Synnøve Thomassen Andersen1, Arild Jansen.
Abstract
The paper addresses an ICT-based, user-driven innovation process in the health sector in rural areas in Norway. The empirical base is the introduction of a new model for psychiatric health provision. This model is supported by a technical solution based on mobile phones that is aimed to help the communication between professional health personnel and patients. This innovation was made possible through the use of standard mobile technology rather than more sophisticated systems. The users were heavily involved in the development work. Our analysis shows that by thinking simple and small-scale solutions, including to take the user's needs and premises as a point of departure rather than focusing on advanced technology, the implementation process was made possible. We show that by combining theory on information infrastructures, user-oriented system development, and innovation in a three-layered analytical framework, we can explain the interrelationship between technical, organizational, and health professional factors that made this innovation a success.Entities:
Year: 2012 PMID: 23304134 PMCID: PMC3523133 DOI: 10.1155/2012/673731
Source DB: PubMed Journal: Int J Telemed Appl ISSN: 1687-6415
Research framework.
| Analytic level | Focus in the analysis | Critical factors/processes |
|---|---|---|
| Organizational level: health service provision and so forth. | Identifying the organizational changes processes and reform(s) in the psychiatric health service provisions that have taken place, including changes in work patterns, relations between professionals and the user, and furthermore, institutional and professional interests and conflicts. | Context: institutional variables, |
| The application development and user level | Identifying and understanding all phases in the system development process and how they involved various user groups which had different background, experience, and interests in the this work | System development approaches and phases. |
| Information infrastructure level (II) | Understanding the specific characteristics of the different II and their installed base; how they influenced the change processes at different levels (technical, organisational). More specifically: what made it possible to move from an old to a new II? | Characteristics of the two II/IB. |
Data collections methods used.
| Methods | Type of activities | Total | |||
|---|---|---|---|---|---|
| 2006 | 2007 | 2008 | |||
| Observation (during participation in meetings) | 3 project teams | 7 project teams | 4 project teams | other | 63 |
| Observation (user courses) | 3 observations | 3 | |||
| Interviews | 12 from ambulant teams | 4 user representatives | 16 | ||
| Questionnaire | 2 questionnaire | 2 | |||
| Literature | Project documents | Meeting notes, e-mail, and reports | user-training notes, workshop documentation | Other documents | <100 |
Figure 1Project organization.
Figure 2Schematic description of the new solution.
Figure 3Examples of the user interfaces and interaction sequences.
Stakeholders, phases, and roles in the system development work.
| Stakeholders | The different phases and roles in the system developing work | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| Analyze, | Choice of | Design | Choice of technology | Testing | Implement- | Courses | Course | Evaluating | |
| Children and youth | X | ||||||||
| Parents | X | X | X | X | X | X | X | ||
| Ambulant team | X | X | X | X | X | X | X | X | X |
| CYP leaders | X | X | X | X | X | X | X | ||
| Clinic superior | X | X | X | X | X | ||||
| Health enterprise leaders | X | X | |||||||
| Project group | X | X | X | X | X | X | X | X | X |
| Steering group | X | X | X | X | X | X | |||
| Reference group | X | X | |||||||
| Techno group | X | ||||||||
| User organizations | X | X | X | X | X | X | X | X | X |
| Regional ICT unit | X | ||||||||
| Local ICT unit | X | ||||||||
| Supplier | X | X | X | ||||||
| Superior for purchase | X | ||||||||
| Service workers in the community | X | X | |||||||
Figure 4Project milestones.
Framework for old and new regime/technical and organisational model.
| Model | ||||
|---|---|---|---|---|
| Level | Old regime/technical and organizational model | New regime: technical and organizational model | ||
| Old organisational structure | Old system development model | New organisational structure | New system development model | |
| Changes in organization and health service provision | Centralized treatment model | Traditional SU methodology: | PMT-O: decentralized | Local, user-oriented, incremental and experimental system |
| Development of the applications | Application based on PC and videoconferences | Application based on mobile phone | ||
| Infrastructure | II/IB: based on Broadband Norw. Health Network | Mobile telephone network. Establishment of local techno group | ||