Literature DB >> 32181400

Planning stand-alone electricity generation systems, a multiple objective optimization and fuzzy decision making approach.

J D Rivera-Niquepa1,2, P M De Oliveira-De Jesus2, J C Castro-Galeano1, D Hernández-Torres3.   

Abstract

This paper presents a fuzzy-multiple objective optimization methodology to plan stand-alone electricity generation systems. The optimization process considers three main objectives, namely technology cost, environmental and societal impacts. For each feasible solution of the Pareto set, a system reliability index is evaluated along the lifetime of the project. As a key contribution, the decision making process is carried out by applying a fuzzy satisfaction method (FSM). The FSM accounts simultaneously four key performance indexes (KPI): technical, economic, environmental and social. The novelty of the proposal lies on the inclusion of societal impact (local wealth creation) in the FSM used here to select the more appropriate solution. Previous contributions on FSM only accounts two of four indexes considered in this paper. The methodology was applied in a Colombian case study. The results show the importance of the simultaneous consideration of technical, economic, environmental and social objectives in the evaluation of off-grid energization solutions.
© 2020 Published by Elsevier Ltd.

Entities:  

Keywords:  Energy; Energy economics; Energy storage technology; Energy sustainability; Fuzzy satisfaction method; Local wealth creation; Multiple objective; Power generation; Renewable energy; Renewable energy resources; Stand alone generation system

Year:  2020        PMID: 32181400      PMCID: PMC7062939          DOI: 10.1016/j.heliyon.2020.e03534

Source DB:  PubMed          Journal:  Heliyon        ISSN: 2405-8440


Introduction

Planning stand-alone electricity systems in rural areas is a topic of great interest for policy makers in developing regions. Energy planners should consider different technic-economic, environmental and social aspects to assess off-grid solutions. The planning problem can be addressed by means of an optimization model with several objectives. In practice these objectives are conflicting and multiple-objective optimization models must be solved to find out the more appropriate combination of resulting objectives. The challenge is how to specify an affordable, cost effective and sustainable solution for stand-alone electricity generation systems since isolated communities lack economic conditions to cover the real cost of service. Furthermore, it is necessary to consider alternative strategies to improve the coverage, mainly if the expansion of the distribution network is unacceptable from a technic and/or economic point of view [1], [2]. As a result, the problem of selecting and sizing the technologies for a stand-alone electricity generation systems must be analyzed from the broader context. A series of contributions can be found in literature about how to optimize stand-alone electricity generation systems [3]. In general, many of these valuable optimization approaches are based on multiple objective deterministic models. Some of them include specific strategies to perform decision making tasks once the set of feasible solutions are identified and ranked. In order to introduce uncertainty in the decision making-process, vast majority of methodologies use statistics to select the appropriate solution [4]. However, when statistics are not available, some few contributions resort to fuzzy modelling to represent the vagueness associated to the reliability of each possible solution is some extent. For instance, a fuzzy satisfaction method (FSM) has been previously applied in Malaysia [5]. This proposal characterizes solutions for stand-alone systems but only accounting only two objectives: economic (system cost) and environmental (carbon dioxide emissions) in the FSM. Including other aspects such as societal and system reliability indexes in the FSM could be worth. Indexes such as local economic impacts or expected energy not supplied can be useful to get a sustainable electricity off-grid solution [6]. After careful review of literature, we did not find decision-making strategies for stand-alone electricity generation systems planning based on fuzzy satisfaction methods accounting simultaneously economic, environmental and societal and technical (reliability) impacts. In order to demonstrate the novelty of the proposal, a exhaustive list of existing contributions in this topic is provided in Section 2 where generation technologies, performance indexes, optimization techniques and decision making strategies are classified and analyzed. To fill the research gap, this document presents a multi-objective optimization model whose decision-making strategy is based on a fuzzy satisfaction method. The optimization process considers three main objectives, namely technology cost, environmental and societal impacts through the concept of local wealth creation [6]. For each feasible solution of the Pareto set, a fourth index (system reliability) is evaluated along the lifetime of the project. The feasible set of efficient solutions are weighted with the fuzzy satisfaction method in order to select the best alternative from the Pareto set. The authors deem the application of a fuzzy approach can provide increased insight into energy planning decision making processes. The proposal has been applied in a off-grid zone of Colombia. This document is organized as follows. Section 2 is devoted to review the state of art. The methodology is presented in Section 3. In Section 4 the results obtained from a Colombian case-study are presented and analyzed. Conclusions are drawn in Section 5.

Background

The planning problem of stand-alone electricity generation systems have been widely treated in literature. Existing references on the topic can be classified according to three different scopes: 1) key performance indexes (KPI) used to valuate feasible solutions (Table 1), 2) optimization methodologies used to screen out feasible solutions (Table 2) and 3) decision-making procedures to select and recommend the best option (Table 3).
Table 1

Review of key performance indexes (KPI) according objectives of the planning problem.

