Abstract
Selecting construction schemes of the building engineering project is a complex multiobjective optimization decision process, in which many indexes need to be selected to find the optimum scheme. Aiming at this problem, this paper selects cost, progress, quality, and safety as the four first-order evaluation indexes, uses the quantitative method for the cost index, uses integrated qualitative and quantitative methodologies for progress, quality, and safety indexes, and integrates engineering economics, reliability theories, and information entropy theory to present a new evaluation method for building construction project. Combined with a practical case, this paper also presents detailed computing processes and steps, including selecting all order indexes, establishing the index matrix, computing score values of all order indexes, computing the synthesis score, sorting all selected schemes, and making analysis and decision. Presented method can offer valuable references for risk computing of building construction projects.Entities:
Mesh:
Year: 2013 PMID: 23533352 PMCID: PMC3603404 DOI: 10.1155/2013/573014
Source DB: PubMed Journal: ScientificWorldJournal ISSN: 1537-744X
Figure 1The multiobjective evaluation chart of building project construction schemes.
The detailed composition of building construction cost.
| The total building construction cost |
|---|
| Direct cost |
| Direct labor cost ( |
| Basic wage ( |
| Wage allowance ( |
| Auxiliary wage ( |
| Welfare expense ( |
| Labor protection expense ( |
| Direct material cost ( |
| Material initial cost ( |
| Material transportation miscellaneous cost ( |
| Transportation loss cost ( |
| Purchasing and storage cost ( |
| Material inspection and testing cost ( |
| Direct mechanical cost ( |
| Mechanical depreciation cost ( |
| Repair cost ( |
| Installing/removing and external transportation cost ( |
| Mechanical labor cost ( |
| Fuel power cost ( |
| Road toll and vehicle and vessel subsidy expenses ( |
| Direct measure cost ( |
| Environmental protection expense ( |
| Civilized construction expense ( |
| Safe construction expense ( |
| Temporary construction expense ( |
| Night construction expense ( |
| Large-scale mechanical equipment inside and out expense |
| ( |
| Concrete formwork expense ( |
| Scaffold expense ( |
| Equipment protection expense ( |
| Dewatering expense ( |
| Indirect cost ( |
| Construction stipulated expense ( |
| Enterprise administration expense ( |
The detailed segment composition of building construction progress.
| Construction progress | ||
|---|---|---|
| First-order progress influence factor segments | Second-order progress influence factor segments | Progress score value |
| Site leveling progress ( | Scene investigation progress ( |
|
| Removing obstacle progress ( |
| |
| Calibrating range, setting benchmarks, and grid progress ( |
| |
| Measuring elevation progress ( |
| |
| Calculating earthwork cut and fill engineering quantities progress ( |
| |
| Land leveling progress ( |
| |
| Field compaction progress ( |
| |
|
| ||
| Ground foundation progress ( | Earth excavation progress ( |
|
| Cushion placement progress ( |
| |
| Foundation placement progress ( |
| |
| Foundation wall placement progress ( |
| |
| Base pillar, ground ring beam progress ( |
| |
| Backfilling earthwork progress ( |
| |
|
| ||
| Body engineering progress ( | Reinforcement engineering progress ( |
|
| Formwork engineering progress ( |
| |
| Concrete engineering progress ( |
| |
| Masonry engineering progress ( |
| |
|
| ||
| Roof engineering progress ( | Clean up, leveling progress ( |
|
| Processing insulation layer progress ( |
| |
| Waterproofing and drainage progress ( |
| |
| Setting qualified seaming progress ( |
| |
| Ventilation, exhaust progress ( |
| |
|
| ||
| Decoration and fitment progress ( | Groundwater seepage test of bathroom and kitchen progress ( |
|
| Laying chisel trough and circuit pipeline progress ( |
| |
| Sealing and burying trunk progress ( |
| |
| Decoration and fitment progress of public wall ( |
| |
| Installing doors and windows progress ( |
| |
|
| ||
| Water, electricity, and HVAC progress ( | Water supply and sewerage progress ( |
|
| Laying circuit progress ( |
| |
| Installing heating progress ( |
| |
| Water, heating, and electrical test progress ( |
| |
|
| ||
| Equipment installation progress ( | Installing elevator progress ( |
|
| Installing fire-fighting equipment progress ( |
| |
| Installing emergency device progress ( |
| |
|
| ||
| Goods transportation progress ( | Goods transportation scheme 1 progress ( |
|
| Goods transportation scheme 2 progress ( |
| |
| Goods transportation scheme 3 progress ( |
| |
|
| ||
| Environmental factor progress ( | Natural environment factor progress ( |
|
| Social environment factor progress ( |
| |
|
| ||
| Other factors progress ( | Construction design drawings change progress ( |
|
| Construction machinery, materials changes progress ( |
| |
| Progress affected by weak supervision ( |
| |
| Progress affected by supply failure of the municipal system ( |
| |
| Progress affected by great political and social activities ( |
| |
The detailed quality influence factor segment composition of the building construction schemes.
