Iraj Mohammadfam1, Gebraeil Nasl Saraji, Ali Kianfar, Shahram Mahmoudi.
Abstract
Quality and efficiency are important issues in management systems. To increase quality, to reach best results, to move towards the continuous improvement of system and also to make the internal and external customers satisfied, it is necessary to consider the system performance measurement. In this study the Health, Safety and Environment Excellence Instrument was represented as a performance measurement tool for a wide range of health, safety and environment management systems. In this article the development of the instrument overall structure, its parts, and its test results in three organizations are presented. According to the results, the scores ranking was the managership organization, the manufacturing company and the powerhouse construction project, respectively. The results of the instrument test in three organizations show that, on the whole, the instrument has the ability to measure the performance of health, safety and environment management systems in a wide range of organizations.Entities:
Year: 2013 PMID: 23369610 PMCID: PMC3561110 DOI: 10.1186/1735-2746-10-7
Source DB: PubMed Journal: Iranian J Environ Health Sci Eng ISSN: 1735-1979
Figure 1The HSEEI scheme.
Number of sub-parts and guidance points in HSEEI
| Leadership | 8 | 93 |
| Policy and strategy | 5 | 43 |
| People management | 6 | 60 |
| Resources | 7 | 54 |
| Processes | 4 | 29 |
| Customer and society results | 2 | 43 |
| People results | 2 | 36 |
| Contractor results | 2 | 33 |
| Key performance results | 2 | 19 |
Figure 2The structure of the measurement in HSEEI.
Results of the third party audit
| Leadership | 25.7 | 31.25 | 34.5 | 100 |
| Policy & strategy | 26.52 | 39.33 | 41.33 | 80 |
| People management | 21.8 | 32.77 | 26.6 | 90 |
| Resources | 21.34 | 18.33 | 24.34 | 90 |
| Processes | 25.42 | 35.41 | 41.17 | 140 |
| Total score in enablers | 120.86 | 157.09 | 167.94 | 500 |
| Customer & society results | 31.25 | 28.75 | 33.8 | 100 |
| People results | 21.87 | 28.12 | 31.2 | 150 |
| Contractor results | 28.12 | 31.25 | 29.72 | 100 |
| Key performance results | 31.25 | 34.37 | 41.27 | 150 |
| Total score in results | 112.49 | 122.49 | 135.99 | 500 |
| Total score (enablers + results) | 233.35 | 279.58 | 303.93 | 1000 |