ObjectiveIndexDescriptionReference
ECNPVNet Present Value[7], [8], [9], [10], [11]
ECTICTotal Investment Cost[12], [13]
ECLCCLife Cycle Cost[14], [15], [16], [17]
ECLCOELevelized Cost of Energy[18], [19], [20], [21], [22]
ECTACTotal Annual Cost[23], [24], [25]
TCLPSPProbability of Loss of Power Supply[21], [24]
CLOLPProbability of Loss of Power[26]
TCEIREnergy Index Reliability[5]
TCLOLRRisk of Load Loss[27]
TCLOLEExpected Load Loss[28]
TCDPSPProbability of Supply Deficiency[29]
TCENSEnergy Not Supplied[30]
TCELFLoad Loss Factor[15], [31]
TCWREUnused Renewable Energy[19]
TCREPPenetration of Renewable Energy[16]
TCP (R)Probability of Risk Status[20]
EVETotalCO2 Emissions[10], [15], [23]
EVEEEmbodied Energy[32]
EVLCALife Cycle Emissions[14], [23]
SCEAEnergy acceptance[7]
SCHDIHuman developing[8]
SCHDIJob creation[8]
SCLWCLocal Wealth Creation[6]
Table 2

Multiple objective optimization models for stand-alone generation systems planning.

TypeMethodDescriptionReference
ConventionalLPLinear Programming[36]
ConventionalMILPMixed Integer Linear Programming[13], [37]
ConventionalNLPNon Linear Programming[33], [34], [38]
HeuristicsGAGenetic Algorithms[39]
HeuristicsMPSOModified Particle Swarm Optimization[12]
HeuristicsSPEAStrength Pareto Evolutionary Algorithms[22]
HeuristicsMOEAMulti-Objective Evolutionary Algorithm[7]
HeuristicsABCArtificial Bee Colony[18]
HeuristicsNSGA IINon-Sorting Genetic Algorithm[29], [32], [40]
HeuristicsMLUCAMOA of Alignment Competition[23]
HybridIPFIterative Fuzzy Pareto[5]
HybridSA-TSHybrid Tabu-Search Simulation-annealing[41]
HybridPSOMCSPSO and Monte Carlo Simulation[42]
HybridHTGA-ESHybrid GA and Exhaustive Search[43]
Table 3

Review of decision making strategies to define stand-alone electricity generation systems.

ObjectivesTechnologiesDecision making methodReferences
EC-EVPV-DG-FC-BAHP[14]
EC-EVPV-WT-T-BRanking[10], [22], [23]
EC-EVPV-WT-BTopsis[19]
EC-EVPV-WT-BSingle Objective Optimization[15], [47]
EC-TCPV-WT-BSingle Objective Optimization[17], [26]
EC-TCPV-WT-BSingle Objective Optimization[24], [25]
EC-TCPV-WT-BRanking[29], [48]
EC-TCPV-WT-T-BSingle Objective Optimization[16], [28], [49]
EC-TCPV-WT-FCSingle Objective Optimization[21], [27], [50]
EC-EV-TCPV-WT-BRanking[32]
EC-EV-TCPV-WT-FC-HTRanking[31]
EC-SCPV-WT-T-BRanking[7]
EC-TCPV-WT-T-BRanking[20]
EC-TCPV-WT-T-BM-BRanking[33]
EC-TCPV-WT-T-BAHP[34]
EC-TCPV-WT-T-HG-BM-BSingle Objective Optimization[51]
EC-TCPV-WT-BFuzzy Satisfaction[5]
EC-TC-EV-SCPV-WT-T-BFuzzy SatisfactionThis paper
Review of key performance indexes (KPI) according objectives of the planning problem. Multiple objective optimization models for stand-alone generation systems planning. Review of decision making strategies to define stand-alone electricity generation systems.

Key performance indexes

Table 1 lists a classification of key performance indexes (KPI) depending on economic (EC), technical (TC), social (SC) and environmental (EV) dimensions of the planning problem. The majority of existing planning methodologies are related with the economic performance (EC) dimension: net present value, total investment cost, life cycle cost, levelized cost of energy and total annual cost. Some specific contributions deal with technic aspects (TC) such as reliability (probability of loss of supply, energy not supplied, etc) and penetration levels of renewable-based generation (unused renewable energy, penetration of renewable energy, etc.). Recent trends on low carbon energization are introducing performance indexes according to environmental considerations (EV) such as total emissions, embodied energy and life cycle assessment. It is worth to highlight that the social aspect (SC) has been previously included in the decision making analysis from a qualitative perspective [20], [33], [34] but not incorporated as a performance index relating societal impacts in the optimization stage. Recently, [7], [8] considered societal indexes at the optimization stage. In this paper, the local wealth creation (LWC) index proposed by [6] is incorporated both in the optimization stage and the decision-making stage.