| Engineering quality | ||
|---|---|---|
| First-order influence quality factor segments | Second-order influence quality factor segments | Quality score value |
| Site leveling quality segment ( | Machinery performance influence quality segment ( |
|
| Measuring tool influence quality segment ( |
| |
| Climate influence quality segment ( |
| |
| Worker influence quality segment ( |
| |
|
| ||
| Ground and foundation quality segment ( | Equipment performance influence quality segment ( |
|
| Materials reliability influence quality segment ( |
| |
| Personnel quality influence quality segment ( |
| |
| Drawings reliability influence quality segment ( |
| |
| Construction plans influence quality segment ( |
| |
| Construction technology influence quality segment ( |
| |
| Construction environment influence quality segment ( |
| |
|
| ||
| Main body engineering quality segment ( | Construction machinery influence quality segment ( |
|
| Construction technology influence quality segment ( |
| |
| Manager's quality influence quality segment ( |
| |
| Construction technique maturation influence quality segment ( |
| |
| Construction materials influence quality segment ( |
| |
| Construction worker technology influence quality segment ( |
| |
| Construction drawing reliability influence quality segment ( |
| |
|
| ||
| Decoration and fitment engineering quality segment ( | Decoration and fitment material influence quality segment ( |
|
| Construction worker influence quality segment ( |
| |
| Constructor influence quality segment ( |
| |
| Construction equipment influence quality segment ( |
| |
|
| ||
| Building roof quality segment ( | Waterproof and thermal insulation material reliability influence quality segment ( |
|
| Construction technology and procedure influence quality segment ( |
| |
| Working environment influence quality segment ( |
| |
|
| ||
| Building water supply and drainage, heating quality segment ( | Water supply and drainage, heating ventilating pipe influence quality segment ( |
|
| Constructor technology level influence quality segment ( |
| |
| Construction technology influence quality segment ( |
| |
|
| ||
| Building equipment and installation quality segment ( | Equipment reliability influence quality segment ( |
|
| Professional technology constructor influence quality segment ( |
| |
The detailed composition of building construction safety influence factor.
| Human safety factor ( | Matter safety factor ( | Environment safety factor ( |
|---|---|---|
| Not wearing security protection apparatus ( | Not setting safety protection ( | Construction natural conditions ( |
| Unsafe costume ( | Incorrect safety protection and dice marking ( | Narrow construction work surface ( |
| Wrong mechanical operation ( | Mechanical equipment being in the unsafe state ( | Disorderly construction yard ( |
| Ignoring safety warning ( | Mechanical equipment being in nonnormal state ( | Artificial lighting in the night is lacking ( |
| Using unsafe equipment ( | The material stacked in the unsafe state ( | Wrong operation process design ( |
| Body or spirit reason ( | Having harmful material ( | Bad ventilation ( |
| Rash advance operation ( | Improper protection for traffic line ( | |
| Being in unsafe site ( | ||
| Error handling of dangerous goods ( |
Taking value of three risk degree indexes.
| Possibility | Probability | Result | |||
|---|---|---|---|---|---|
| Caused accident possibility | Taking the value of | Caused accident probability | Taking the value of | The result caused by accident | Taking the value of |
| Sustainably occur | 10 | Very large possible occurrence | 10 | Extreme large accident, shutdown, and rectification | 10 |
| Often occur | 8 | Large possible occurrence | 8 | Very large accident, causing death | 9 |
| Occur for many times | 6 | Possible occurrence | 6 | Severe accident, having severe injury | 7 |
| Occur in a few times | 5 | Occur for once a while | 5 | Accident, having slight injury | 5 |
| Occur for very few times | 3 | Rare occurrence | 3 | Small accident, having minor injures | 3 |
| Basically not occur | 1 | Basically impossible | 1 | Very small accident, no injury | 1 |
The calculated cost value of 4 construction schemes (unit: ten thousand yuan).
|
|
|
|
|
| |
|---|---|---|---|---|---|
| Scheme 1 | 89.70 | 110.85 | 69.80 | 13.52 | 22.71 |
| Scheme 2 | 76.80 | 121.90 | 73.75 | 13.62 | 22.89 |
| Scheme 3 | 81.45 | 115.37 | 60.15 | 12.85 | 21.59 |
| Scheme 4 | 79.45 | 118.69 | 70.23 | 13.42 | 22.54 |
The calculated progress score value of 4 building construction schemes.
