 2017 May 2020 | 70.28% | 72.14% | 2.14% |
| 5 | Babile-Fik, Lot II | May 2017 to May 2020 | 43.68 % | 72.4% | 31 % |
| 6 | Chereti- Hagermekor | Apr. 2017 to Apr. 25, 2020 | 67.69% | 73.97% | 6.28% |
| 7 | Ertale Junction – Ahmeela | May 2017 to May 2021 | 34.12% | 77.62% | 43.12% |
| 8 | Fik-Hamero-Imi | May 2017 to May 2020 | 61.69% | 72.95% | 11.26% |
| 9 | Jigjiga–Gelelesh-Degahamedo-Segeg Con.1 | May 2017 to May 2020 | 73.18% | 74.89% | 1.71% |
DB road projects contract duration and project status in percentage.
| No | Project Name | Initial Contract period | Completion (Yes/No) | Revised Contract | EOT in % |
|---|---|---|---|---|---|
| 1 | Dallol-MusliBada | Jan.2016 to Jan.2019 | No | No revision | --- |
| 2 | Dejen-Felegebirhan | Aug. 2011 to Feb. 2015 | No | Aug.2011 to Apr. 2018 | 90.03% |
| 3 | DichotoGalafi Junction – | Oct. 2015 to Jan. 2019 | No | Oct. 2015 to Jul. 2019 | 15.29% |
| 4 | Dire Dawa – Dewelle | Oct. 2014 to Sep. 2017 | No | Oct. 2014 to Nov. 2018 | 37.53% |
| 5 | F6 Junction | Dec.2014 to Dec. 2017 | On-time | No changes | --- |
| 6 | Fendika-Ayma | Dec. 2012 to Jun. 2015 | No | Dec. 2012 to Jun 2017 | 78.97% |
| 7 | Hargele-Dolobay-Dolo | Sep. 2011 to Aug. 2013 | 22% ahead of time | No Changes | --- |
| 8 | Jinka – Medir | Feb. 2016 to Feb.2018 | No | Feb.2016 to Nov 2019 | 91.66% |
| 9 | Koka-Adulala- Debrezeit | Mar. 2015 to Mar. 2017 | No | Oct. 2014 to Nov. 2018 | 29.31 |
| 10 | May Tsebri-Dima – | Jun. 2014 to Jun. 2017 | Ahead of Schedule | No changes | --- |
| 11 | Moricho – Dimtu – | Dec.2014 to Jun. 2017 | No | Mar. 2015 – Jan. 2018 | 18.72% |
| 12 | Moricho- Dimtu-Bitena- Sodo | Dec. 2014to Aug. 2018 | On time | No changes | --- |
| 13 | Omo-F6 junction | Dec. 2014 to Dec 2017 | Yes | No changes | --- |
| 14 | Robe-Gassera | Nov. 2017 to Oct. 2020 | 25.45 slippage | No revision | --- |
| 15 | Sawla-Maji | Aug. 2011to Aug.2014 | No | Aug. 2011 to Jan. 2018 | 144% |
DBB projects status after EOT, time overrun, and/or slippage of work.
| No | Project Name | Revised Contract Period | Date when the report was made | Project status at/after EOT | Time overrun after EOT | Slippage of work |
|---|---|---|---|---|---|---|
| 1 | Ageremariam – Yabelo | May 2011 to Nov. 2015 | Oct. 2017 | 100% | 6.28% | 0% |
| 2 | Aposto-Wondo-Negele Con.1 | Apr.2009 to Jun. 2014 | Jun.2015 | 98.74% | 8.10% | 1.26 |
| 3 | Arbaminch-Kemba-Sawla contract I | April.2010 to Aug. 2016 | Jun. 2019 | 94.91% | 47.23% | 5.09% |
| 4 | Arbaminch-Kemba-Sawla | Sep. 2011 to July 2017 | June 2017 | 90.10 | 0% | 9.84% |
| 5 | Arbereketi-Gelemso | May 2015 to May 2019 | Jul. 2019 | 66.23 % | 4.45% | 33.77 |
| 6 | Ayra – Chanka | Jul.2011 to Dec. 2015 | May 2017 | 100% | 0% | 0% |
| 7 | Chanka- Dembidolo | Jul.2011to Oct.2015 | Oct. 2016 | 100% | 17.19% | 0% |
| 8 | Dansha - Abderafi – Maikadra | Dec. 2013 -Dec 2016 | Apr. 2018 | 100% | 0% | 0% |
| 9 | GedoBako-Nekemte Con.2 | Jan. 2010 to Jun. 2014 | Aug.2014 | 99.4% | 0% | 0.6% |
| 10 | Gelemso-Mechara-Micheta | Nov. 2015 to Feb. 2019 | Jul.2019 | 56.53% | 12.65% | 43.47 |
| 11 | Kong – Begondi – Wombera | Jan. 2013 to May 2019 | Jul. 2019 | 82% | 2.6% | 18% |
| 12 | Mekenajo-Ayra | Jul. 2011 to Dec. 2015 | Jan.2016 | 100% | 6.76% | 0% |
| 13 | Otolo-Sawla lot III | Sep. 2011 to Nov.2016 | Apr. 2017 | 98.31 | 7.95% | 1.61 |
| 14 | Sawla-Kako | Sep.2011 to Nov. 2014 | Jan. 2016 | 89.84% | 44.75% | 10.16 |
| 15 | Sembo – Sholagebeya – | Jan. 2010 to May 2016 | Dec. 2018 | 94.63% | 40.78% | 5.5% |
| 16 | Shambu- Bako | Jul. 2016 to Jul. 2019 | Jul. 2019 | 84.33% | 0% | 16% |
DB projects status of after EOT, time overrun, and/or slippage of work.