Multiple-objective optimization stage

Since foregoing indexes are relevant to assess the suitability of an effective solution, the evaluation of the problem as a whole requires to pose a mathematical optimization problem with multiple objectives (MO) [35]. This kind of optimization allows to identify the set of strategies for an appropriate design solution. The methodology of selection and sizing of stand-alone generation systems can be written as a MO optimization problem. The solution of the MO problem is then described by the Pareto front, a set of non-dominated solutions [44] obtained by conventional, heuristic or hybrid methods and use of specific software [45]. Table 2 in a general way the main MO optimization methods reported in literature applied to plan stand-alone electricity generation systems. The methods are classified by the corresponding optimization technique [46]. There are a number of commercial/open source software tools suitable to be used in the planning process. The Standard optimization microgrid design software HOMER [9] and Clean Energy Management software RetScreen [45] use conventional linear-programming optimization methods to get feasible solutions. The Hybrid Optimization by Genetic Algorithms (iHOGA) is based on heuristic methods [8]. In this paper, we use a genetic algorithm [39] to screen out feasible solutions of the MO problem considering economic (EC), environmental (EV) and societal (SC) objectives. Technical performance (TC) is calculated a posteriori. A reliability index, Energy not supplied (ENS), is evaluated for each solution of the Pareto set.

Decision-making stage

Once the multiple objective optimization problem is stated with the performance indexes listed in Table 1 and later solved using any technique listed in Table 2, it is necessary to select the more appropriate solution accounting all aspects under consideration. Therefore, the decision-making process is carried out using a number of strategies. Table 3 presents different decision making procedures applied to select efficient solutions. The list of contributions on this topic is classified according to economic, technical, environmental and societal objectives (EC, TC, EV and SC) and also by technologies considered wind (WT), solar photovoltaic (PV), combined with battery banks (B), thermal solutions (including diesel reciprocating engines and natural gas micro-turbine) (T), fuel cells (FC), small-scale hydraulic generation (HG), biomass (BM) and hydro tank (HT). Some contributions in Table 3 pose planning problem as a single objective optimization problem. In this case, only one solution is get and no decision making process is carried out. Contributions based on multiple objective optimization can rank the set of efficient solutions (Pareto front) according decision maker preferences. In this case qualitative aspects are included to guide the best choice. Other contributions select the best option according to a given methodology such as Topsis, Analytical Hierarchal Processing (AHP) or Fuzzy Satisfaction methods (FSM). Notice that the economic objective is clearly predominant in decision making process. In some contributions such as [14], [19], [23], the environmental or technical objectives are also included. Contributions [20], [33], [34] deal with economic and technical objectives at the same time. In this review we found only one contribution that applies the fuzzy satisfaction method (FSM) in the decision making process [5]. However only two objectives are considered economic (EC) and technical (TC). In this paper we improve the approach proposed in [5] by including the environmental (EV) and societal (SC) objectives [6]. Last row of Table 3 shows how this contribution makes the difference with respect to existing decision making procedures used in literature to select the more appropriate solution for the stand-alone generation systems planning problem.

Methodology

In this section the statement of the multiple objective optimization problem and the proposed decision-making process is described in detail. The multiple objective problem can be solved using any suitable technique based on traditional mathematical programming or heuristic algorithms. In this paper, the multiple objective problem is solved using a Genetic Algorithm. Each solution of the Pareto set includes specific figures for economic (EC), environmental (EV) and societal (SC) objectives. System reliability - Expected Energy Non Supplied - regarded here as a technical objective (TC) is determined a posteriori for each element of the Pareto set. The decision-making process – selecting the best option from the Pareto set – is carried out through the fuzzy satisfaction method (FSM) considering all four objectives stated above: EC, EV, SC and TC.

The multiple-objective optimization model

The optimization problem is defined as a three-objective constrained model in Eq. (1). The first objective corresponds to the minimization of life cycle costs (LCC) of the project. Life Cycle Cost (LCC) is an important economic (EC) performance index that account the impact both pending and future costs of the project. It compares initial investment options and identifies the least operational cost over a given period. The second objective – the environmental (EV) one – corresponds to the minimization of the life cycle of carbon dioxide CO2 emissions (LCE). Finally, the third objective accounts a societal benefit (SC). The inclusion of this societal objective in the planning process of stand-alone generation systems constitutes the main contribution of the paper. This objective comprises the maximization the social benefit associated to economic growth and job creation in the life cycle of local wealth creation (LWC) [6]. The vector of decision variables is given by four elements: where, is the total surface area of the photovoltaic system (PV) in m2, is the total sweep area of the wind turbine(WT) system turbines in m2, is the average power output of the thermal (T) reciprocating engine in kW. is the charge level of the battery bank (B) in Ah. The aforementioned objective functions are constrained to one () equilibrium equation (energy balance) and four () capacity constraints associated to admissible upper and lower bounds for the dispatch of each technology: photovoltaic (PV), wind (WT), diesel (T) and battery storage (B). In the following, each objective of the multiple objective optimization problem written in Eq. (1) is defined.