| Scheme 1 | Scheme 2 | Scheme 3 | Scheme 4 | |
|---|---|---|---|---|
|
| 0.98 | 0.96 | 0.98 | 0.97 |
|
| 0.92 | 0.93 | 0.94 | 0.95 |
|
| 0.97 | 0.95 | 0.86 | 0.95 |
|
| 0.87 | 0.86 | 0.92 | 0.98 |
|
| 0.99 | 0.87 | 0.95 | 0.95 |
|
| 0.96 | 0.91 | 0.89 | 0.88 |
|
| 0.89 | 0.97 | 0.97 | 0.93 |
|
| 0.95 | 0.94 | 0.97 | 0.94 |
|
| 0.92 | 0.98 | 0.86 | 0.89 |
|
| 0.93 | 0.91 | 0.94 | 0.93 |
|
| 0.99 | 0.98 | 0.89 | 0.92 |
|
| 0.98 | 0.92 | 0.99 | 0.89 |
|
| 0.88 | 0.97 | 0.97 | 0.99 |
|
| 0.98 | 0.87 | 0.95 | 0.91 |
|
| 0.94 | 0.95 | 0.92 | 0.98 |
|
| 0.97 | 0.88 | 0.92 | 0.87 |
|
| 0.91 | 0.86 | 0.94 | 0.87 |
|
| 0.89 | 0.91 | 0.91 | 0.92 |
|
| 0.92 | 0.87 | 0.96 | 0.98 |
|
| 0.89 | 0.89 | 0.88 | 0.96 |
|
| 0.92 | 0.94 | 0.91 | 0.87 |
|
| 0.97 | 0.85 | 0.90 | 0.96 |
|
| 0.88 | 0.98 | 0.94 | 0.87 |
|
| 0.85 | 0.91 | 0.87 | 0.91 |
|
| 0.98 | 0.94 | 0.86 | 0.92 |
|
| 0.89 | 0.95 | 0.86 | 0.86 |
|
| 0.99 | 0.91 | 0.91 | 0.92 |
|
| 0.86 | 0.88 | 0.87 | 0.96 |
|
| 0.98 | 0.96 | 0.89 | 0.98 |
|
| 0.92 | 0.88 | 0.90 | 0.92 |
|
| 0.91 | 0.91 | 0.90 | 0.95 |
|
| 0.90 | 0.93 | 0.88 | 0.95 |
|
| 0.88 | 0.95 | 0.91 | 0.94 |
|
| 0.92 | 0.86 | 0.90 | 0.85 |
|
| 0.89 | 0.91 | 0.91 | 0.85 |
|
| 0.92 | 0.88 | 0.94 | 0.88 |
|
| 0.88 | 0.90 | 0.86 | 0.96 |
|
| 0.86 | 0.93 | 0.96 | 0.99 |
|
| 0.89 | 0.95 | 0.95 | 0.86 |
|
| 0.89 | 0.87 | 0.96 | 0.88 |
|
| 0.85 | 0.85 | 0.89 | 0.98 |
|
| 0.93 | 0.94 | 0.98 | 0.91 |
|
| 0.94 | 0.97 | 0.91 | 0.89 |
|
| 0.98 | 0.88 | 0.93 | 0.86 |
The calculated quality score value of 4 building construction schemes.
| Scheme 1 | Scheme 2 | Scheme 3 | Scheme 4 | |
|---|---|---|---|---|
|
| 0.97 | 0.92 | 0.96 | 0.90 |
|
| 0.93 | 0.91 | 0.98 | 0.93 |
|
| 0.99 | 0.91 | 0.97 | 0.96 |
|
| 0.92 | 0.94 | 0.98 | 0.96 |
|
| 0.93 | 0.97 | 0.97 | 0.98 |
|
| 0.95 | 0.93 | 0.94 | 0.99 |
|
| 0.94 | 0.99 | 0.91 | 0.93 |
|
| 0.91 | 0.97 | 0.96 | 0.92 |
|
| 0.91 | 0.94 | 0.96 | 0.96 |
|
| 0.94 | 0.96 | 0.96 | 0.98 |
|
| 0.92 | 0.97 | 0.93 | 0.90 |
|
| 0.98 | 0.97 | 0.97 | 0.91 |
|
| 0.91 | 0.98 | 0.92 | 0.92 |
|
| 0.95 | 0.90 | 0.97 | 0.93 |
|
| 0.92 | 0.92 | 0.91 | 0.97 |
|
| 0.95 | 0.91 | 0.91 | 0.97 |
|
| 0.91 | 0.96 | 0.96 | 0.90 |
|
| 0.95 | 0.93 | 0.98 | 0.95 |
|
| 0.94 | 0.98 | 0.98 | 0.92 |
|
| 0.92 | 0.97 | 0.97 | 0.93 |
|
| 0.92 | 0.94 | 0.98 | 0.95 |
|
| 0.93 | 0.94 | 0.93 | 0.96 |
|
| 0.90 | 0.92 | 0.91 | 0.94 |
|
| 0.96 | 0.96 | 0.95 | 0.91 |
|
| 0.94 | 0.98 | 0.96 | 0.96 |
|
| 0.97 | 0.94 | 0.91 | 0.93 |
|
| 0.90 | 0.94 | 0.92 | 0.97 |
|
| 0.96 | 0.98 | 0.96 | 0.94 |
|
| 0.92 | 0.92 | 0.93 | 0.98 |
|
| 0.90 | 0.93 | 0.92 | 0.94 |
The calculated safety score value of 4 building construction schemes.