| No | Project Name | Revised Contract Period | Date when the report was made | Project status at the date of the report | Time overrun | Slippage of work |
|---|---|---|---|---|---|---|
| 1 | Dallol-MusliBada | Jan.2016 to Jan.2019 | Jul. 2019 | 86.14 | 16.43% | 13% |
| 2 | Dejen-Felegebirhan | Aug.2011 to Apr. 2018 | Sep. 2018 | 94.6 | 7.5 | 5.4% |
| 3 | DichotoGalafi Junction - Elidar – Belho | Oct. 2015 to Jul. 2019 | Jul. 2019 | 90.7% | 0% | 9.3% |
| 4 | Dire Dawa – Dewell | Oct. 2014 to Nov. 2018 | Feb. 2019 | 97.38% | 0% | 2.62% |
| 5 | F6 Junction – F4 Junction | Dec.2014 to Dec. 2017 | Nov. 2017 | 98.32 | 0% | 0% |
| 6 | Fendika-Ayma | Dec. 2012 to Jun 2017 | Jan 2018 | 100% | 0% | 0% |
| 7 | Hargele-Dolobay-DoloOdo | Sep. 2011 to Dec.2012 | May 2016 | 100% | 0% | 0% |
| 8 | Jinka – Medir | Feb.2016 to Nov 2019 | Jul. 2019 | 43% | 0% | 57% |
| 9 | Koka-Adulala- Debrezeit | Oct. 2014 to Nov. 2018 | May 2018 | 99.53% | 0% | 0.47% |
| 10 | May Tsebri-Dima - FiyelWuha-AbiAdi | Jun. 2014 to Jun. 2017 | May 2017 | 97% | 0% | 0% |
| 11 | Moricho – Dimtu – Bitena – Sodo | Mar. 2015 – Jan. 2018 | Aug. 2018 | 99.27% | 0% | 0.83% |
| 12 | Moricho- Dimtu- Bitena- Sodo | Dec. 2014to Aug. 2018 | Nov. 2018 | 99.7% | 0% | 0.83% |
| 13 | Omo-F6 junction | Dec. 2014 to Dec 2017 | Nov. 2017 | 99.6% | 0% | 0% |
| 14 | Robe-Gassera | Nov. 2017 to Oct. 2020 | Jul. 2019 | 32.81% | -- | 25.45% |
| 15 | Sawla-Maji | Aug. 2011 to Jan. 2018 | Dec. 2018 | 89.66% | 0% | 10.34% |
Project status of DBB public building projects within the original contract period.
| No | Project Name | Initial Contract period | Completed or not (yes/no) | Revised | EOT in % |
|---|---|---|---|---|---|
| 1 | Research Center and Conference Hall (main contract) | May 2010 to Dec. 2011 | No | May 2010 to Jan. 2013 | 71.60% |
| 2 | Research Center and Conference Hall (supplementary contract) | Aug. 2016 to Feb. 2017 | No | Aug. 2016 to Apr. 2017 | 30.52% |
| 3 | Hospitality and Tourism | Dec. 2015 to Aug. 2017 | No | Dec. 2015 to Jul. 2019 | 112% |
| 4 | Head Quarter Building | Oct. 2015 to Oct. 2017 | No | Oct. 2015 to Oct. 2019 | 109% |
| 5 | Sports Courts Project | Jun. 2015 to Mar. 2016 | No | Jun. 2015 to Feb. 2018 | 270% |
| 6 | Student canteen project | Jul. 2014to Aug. 2015 | No | Jul. 2014 to Jun. 2017 | 228.25% |
| 7 | Teaching and referral hospital | Aug. 2014 to Aug. 2016 | No | Aug. 2014 to Jan. 2019 | 120% |
Project status after EOT, percentage of time overrun, and/or slippage of work.
| No | Project Name | Revised Contract period | Date when the report was made | Project status at the date of the report | Time overrun | Slippage of work |
|---|---|---|---|---|---|---|
| 1 | Research Center and Conference Hall (main contract) | May 2010 to Jan. 2013 | Nov. 2015 | 100% | 106.13% | 0% |
| 2 | Research Center and Conference Hall (supplementary contract) | Aug. 2016 to Apr. 2017 | Jun. 2018 | 100% | 176.61% | 0% |
| 3 | Hospitality and Tourism Institute | Dec. 2015 to Jul. 2019 | Jul. 2019 | 29.04% | 2.11% | 71% |
| 4 | Head Quarter Building | Oct. 2015 to Oct. 2019 | Jul.2019 | 78.16% | 0% | 10% |
| 5 | Sports Courts Project | Jun. 2015 to Feb. 2018 | Apr. 2019 | 111% | 42% | Unknown |
| 6 | Student canteen project | Jul. 2014 to Jun. 2017 | Jul.2019 | 95% | 57.88% | 5% |
| 7 | Teaching and referral hospital | Aug. 2014 to Jan. 2019 | Oct. 2019 | 82.53% | 20.41% | 17.47% |
Contract time data of DB building projects.
| No | Project Name | Original Contract period | Revised Contract period | Date when the report was made | Project status at the date of the report | Slippage of work |
|---|---|---|---|---|---|---|
| 1 | CBE Head Quarter | Jul. 2015-Jul. 2019 | Jul.2015 to Jan. 2020 | July 2019 | 89.72% | Ahead of time |
| 2 | ethio-telecom Headquarter | Aug.2016 to Nov. 2019 | No revision | Feb. 2019 | 73% | 2% |