Economic objective: Life Cycle Cost (LCC)

The Life Cycle Cost (LCC) of the stand-alone generation system evaluates for each technology the net present value of capital and maintenance expenditure (CAPEX) and operational costs (OPEX). where, is the project lifetime in years, γ is the annual discount rate in percent, ν is the annual inflation rate in percent, is the present value of capital costs in $ (Colombian currency), is the present value of maintenance costs of system elements in $, is the present value of operating costs of the system (fuel) in $, is the present value of the income from avoided CO2 emissions in $. The capital expenditure or fixed cost () corresponds to the overnight cost of the generation system as well as the present value of battery replacements in the future. The cost of replacement of the associated electronic equipment such as regulator and inverter are not considered, taking into account that the life span of these equipments commercially is higher than 25 years. The fixed cost also includes the engineering, procurement and construction (EPC) expenditures. The maintenance cost (), operating cost () and avoided emission cash flows () are given by their net present value cost along years project and an annual discount rate γ expressed in percent. The fixed cost can be decomposed in four components: the fixed cost of photovoltaic (), wind (), diesel plant () and battery solutions (). The fixed cost of batteries is calculated at present value considering a number of replacements along the project lifetime. where, is the fixed cost of the photovoltaic panels per unit of installed area in $/m2, is the fixed cost of the wind turbine system per unit of swept area in $/m2, is the fixed cost of the battery banks in $/Ah, is the fixed cost of the thermal reciprocating engine in $/kW, is the battery lifetime in years, is the number of battery replacement along the project lifetime: Where, is the battery bank lifespan and is the project lifetime. Depending on the technology used (photovoltaic, wind, storage and diesel) the net present value of the maintenance cost is determined as: where, is the maintenance cost of photovoltaic system in $/m2, is the maintenance cost of the wind solution in $/m2, is the maintenance cost of the batteries in $/Ah, is the maintenance cost of the thermal reciprocating engine in $/kW. The net present value of the operational cost is given by where, is the fuel cost, given in $/m3 for GLP and $/l for diesel, is the heat rate of thermal component in Btu/kWh, T is the average operation time in hr/year, this is established by the planner, is the specific heat value by fuel, given in Btu/m3 for GLP and Btu/l for diesel. The net present value of the income due to avoided CO2 emissions is estimated by comparing the emissions of the system with the virtual emissions obtained if the energy was obtained from the network. This is given by: where, λ is price of avoided emissions in $/tCO2, is the emissions factor with reference to the network in tCO2/ MWh, is the emissions factor of CO2 produced by the thermal reciprocating engine in tCO2/MWh, is the annual real energy produced by the photovoltaic system in MWh/year, is the annual real energy produced by the wind system in MWh/year, is the annual real energy stored in the battery bank in MWh/year, is the annual energy produced by the reciprocating engine in MWh/year. The energy produced by the photovoltaic generation system in kWh is a function of the average solar irradiation in the area, assuming an operating time in the year of 8760 hours. where, is the annual average output of the photovoltaic system in kW, is the total efficiency of the photovoltaic system in per unit, is the total efficiency of the inverter system in per unit, is the average solar irradiance in kW/m2. The efficiency of the wind conversion process is determined according to [32] as: where, is the wind turbine conversion efficiency, is the efficiency of the gear box, is the efficiency of the electric generator. The density of the air relies on the height in () of the wind turbines and its value is estimated according to [32] as: where, z is the average height of the wind turbine hub in meters, is the average temperature of the environment in . For the simplification of the model, the energy produced by the wind unit is obtained from average wind speed in the area, assuming an operating time in the year of 8760 hours: where, is the annual average output of the wind system in kW, is the total efficiency of the wind conversion, ρ is the density of the air kg/m3, v is the average wind speed m/s. The energy stored in battery bank is a function of the operational voltage. Using a reduced battery model for optimization model simplicity, assuming an average state of charge (SOC). where, is the percentage of average battery state of charge, is the battery bank capacity in Ah, is the operating voltage of the battery bank in V. The energy produced by the thermal reciprocating engine is a function of the average time of operation T in hours and given by

Environmental objective - Life Cycle Emissions (LCE)