| Schemes | Scheme 1 | Scheme 2 | Scheme 3 | Scheme 4 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Risk degree indexes |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 5 | 8 | 3 | 8 | 5 | 5 | 6 | 5 | 3 | 1 | 5 | 3 |
|
| 8 | 3 | 2 | 4 | 1 | 7 | 5 | 8 | 2 | 5 | 7 | 2 |
|
| 6 | 1 | 5 | 8 | 6 | 3 | 4 | 4 | 3 | 2 | 8 | 3 |
|
| 8 | 1 | 1 | 7 | 6 | 4 | 8 | 4 | 2 | 9 | 2 | 3 |
|
| 2 | 6 | 3 | 6 | 3 | 9 | 3 | 7 | 6 | 6 | 8 | 5 |
|
| 5 | 4 | 5 | 4 | 3 | 3 | 1 | 5 | 7 | 7 | 3 | 1 |
|
| 5 | 6 | 7 | 5 | 3 | 3 | 2 | 5 | 2 | 1 | 5 | 8 |
|
| 5 | 5 | 9 | 7 | 6 | 4 | 4 | 7 | 7 | 5 | 5 | 5 |
|
| 5 | 7 | 7 | 8 | 3 | 8 | 7 | 4 | 5 | 1 | 8 | 6 |
|
| 6 | 5 | 4 | 5 | 2 | 3 | 5 | 6 | 5 | 3 | 7 | 9 |
|
| 8 | 6 | 2 | 2 | 9 | 1 | 1 | 3 | 1 | 5 | 3 | 8 |
|
| 8 | 9 | 4 | 9 | 4 | 7 | 4 | 1 | 9 | 5 | 8 | 4 |
|
| 8 | 6 | 5 | 2 | 1 | 5 | 4 | 9 | 4 | 9 | 1 | 9 |
|
| 2 | 8 | 4 | 8 | 7 | 2 | 8 | 8 | 4 | 8 | 1 | 3 |
|
| 6 | 6 | 1 | 9 | 7 | 2 | 3 | 7 | 6 | 8 | 6 | 3 |
|
| 5 | 8 | 3 | 8 | 5 | 4 | 2 | 6 | 8 | 3 | 4 | 9 |
|
| 5 | 6 | 3 | 8 | 3 | 7 | 6 | 7 | 2 | 9 | 7 | 7 |
|
| 5 | 8 | 1 | 6 | 2 | 1 | 5 | 4 | 9 | 2 | 8 | 9 |
|
| 1 | 3 | 8 | 7 | 2 | 8 | 6 | 8 | 2 | 2 | 1 | 5 |
|
| 8 | 3 | 2 | 2 | 3 | 6 | 5 | 6 | 9 | 7 | 4 | 9 |
|
| 1 | 5 | 9 | 8 | 3 | 2 | 1 | 2 | 5 | 7 | 7 | 8 |
|
| 6 | 7 | 7 | 3 | 1 | 2 | 5 | 5 | 8 | 8 | 5 | 4 |
The calculated total value of 4 indexes including cost, progress, quality, and safety of 4 building construction schemes.
| Cost | Progress | Quality | Safety | |
|---|---|---|---|---|
| Scheme 1 | 306.58 | 0.192 | 0.233 | 2527.00 |
| Scheme 2 | 308.96 | 0.173 | 0.291 | 2233.00 |
| Scheme 3 | 291.40 | 0.203 | 0.368 | 2450.00 |
| Scheme 4 | 304.33 | 0.172 | 0.260 | 2886.00 |
The standardization result of 4 building construction schemes based on 4 decision indexes.
| Cost | Progress | Quality | Safety | |
|---|---|---|---|---|
| Scheme 1 | 0.136 | 0.645 | 0.001 | 0.55 |
| Scheme 2 | 0.001 | 0.032 | 0.430 | 1.00 |
| Scheme 3 | 1.000 | 1.000 | 1.000 | 0.67 |
| Scheme 4 | 0.264 | 0.001 | 0.200 | 0.01 |
The calculated entropy value and entropy weight of 4 schemes.
| Indexes | Cost | Progress | Quality | Safety |
|---|---|---|---|---|
| Entropy value ( | 0.678 | 0.567 | 0.873 | 0.413 |
| Entropy weighs ( | 0.219 | 0.295 | 0.087 | 0.400 |