| Literature DB >> 15738926 |
Abstract
We have recently commissioned a temporary radiation therapy facility that is novel in two aspects: it was constructed using modular components, and the LINAC was installed in one of the modular sections before it was lifted into position. Additional steel and granular fill was added to the modular sections on-site during construction. The building will be disassembled and removed when no longer needed. This paper describes the radiation shielding specifications and survey of the facility, as well as the ramifications for acceptance testing occasioned by the novel installation procedure. The LINAC is a Varian 21EX operating at 6 MV and 18 MV. The radiation levels outside the vault satisfied the design criteria, and no anomalous leakage was detected along the joints of the modular structure. At 18 MV and 600 monitor units (MU) per minute, the radiation level outside the primary barrier walls was 8.5 micro Sv/h of photons; there were no detectable neutrons. Outside the direct-shielded door, the levels were 0.4 micro Sv/h of photons and 3.0 micro Sv/h of neutrons. The isocentricity of the accelerator met the acceptance criteria and was not affected by its preinstallation into an integrated baseframe and subsequent transport to the building site.Entities:
Mesh:
Year: 2004 PMID: 15738926 PMCID: PMC5723524 DOI: 10.1120/jacmp.v5i4.2025
Source DB: PubMed Journal: J Appl Clin Med Phys ISSN: 1526-9914 Impact factor: 2.102
Figure 1Schematic of modular layout. Solid lines represent the 10 modules that comprise the vault. Dashed lines represent the modules that provide the ancillary work areas.
Figure 2Plan view of structure. Solid lines are finished walls; light gray dashed lines represent boundaries of modular sections; dash‐dot lines represent beam limits. The area designations correspond to Table 1.
Design summary for the radiation barriers, assuming full use at 18 MV and with the workloads described in the text. The “use factor” refers to the fraction of the time the beam is directed at the barrier. For the calculation based on limits per hour, the use factor is taken to be one, and the “duty factor” refers to the fraction of one hour that the beam may be on. The required meters of concrete (or equivalent) is given for the limiting case, using tenth‐value layers as described in the text.
| Barrier ID | Location | Barrier type | Area type | Workload period | Limit (μSv) | Use factor | Occup. factor | Duty factor | Trans. factor | Meters o concrete |
|---|---|---|---|---|---|---|---|---|---|---|
| P1, P2 | side walls | 1° | uncontrolled | per week | 1000 |
|
| 2.69E‐05 | ||
| per hour (TBI) | 20 | 1 | 1 |
| 1.40E‐05 | |||||
| per hour (continuous) | 20 | 1 | 1 | 1 | 2.80E‐06 | 2.47 | ||||
| P1a, P2a | above 3.2 m | 1° | uncontrolled | per week | 1000 |
|
| 1.34E‐04 | 1.76 | |
| per hour | 20 | 1 | 1 | 0.025 | 1.12E‐04 | |||||
| P3 | roof | 1° | controlled | per hour | 1000 | 1 | 1 |
| 2.57E‐04 | 1.60 |
| S1 | front wall | 2° | controlled | per week | 100 | 1 | 1 | 1.37E‐03 | 1.13 | |
| S1a | door | 2° | controlled | per week | 100 | 1 | 1 | 1.37E‐03 | 1.13 | |
| S2 | back wall | 2° | uncontrolled | per week | 20 | 1 |
| 1.13E‐03 | 1.16 | |
| S3,4 | side walls | 2° | uncontrolled | per week | 20 | 1 |
| 2.23E‐03 | 1.09 | |
| S5 | roof | 2° | uncontrolled | per week | 20 | 1 |
| 3.48E‐03 | ||
| per hour | 20 | 1 | 1 |
| 2.29E‐03 | 1.04 |
TBI = total body irradiation.
Radiation barriers, design limits, and measured values for dose equivalent rates with the accelerator producing 18 MV at 600 MU/min. These rates are for the worst‐case irradiation condition (e.g., for a primary barrier, the beam is directed at the barrier). The design limit is the predicted total dose equivalent rate for the barrier using the limiting transmission factor from Table 1.
| Barrier ID | Location | Design limit | Measured photons | Measured neutrons | Total |
|---|---|---|---|---|---|
| P1, P2 | side walls | 20 | 8.5 |
|
|
| P1a, P2a | above 3.2 m | 800 | 300 |
| 300 |
| P3 | roof | 4000 | 2200 | 40 | 2240 |
| S1 | front wall | 24 | 0.1 | 2.0 | 2.1 |
| S1a | door | 24 | 0.4 | 3.0 | 3.4 |
| S2 | back wall | 19 | 0.3 |
|
|
| S3, 4 | side walls | 19 | 1.7 |
|
|
| S5 | roof | 80 | 25 |
| 25 |
Figure 3The central module with the LINAC being lifted into position