The second objective function of the multiple objective optimization problem accounts the CO2 emissions produced during the operation of the system. The emissions comprise the carbon footprint produced during the construction process, installation and commissioning of each technology including the emissions generated in the manufacturing of the components, transporting of the components from the factory to the place of the system. Photovoltaic and wind turbine technologies have a foot-print associated with emissions produced during the manufacturing process. In this way, a broad context of the environmental emissions and impacts generated by the stand-alone electricity energy system is considered. Thus, total emissions are determined through specific emission factors for the installed capacity of each technology that should be added to the emissions produced by the operation of the thermal reciprocating engine. The emission factors applied in this paper were taken from [22]. The overall objective function for the Life Cycle Emissions (LCE) is given by the following expression: where, is the average charge level of the battery bank in Ah, is the average power output by the thermal reciprocating engine kW, is the emission factor for the photovoltaic system kgCO2/kW, is the emission factor for the wind turbine system kgCO2/ kW, is the emission factor associated with battery installation kgCO2/Ah, is the emission factor associated with reciprocating engine manufacturing kgCO2/kW, is the emission factor for thermal operation kgCO2/kWh.

Societal objective - Local Wealth Creation (LWC)

The third objective to be considered in the optimization problem accounts the social impact of the stand-alone energy supply in the area. The inclusion of this objective constitutes the main contribution of the paper. The concept of Local Wealth Creation (LWC) is applied [6]. This concept combines economic growth with job creation accounting the acceptance and appropriation of the project by the community. This function considers the job creation during the life cycle [33]. The contribution of the stand-alone generation system to economic growth is determined considering the energy intensity and the job creation related to each component of the system. The local wealth creation function is expressed as: where, is the local energy intensity in $/MWh, α is the contribution factor to the LWC for job created in $/Jobs is the job creation function. The job creation function is defined by unitary factors that relate the jobs created during to the construction, transportation and installation of hybrid generation system technologies. Job requirements for operation and maintenance are also included. Given by the number of jobs created during the life cycle and based on the job creation factors presented in [7] and [33], the function of job creation is expressed as: where, is the job creation factor for photovoltaic system in Jobs/kW, is the job creation factor for WT system in Jobs/kW, is the job creation factor for installation of the batteries in Jobs/kW, is the job creation factor for thermal installation in Jobs/kW, is the job creation factor for the operation of the reciprocating engine in Jobs/kWh.

Optimization model constraints

The three objectives detailed above are constrained to the energy balance of the system as well as the lower and upper bounds of the decision variables. Thus, one energy balance equation and four capacity constraints are recognized. System energy balance in kWh/yr is given by where photovoltaic (), wind (), storage () and diesel generator () generated energy flows expressed in kWh per year. These energy contributions are determined according to equations (10)-(15). Energy demand () in kWh/yr is previously defined by the energy planner. For the sake of simplicity, the amount of energy wasted from renewable sources is considered negligible when it exceeds the demand and the battery bank is charged. The system capacity constraints are given by where lower and upper capacity bounds are specified by each technology. For the sake of simplicity, this model does not include distribution lines since generation facilities and loads are located in the same place. For this reason, a restriction on distribution losses is not included and no associated cost is added in the objective function of the economic aspect. The average power output of each kind of renewable units depends on the decision variables and and a scaling factor and in kW/m2, respectively.

Solution approach

The planning problem is solved in three different stages. In the first stage I, the multiple objective optimization problem is solved with a Genetic Algorithm (MOGA) and the Pareto front (containing LCC, LCE and LWC performance indexes) is identified from the set of the feasible solutions. In the second stage II, the energy reliability index (EIR) is determined for each solution of the Pareto front. The most appropriate solution is selected at third stage III by applying the proposed fuzzy satisfaction method (FSM) according to the three objectives obtained in stage I (LCC, LCE and LWC performance indexes) and the energy reliability index (EIR) evaluated in stage II. The complete solution approach is described in detail in the ten-step algorithm depicted in Fig. 1.
Figure 1

General planning algorithm.

General planning algorithm.

Data setup

Step 1: Input parameters of the optimization algorithm are settled: the load curves, the annual irradiance curve, the annual wind speed curve, technology costs (CAPEX, OPEX), technical parameters of each technology, emission factors, job creation factors, project parameters such as interest rates and life cycle time, maximum demand and consumption. Upper and lower limits of decision variables are also established.

Stage I: MOGA solution and Pareto front identification

Step 2: The mathematical problem is solved. A multiple objective genetic algorithm (MOGA) is run to solve the optimization problem stated in Eqs. (3)-(18) subject to Eqs. (19)-(25). Technical solutions for economic, environmental and societal objectives are identified. This approach is based on a variation of the algorithm NSGA-II (Non-Sorting Dominated Genetic Algorithm) with elitist selection of non-dominance [32]. The algorithm favors individuals with a higher value that help increase the diversity of the population, even if they have a lower fitness value. It is important to assure the diversity of the population for the convergence of the Pareto optimal front and to identify the number of elite members (Pareto non-dominated solutions) in the iterative process. There are two options for elite identification in the search of the Pareto optimal front: Pareto fraction and distance function. The fraction function limits the number of individuals on the Pareto front (elite members) and the distance function helps maintain sufficient diversity to favor individuals who are far from the optimal front The optimization problem yields the Pareto front with solutions in the form . Each solution is evaluated at objective function , . The average power output of renewable, charge level and thermal reciprocating engines are determined (, and ) from decision variables.

Stage II: energy reliability index evaluation

Step 3: Each solution of the Pareto front is setup for initial time. Technical attributes of the system are calculated at hour : 1) Power output of renewable sources (, ) is determined according to equations (10) and (13), 2) State of charge (SOC) of the batteries is given by () for batteries: , 3) the base output of thermal reciprocating engines is also fixed to give voltage-frequency support to the system. In order to promote the use of renewable resources and use the thermal resource as a reliability support only, the base output of the fossil-based plant is adjusted as 15% of the peak load . Step 4: (Conditional): At hour it is verified if the available renewable resource can satisfy the demand. Depending on the difference between the load demand () and the available renewable resource (), it is defined whether the batteries are suitable to be charged. Step 5.1: If the batteries are charging, then the stored energy () in kWh is given by: Thus, the total charge level is given by: (Conditional) If the total charge is greater than the nominal level , the batteries are charged at its nominal value, and the excess power () is dissipated through a resistance. The output of the reciprocating engine remains at its base value. Then, power balance is given by: (Conditional) If the total charge is lower than the nominal level , the batteries are loaded with the available power. The output of the thermal reciprocating engine remains at its base value . In both cases, no load shedding is required, then power not supplied is zero. Step 5.2: If the batteries are discharging and It is verified if the total charge . (Conditional) If is greater than , batteries are going to be discharged and a new is established for the next hour . The output of the thermal reciprocating engine remains at its base value. (Conditional) If is lower than , battery charge level reaches its minimum value and the total battery discharge is given by The battery discharge output is then compared with the available thermal output . (Conditional) If the total discharge output is lower than thermal based output , the thermal output should be increased to meet the balance: (Conditional) If the total discharge output is greater than , the thermal reciprocating engine is dispatched to its nominal output value but it cannot provide enough power to cover the peak demand and load shedding is required: In this case, the load shedding is -. Step 6: The sequential simulation for the estimation of the reliability of the technical arrangement is executed for a period of one year. This reliability analysis is carried out assuming that annual solar irradiance and annual wind speed conditions do not change significantly across the project lifespan. Then, Step 5 is repeated for each hour of the year from to according to the annual load curve, the wind sped and irradiance annual curves. Step 7: The annual Energy Reliability Index (EIR) is determined from power not supplied (PNS) figures obtained in Step 5.2 from hour to hour : where is the annual energy not supplied in kWh/year and is the annual load consumption in kWh/year. Step 8: Steps 3 to 7 are repeated for every solution of the Pareto set. Step 9: At this point, all three optimized objectives – economic (LCC), environmental (LCE) and societal (LWC) – were characterized with a corresponding energy reliability index (EIR) for every feasible solution in the Pareto set.

Stage III: decision making: fuzzy satisfaction method FSM application

Step 10: Accounting the four objectives per Pareto solution summarized at Step 9, the decision-making process is carried out in order to select the best option. In this paper a fuzzy satisfying method is used for this purpose. The method is described as follows: for each feasible solution of the Pareto set, a membership function is defined for each objective . The magnitude of the membership function ranges from 0 to 1 reflecting the level upon which a given solution belongs or not to the set that minimizes the objective function . All solutions should be evaluated in order to select the best one that equitably reconciles all the three objectives of the optimization problem. The method takes two formulations depending on whether the objective function is minimized (Eq. (53)) or maximized (Eq. (54)). On one hand, when the objective function is minimized, a linear membership function is used for all objective functions as follows: where is the weight assigned to the i-th solution of a minimization objective; It is the maximum value of the minimization objective obtained; It is the minimum value of the minimization objective obtained; It is the value of the minimization objective obtained by the i-th solution. On the other hand, when the objective function is maximized, a linear membership function is used for all objective functions as follows: where is the weight assigned to the i-th solution of a maximization objective; is the maximum value of the maximization objective obtained; is the minimum value of the maximization objective obtained; is the value of the maximization objective obtained by the i-th solution. The normalized weight of each solution () combines the weights obtained for all the objectives considered in the decision making process. This normalized weight makes it possible to compare solutions. where, is the normalized weight for each solution. When calculating the normalized weights for all solutions, it is possible to obtain the best solution within the Pareto set by selecting highest normalized weight.

System data

The input parameters for the algorithm are summarized in Table 4. All costs and prices are given in Colombian currency $. , job creation factor for photovoltaic system in Jobs/kW, , job creation factor for WT system in Jobs/kW, , job creation factor for installation of the batteries in Jobs/kW, , job creation factor for thermal installation in Jobs/kW, , job creation factor for the generator operation in Jobs/kWh. , CO2 em. factor for the photovoltaic system kgCO2/kW, , CO2 em. factor for the wind turbine system kgCO2/kW, , CO2 em. factor associated with battery installation kgCO2/kW, , CO2 em. factor for manufacturing kgCO2/kW, , CO2 em. factor for diesel/gas operation gCO2/kWh. is the local energy intensity in $/MWh, and α is the contribution factor to the LWC for job created in $/JobsLC
Table 4

Data setup.

ParameterValue
Average inflation rate, ν9%
Battery bank lifespan, bl6 years
NG init cost, CT6000 M$/kW
WT init cost, CWT600 M$/m2
NG maint cost, CmT120 M$/kW
WT maint cost, CmWT10.4 M$/m2/yr
Battery replac, YB4
CO2 price, λ5 k$/tCO2
Voltage bat bank, VB48 [V]
Inverter efficiency, ηinv95%
Wind generator eff, ηG80%
NG em. fact, ϵT800 gCO2/kWh
Specific Heat fuel, Hfuel35315 Btu/m3
Discount rate, γ12%
Project lifetime, lf25 yr
PV init cost, CPV180 M$/m2
Batt init cost, CB150 M$/Ah
PV maint cost, CmPV16.4 M$/m2/yr
Batt maint cost, CmB40 M$/Ah/yr
NG fuel cost, Cfuel1500 M$/m3/yr
Em. factor Net, ϵn370 gCO2/kWh
PV Efficiency, ηPV16%
Wind conv eff, ηWT60%
Gear box eff, ηGB70%
Wind turb conv eff, ηTC60%
NG Heat Rate, HR11.2 Btu/kWh
Data setup.

Results

The proposed methodology was applied into a village located in the municipality of Guican, department of Boyacá (Colombia). According to [53] by 2013 the department had a total of 382,416 households and a coverage index (ratio of number of users with energy service to number of households) of 96.43%. According to the statistics presented in [53] a coverage growth of up to 97.6% was estimated for 2017. This means that 9,178 homes lack electricity. The village under study is located in a rural off-grid zone at the north of the department (715059 786264 18N UTM). The distance between the village and Tunja (the capital of the department) is 255 km, with an average altitude of 2983 m.a.s.l. and a total population of 6,909 inhabitants. A share of 75% (5197 inhabitants) are located in rural zones. Results of the application of the step-by-step planning algorithm depicted in Fig. 1 is presented. Step 1 - Data Setup: The average annual load to serve is 2 MW, 17.47 GWh/year with a peak load of 3.25 MW. The estimation of the wind and solar irradiance potential was obtained from the NREL [52] according to the GPS location of the village under study. Annual demand, solar irradiance, wind speed curves are depicted in Fig. 2.
Figure 2

Annual load demand curve d (MW), annual solar irradiance curve, S (kW/m2), speed curve v (m/s), NREL-NRSDB Data, 2014 [52].

Annual load demand curve d (MW), annual solar irradiance curve, S (kW/m2), speed curve v (m/s), NREL-NRSDB Data, 2014 [52]. Technology and fuel costs consider particular conditions to build and operate off-grid solutions in rural areas of developing countries such as Colombia. Optimization model constraints are defined as follows: Stage I, Step 2, optimization results: Fig. 3 depicts the results of the optimization process. The Pareto front comprises 133 non-dominated solutions. Thus, the Pareto set size is 133. The optimization process was carried out in a PC computer with the following characteristics: Intel (R) Core (TM) i7-5500U CPU @ 2.40 GHz, 8.00 GB (RAM). The optimization method was coded in Matlab using the gamultiobj function. The genetic algorithm runs with a population size of 380 and with 120 generations. The processing time obtained was 204.15 seconds. The resulting 3-dimension graphs show that cost in the life cycle cost (LCC) ranges between 25 and 40 billion $ (approx. US$8.6 and 10.3 million). This result implies an average LCC cost of US$0.27-0.32 per kWh. The life cycle of emissions (LCE) objective varies between 60 and 85 MtCO2. Finally, the local wealth creation (LWC) ranges between 22 and 28 billion $ (approx. US$ 13.6 and 15.3 million).
Figure 3

Case study Pareto optimal set.

Case study Pareto optimal set. Stage II, Steps 3-9, reliability analysis: Once obtained the set of non-dominated solutions in Stage I, the energy reliability index (EIR) is calculated for each optimal solution of the Pareto, the results are presented in Fig. 4. The calculated EIR ranges 0.83 and 0.91. This means that load shedding is required in all solutions with different degree of severity.
Figure 4

Energy Index Reliability (EIR).

Energy Index Reliability (EIR). Stage III, Step 10, decision making using a fuzzy satisfaction method FSM: In the top-right hand of Fig. 3 it is showed the results obtained for the normalized weights computed using Eq. (55). The highest normalized weight is . The best normalized weight corresponds to the non-dominated solution number 109 of the pareto set. Table 5 lists the attributes of the best option. The best solution 109 is highlighted as a red bullet in the Pareto set shown in Fig. 3.
Table 5

Best solution - Solution 109.

kW/AhGWhObjectiveValue
PPV523.3WPV4.58LCC [Bi $]32.9
PWT341.8WWT3.00LCE [MtCO2]81.9
PB1460WB12.78LWC [bi$]26.6
PT1264.4WT11.07EIR [%]91
Best solution - Solution 109. It is worth to note that the fuzzy satisfaction method (FSM) seeks the best solution in the around of the middle of the Pareto front. This result is consistent with the fact that in this area the four objectives are well balanced. The best solution represents a reduction of 4248 kTon year with respect to the emissions that would have been obtained if the energy had been taken from the grid. The resulting dispatch profile of renewable and fossil-based technologies for the best solution 109 is depicted in Fig. 5.
Figure 5

Hourly dispatch by technology to cover the system load.

Hourly dispatch by technology to cover the system load. The resulting capacity specifications by technology are determined according to the results for best solution 109 displayed in Table 5. The recommended nominal sizes of the system are , , , . We can observe from Fig. 5 that the thermal reciprocating engine can represent around 40% of the annual load demand. The use of storage is really limited in Colombia due to its higher costs. Solar PV and wind WT output have a share of almost 60% the annual load demand. Particular conditions of Colombia such as moderate fuel cost and high renewable potential suggest to limit the use of storage as a solution to tackle renewable energy intermittency. Regarding the inclusion of societal considerations such as local wealth creation (LWC), the results show the importance of off-grid energy solutions to improve local economy. The planning process for a stand-alone electricity system in Colombia has considered three optimized objectives (economic EC, environmental EV and social SC) and evaluated a reliability index (technical TC). Four technologies are considered: solar PV, wind WT, thermal reciprocating engines (T) and batteries (B). The optimization process was carried out taking into account the costs on-site (a rural area) for every technology. We obtained a design specification (solution 109) that reconciles the trade-offs among the four key performance indexes (LCC, LCE, LWC and EIR). The state of art in this topic is improved by including societal objectives – strongly dependent on local economies – in both the optimization and decision making processes. As a key contribution, the proposed methodology enhances the decision making process by applying a fuzzy satisfaction method considering economic, technical, societal and environmental attributes at once.

Conclusions

This paper presents a fuzzy-multiple objective optimization methodology to plan stand-alone electricity generation systems. The novelty of the proposal lies on the inclusion of societal impact (local wealth creation) in the FSM used here to select the more appropriate solution. We conclude that the use of decision-making processes based upon fuzzy satisfaction methods (FSM) in stand-alone system specification produces satisfactory solutions accounting simultaneously four key performance indexes (KPI): technical, economic, environmental and societal. Real-world application in Colombia suggests a fossil-renewable mix of 40-60% with a local health creation income of $26 Billion per year and a environmental impact of 80 MtCO2 per year. Finally, one of the recommendations to improve the model and to consider in future works, can be the inclusion of the losses in distribution lines, taking into account the magnitude of the power of the system and that the consumers can be at a significant distance from the generation node of the microgrid. With this factor it is necessary to reformulate the cost function and the calculation of CAPEX and OPEX of the project would change.

Declarations

Author contribution statement

J. D. Rivera-Niquepa: Performed the experiments; Analyzed and interpreted the data. P. M. De Oliveira-De Jesus: Conceived and designed the experiments; Analyzed and interpreted the data; Wrote the paper. J. C. Castro-Galeano & D. Hernandez-Torres: Analyzed and interpreted the data; Contributed reagents, materials, analysis tools or data.

Funding statement

This work was funded by Gobernacion de Boyaca, Colciencias and Colfuturo Grant No. 743.

Competing interest statement

The authors declare no conflict of interest.

Additional information

No additional information is available for this paper.
  1 in total

1.  A global satisfaction degree method for fuzzy capacitated vehicle routing problems.

Authors:  Juan Carlos Figueroa-García; Jhoan Sebastián Tenjo-García; Carlos Franco
Journal:  Heliyon       Date:  2022-06-20
  1 in total

北京卡尤迪生物科技股份有限公司 © 2022-2023.